Subject Name & Code Advance Construction Techniques 3 CEN 102 Student Name Dwij Vipulkumar Jani Deep Narsinhbhai Patel Enrollment Number
Subject Name & Code Advance Construction Techniques 3 CEN 102 Student Name Dwij Vipulkumar Jani Deep Narsinhbhai Patel Enrollment Number
Subject Name & Code Advance Construction Techniques 3 CEN 102 Student Name Dwij Vipulkumar Jani Deep Narsinhbhai Patel Enrollment Number
Declaration of originality:
We hereby declare that the report submitted by us is an outcome of our teamwork and
original work. We have duly acknowledged all the sources from which the ideas and
extracts have been taken. The report is free from any plagiarism, and we take full
responsibility of the content of this report.
BACKGROUND
Project Details
Our project shree Ananta is located at the hadiyol Road,
Himatnagar, Gujarat.
Area of the residential area is 3 Acres.
III
1) INTRODUCTION ABOUT JOB LAYOUT
Safety:
Site Accessibility
Information Signs
Security
Accommodation
Offices
Water Supply and Sanitation
Material Handling
Storage and site cleaning
Craft Change-Houses
Batch plant and Fabrication Shops
Labor colony at the site
Engineers and contractor office
V
1) Bar bending shop
2) Fabricated rebar storage yard
Group 6
1) Testing lab
2) Material storage lab
Group 7
1) Equipment maintenance room
2) Parking for machines
Group 8
1) Canteen
2) Toilet on site.
Others
1) Internal Road
2) Electric Poles.
2)
VI
Purpose of job layout
VII
2) GENERAL INFORMATION ABOUT SITE
Amenities:
VIII
Compound wall
C.C Road
Led street lights
Garden and common plot
Under ground GEB cables
Attractive entry gate with security cabin
Water facility 24 hours
CCTV Camera
IX
1) Safety:
Fire prevention Fire is a major causes of the damage on
construction sites. So that fire extingunishes are basic
requirement in aconstruction project.
2) Site accessibility:
Easy accessibility will keep the morals of the equipment
and vehicle drivers higt, minimize the chance of the
accident and save the time in th emaneuvering o the
arrive at an dleavers the project.
In case of the large projects, proper planning is required
to layout the roads leading from the nearest highway.
Internak road are necessary for easy flow of work.
Also parking lots are provided for the owner, office, and
crafts personnel but this facility must be planned where
space does exist.
3) Information sign:
Site map: It should locate details of the project, and displayed in the
office of the site superintendent or project manager and posted at the
entrance gate.
Traffice regulatory sign: For large projects, traffic regulatory signs help in
guiding the traffic on the site and avoid accidents to a considerable
extent.
Display of the labours policy and safety rules: This will help in eliminating
disputes between labor and management.
Emergency routers and underground services: It is important to display
the emergency escape routes on every floor as the building progresses.
Locations of underground services should be marked to prevent its
damage.
X
4)Security:
Enterance it is necessary to have guard entrance to the site provided
by a booth. Also it is necessary to keep track of all visitiors to the
project.
Lighting it is necessary to have standby generator to maintainsite
lighting.
Fencing the boundary should be fenced off from a security point of
view.
5)Accommodation:
On the large construction it is necessary to provide camp
accommodation for all type of staff innvolved in yhe project.
6)Offices:
The office should be closs together close to the site and in a safe
area. Also provide office equipment. The office at the site may
include job office, general contractor office, sub-contractor and
consultant offices.
8) Material handeling:
One third or more of all construction operations can be classified
as material handeling. The use of the proper equipment for the
material handeling and advanceplanning for minizing handling will
results in direct cost and time savings.
XI
Laydown areas Areas reservd for Storage of the large material and
equipment and it can be short term or long term.
Warehouse: They are shelted storage facilites where materials are
stored until they have disbursed to the job.
Materials staging area: They used when materials are stored near the
work on a short term basis. They are generally as close to work as
possible.
Site cleaning: It is necessary at a work place and espicially where the
extent of debries produced is high. Regular disposal of debries is
necessary.
XII
varios projects in remote areas and highly experienced with the
necessary technical experiences.
Material position:
It is very important to un load the material to the
nearist and at the centre of the site, so the labours
are commonly used the material and easy to work,
that can save the time of constructio.
For the material we provide the steel yard, cement
storage, aggregate storage and also when some
emergency the storage full then we also unload the
material to the emergency storage.
Steel position:
Steel is very important in the construction
work so, we stored the steel at maximum
numbers and we stored in the steel yard.
For the cutting of bar. we provide the steel
working unit from the 10mt from the steel
yard.
XIII
Steel storage is at the centre of the
construction site so that labours are easily
used.
Labor colony:
Labor colony for onsite labors, staff, site office
as per given site location.
The size is decided so that after the
construction is over we can dismantle.
AREA:
XIV
F.S.I:
Permissible F.S.I ( 1.1) = 12140.569sqm
Utilized F.S.I = 12140sqm
Traffic situation:
This traffic survey is done by the morning 8 to 10 am and
evening 5 to 6 pm.
XV
DISTANCE FROM MAJORITY WANDORS:
The average distance from site to the wandors is about
2 to 2.5km.
XVI
XVII
XVIII
XIX
XX
Labor colony:
XXI
XXII
Discussing with site engineer:
XXIII
XXIV
XXV
XXVI
XXVII
XXVIII
XXIX
XXX
XXXI
XXXII
XXXIII