Professional Documents
Culture Documents
Gas Line Audit Final
Gas Line Audit Final
4,942
3,497
520
246
118
75
We reviewed all inspection records and eliminated any property that did
not have “reinforcing steel,” “OK to pour,” or “grade beam” in the
inspection notes. These elements would be present if a gas line would
potentially run through a grade beam. 3
Audit Process – Step 2
520 could not be confirmed to be
cased.
We compared the foundation layout and details from the approved plans with
a visual inspection to determine if a new foundation element had been poured
and if there was any chance that the gas line could run through it. 5
Audit Process – Step 4
118 were confirmed as uncased through
PG&E site visits
DBI conducted site inspections at the 246 properties to determine whether the gas
line was 1) not near new concrete, 2) through new concrete, or 3) undetermined
relative to concrete. Of PG&E’s 118 confirmed uncased properties, DBI determined
75 could have a gas line running through a new foundation element.
7
Next Steps
There are 75 properties that may have a gas line running through a grade beam.
While these have likely been protected according to code, PG&E has agreed to
upgrade service lines for all of these addresses to ensure compliance.
1. PG&E aims to complete the work by the end of 2022 – dependent on city
cooperation in order to meet that schedule
2. DBI will submit a final report to the Building Inspection Commission and the Board
of Supervisors by the end of the year
3. DBI and PG&E will collaborate on a letter to property owners in advance of any
construction activity
4. DBI agreed to facilitate any plumbing permits and inspections and work with
Public Works on any permit needed to complete the outstanding work
8
THANK YOU!