Using BOM's To Gain Planning & Scheduling Efficiencies: Jeff Smith
Using BOM's To Gain Planning & Scheduling Efficiencies: Jeff Smith
Efficiencies
Jeff Smith
Fairfax Water
Construction
type
Mat 1 Mat 3
Mat 2 Mat 6
Mat 20
Mat 7
Mat 10
Mat 11
Types of BOMs
Savings
A planned and scheduled job may be completed at ½ to ¼ the
cost of a job performed on a breakdown or emergency mode.
2,000
1,500
Equip BOMs
FLOC BOMs
1,000 Assemblies
500
0
171-01 4000 526-01 526-03 721-01 723-01 728-01 729-01
Bills of Material Created (Post Go-Live)
2,500
2,000
1,500
Equip BOMs
FLOC BOMs
1,000 Assemblies
500
0
171-01 4000 526-01 526-03 721-01 723-01 728-01 729-01
Is this a coincidence?
Is this a coincidence?
Work Center 723-01 backlog has been reduced by over 2,000
planned hours (close to half of what it was Sept 2011)