Professional Documents
Culture Documents
Project Management For Construction - Construction Pricing and Contracting
Project Management For Construction - Construction Pricing and Contracting
Go To Chapter 7 Go To Chapter 9
(Financing of Constructed Facilities) (Construction Planning)
Construction Pricing and Contracting
Pricing for Constructed Facilities
Contract Provisions for Risk Allocation
Risks and Incentives on Construction Quality
Types of Construction Contracts
Relative Costs of Construction Contracts
Principles of Competitive Bidding
Principles of Contract Negotiation
Negotiation Simulation: An Example
Resolution of Contract Disputes
References
Problems
Footnotes
Competitive Bidding
The basic structure of the bidding process consists of the formulation of detailed
plans and
specifications of a facility based on the objectives and requirements of the
owner, and the
invitation of qualified contractors to bid for the right to execute the
project. The definition
of a qualified contractor usually calls for a minimal evidence of
previous experience and
financial stability. In the private sector, the owner has
considerable latitude in selecting the
bidders, ranging from open competition to the
restriction of bidders to a few favored
contractors. In the public sector, the rules are
carefully delineated to place all qualified
contractors on an equal footing for
competition, and strictly enforced to prevent collusion
among contractors and unethical or
illegal actions by public officials.
Negotiated Contracts
Generally, negotiated contracts require the reimbursement of direct project cost plus
the
contractor's fee as determined by one of the following methods:
The fixed percentage or fixed fee is determined at the outset of the project, while
variable
fee and target estimates are used as an incentive to reduce costs by sharing any
cost savings.
A guaranteed maximum cost arrangement imposes a penalty on a contractor for
cost
overruns and failure to complete the project on time. With a guaranteed maximum price
contract, amounts below the maximum are typically shared between the owner and the
contractor, while the contractor is responsible for costs above the maximum.
Force-Account Construction
Some owners use in-house labor forces to perform a substantial amount of construction,
particularly for addition, renovation and repair work. Then, the total of the
force-account
charges including in-house overhead expenses will be the pricing arrangement
for the
construction.
Back to top
Force majeure (i.e., this provision absolves an owner or a contractor for payment for
costs due to "Acts of God" and other external
events such as war or labor strikes)
Indemnification (i.e., this provision absolves the indemified party from any payment
for losses and damages incurred by a third party such as adjacent property owners.)
Liens (i.e., assurances that third party claims are settled such as "mechanics
liens" for
worker wages),
Labor laws (i.e., payments for any violation of labor laws and regulations on the job
site),
Differing site conditions (i.e., responsibility for extra costs due to unexpected site
conditions),
Delays and extensions of time,
Liquidated damages (i.e., payments for any facility defects with payment amounts
agreed
to in advance)
Consequential damages (i.e., payments for actual damage costs assessed upon impact
of
facility defects),
Occupational safety and health of workers,
Permits, licenses, laws, and regulations,
Equal employment opportunity regulations,
Termination for default by contractor,
Suspension of work,
Warranties and guarantees.
The language used for specifying the risk assignments in these areas must conform to
legal
requirements and past interpretations which may vary in different jurisdictions or
over
time. Without using standard legal language, contract provisions may be
unenforceable.
Unfortunately, standard legal language for this purpose may be difficult to
understand. As a
result, project managers often have difficulty in interpreting their
particular
responsibilities. Competent legal counsel is required to advise the different
parties to an
agreement about their respective responsibilities.
Standard forms for contracts can be obtained from numerous sources, such as the
American
Institute of Architects (AIA) or the Associated General Contractors (AGC). These
standard
forms may include risk and responsibility allocations which are unacceptable to
one or
more of the contracting parties. In particular, standard forms may be biased to
reduce the
risk and responsibility of the originating organization or group. Parties to a
contract should
read and review all contract documents carefully.
The three examples appearing below illustrate contract language resulting in different
risk
assignments between a contractor (CONTRACTOR) and an owner (COMPANY). Each contract
provision allocates different levels of indemnification risk to the contractor. [1]
Comment: This is a very burdensome provision for the contractor. It makes the
contractor
responsible for practically every conceivable occurrence and type of damage,
except when a
claim for loss or damages is due to the sole negligence of the owner.
As a practical matter,
sole negligence on a construction project is very difficult to
ascertain because the work is so
inter-twined. Since there is no dollar limitation to the
contractor's exposure, sufficient
liability coverage to cover worst scenario risks will be
difficult to obtain. The best the
contractor can do is to obtain as complete and broad
excess liability insurance coverage as
can be purchased. This insurance is costly, so the
contractor should insure the contract price
is sufficiently high to cover the expense.
Back to top
Many public owners have been the victims of their own schemes, not only because of the
usual requirement in letting contracts of public works through competitive bidding to
avoid
favoritism, but at times because of the sheer weight of entrenched bureaucracy. Some
contractors steer away from public works altogether; others submit bids at higher prices
to
compensate for the restrictive provisions of contract terms. As a result, some public
authorities find that either there are few responsible contractors responding to their
invitations to submit bids or the bid prices far exceed their engineers' estimates. Those
public owners who have adopted the federal government's risk sharing/risk assignment
contract concepts have found that while initial bid prices may have decreased somewhat,
claims and disputes on contracts are more frequent than before, and notably more so than
in privately funded construction. Some of these claims and disputes can no doubt be
avoided by improving the contract provisions. [2]
Since most claims and disputes arise most frequently from lump sum contracts for both
public and private owners, the following factors associated with lump sum contracts are
particularly noteworthy:
unbalanced bids in unit prices on which periodic payment estimates are based.
change orders subject to negotiated payments
changes in design or construction technology
incentives for early completion
An unbalanced bid refers to raising the unit prices on items to be completed in the
early
stage of the project and lowering the unit prices on items to be completed in the
later stages.
The purpose of this practice on the part of the contractor is to ease its
burden of
construction financing. It is better for owners to offer explicit incentives to
aid construction
financing in exchange for lower bid prices than to allow the use of
hidden unbalanced bids.
Unbalanced bids may also occur if a contractor feels some item of
work was underestimated
in amount, so that a high unit price on that item would increase
profits. Since lump sum
contracts are awarded on the basis of low bids, it is difficult to
challenge the low bidders on
the validity of their unit prices except for flagrant
violations. Consequently remedies should
be sought by requesting the contractor to submit
pertinent records of financial transactions
to substantiate the expenditures associated
with its monthly billings for payments of work
completed during the period.
One of the most contentious issues in contract provisions concerns the payment for
change
orders. The owner and its engineer should have an appreciation of the effects of
changes for
specific items of work and negotiate with the contractor on the identifiable
cost of such
items. The owner should require the contractor to submit the price quotation
within a
certain period of time after the issuance of a change order and to assess whether
the change
order may cause delay damages. If the contract does not contain specific
provisions on cost
disclosures for evaluating change order costs, it will be difficult to
negotiate payments for
change orders and claim settlements later.
In some projects, the contract provisions may allow the contractor to provide
alternative
design and/or construction technology. The owner may impose different
mechanisms for
pricing these changes. For example, a contractor may suggest a design or
construction
method change that fulfills the performance requirements. Savings due to such
changes
may accrue to the contractor or the owner, or may be divided in some fashion
between the
two. The contract provisions must reflect the owners risk-reward objectives in
calling for
alternate design and/or construction technology. While innovations are often
sought to save
money and time, unsuccessful innovations may require additional money and
time to
correct earlier misjudgment. At worse, a failure could have serious consequences.
In spite of admonitions and good intentions for better planning before initiating a
construction project, most owners want a facility to be in operation as soon as possible
once
a decision is made to proceed with its construction. Many construction contracts
contain
provisions of penalties for late completion beyond a specified deadline; however,
unless
such provisions are accompanied by similar incentives for early completion, they
may be
ruled unenforceable in court. Early completion may result in significant savings,
particularly in rehabilitation projects in which the facility users are inconvenienced by
the
loss of the facility and the disruption due to construction operations.
A 1986 court case can illustrate the assumption of risk on the part of contractors
and
design professionals. [3] The Arkansas Rice Growers Cooperative contracted
with
Alchemy Industries, Inc. to provide engineering and construction services
for a new
facility intended to generate steam by burning rice hulls. Under the
terms of the
contract, Alchemy Industries guaranteed that the completed plant
would be capable of
"reducing a minimum of seven and one-half tons of rice hulls
per hour to an ash and
producing a minimum of 48 million BTU's per hour of
steam at 200 pounds pressure."
Unfortunately, the finished plant did not meet this
performance standard, and the Arkansas
Rice Growers Cooperative Association
sued Alchemy Industries and its subcontractors for
breach of warranty. Damages
of almost $1.5 million were awarded to the Association.
Back to top
In a lump sum contract, the owner has essentially assigned all the risk to the
contractor,
who in turn can be expected to ask for a higher markup in order to take care
of unforeseen
contingencies. Beside the fixed lump sum price, other commitments are often
made by the
contractor in the form of submittals such as a specific schedule, the
management reporting
system or a quality control program. If the actual cost of the
project is underestimated, the
underestimated cost will reduce the contractor's profit by
that amount. An overestimate has
an opposite effect, but may reduce the chance of being a
low bidder for the project.
In a unit price contract, the risk of inaccurate estimation of uncertain quantities for
some
key tasks has been removed from the contractor. However, some contractors may submit
an
"unbalanced bid" when it discovers large discrepancies between its estimates
and the
owner's estimates of these quantities. Depending on the confidence of the
contractor on its
own estimates and its propensity on risk, a contractor can slightly
raise the unit prices on
the underestimated tasks while lowering the unit prices on other
tasks. If the contractor is
correct in its assessment, it can increase its profit
substantially since the payment is made
on the actual quantities of tasks; and if the
reverse is true, it can lose on this basis.
Furthermore, the owner may disqualify a
contractor if the bid appears to be heavily
unbalanced. To the extent that an
underestimate or overestimate is caused by changes in
the quantities of work, neither
error will effect the contractor's profit beyond the markup in
the unit prices.
For certain types of construction involving new technology or extremely pressing needs,
the
owner is sometimes forced to assume all risks of cost overruns. The contractor will
receive
the actual direct job cost plus a fixed percentage, and have little incentive to
reduce job cost.
Furthermore, if there are pressing needs to complete the project,
overtime payments to
workers are common and will further increase the job cost. Unless
there are compelling
reasons, such as the urgency in the construction of military
installations, the owner should
not use this type of contract.
For this type of contract, the contractor agrees to a penalty if the actual cost
exceeds the
estimated job cost, or a reward if the actual cost is below the estimated job
cost. In return
for taking the risk on its own estimate, the contractor is allowed a
variable percentage of the
direct job-cost for its fee. Furthermore, the project duration
is usually specified and the
contractor must abide by the deadline for completion. This
type of contract allocates
considerable risk for cost overruns to the owner, but also
provides incentives to contractors
to reduce costs as much as possible.
When the project scope is well defined, an owner may choose to ask the contractor to
take
all the risks, both in terms of actual project cost and project time. Any work change
orders
from the owner must be extremely minor if at all, since performance specifications
are
provided to the owner at the outset of construction. The owner and the contractor
agree to a
project cost guaranteed by the contractor as maximum. There may be or may not
be
additional provisions to share any savings if any in the contract. This type of
contract is
particularly suitable for turnkey operation.
Back to top
(8.1)
The underestimation of the cost of work in the original contract is defined as:
(8.2)
Then, at the completion of the project, the contractor's actual cost for the original
scope of
work is:
(8.3)
For various types of construction contracts, the contractor's markup and the price for
construction agreed to in the contract are shown in Table 8-1. Note that at the time of
contract award, it is assumed that A = E, even though the effects of underestimation on
the
contractor's gross profits are different for various types of construction contracts
when the
actual cost of the project is assessed upon its completion.
Payments of change orders are also different in contract provisions for different types
of
contracts. Suppose that payments for change orders agreed upon for various types of
contracts are as shown in column 2 of Table 8-2. The owner's actual payments based on
these provisions as well as the incentive provisions for various types of contracts are
given
in column 3 of Table 8-2. The corresponding contractor's profits under various
contractual
arrangements are shown in Table 8-3.
It is important to note that the equations in Tables 8-1 through 8-3 are illustrative,
subject to
the simplified conditions of payments assumed under the various types of
contracts. When
the negotiated conditions of payment are different, the equations must
also be modified.
(a) U = 0, C = 0
(b) U = 0, C = 6% E = $360,000
(c) U = 4% E = $240,000, C = 0
(d) U = 4% E = $240,000 C = 6% E = $360,000
(e) U = -4% E = -$240,000, C = 0
(f) U = -4% E = -$240,000, C = 6% E = $360,000
In this example, the percentage markup for the cost plus fixed percentage contract is
10%
which is used as the bench mark for comparison. The percentage markup for the lump sum
contract is 12% while that for the unit price contract is 11%, reflecting the degrees of
higher
risk. The fixed fee for the cost plus fixed fee is based on 10% of the estimated
cost, which is
comparable to the cost plus fixed percentage contract if there is no
overestimate or
underestimate in cost. The basic percentage markup is 10% for both the
cost plus variable
percentage contract and the target estimator contract, but they are
subject to incentive
bonuses and penalties that are built in the formulas for owners'
payments. The percentage
markup for the guaranteed maximum cost contract is 15% to account
for the high risk
undertaken by the contractor. The results of computation for all seven
types of contracts
under different conditions of underestimation U and change order C are
shown in Table 8-4
Using the data in Example 8-5, determine the owner's actual payment for each of the
seven
types of construction contracts for the same conditions of U and C. The results of
computation are shown in Table 8-5.