Professional Documents
Culture Documents
Project Specifications - Ca Set MT Hood Senior Living: DATE: 12/1/2021
Project Specifications - Ca Set MT Hood Senior Living: DATE: 12/1/2021
Project Specifications - Ca Set MT Hood Senior Living: DATE: 12/1/2021
DATE: 12/1/2021
1.01 SUMMARY
A Section Includes selective removal and subsequent disposal of selected flooring, drywall, electrical items,
cabinetry, ceilings, plumbing fixtures and other items.
1 Extent of demolition work is indicated on the Contract Drawings.
2 Temporary shoring.
B Related Requirements:
1 Items to be temporarily removed, salvaged, and re-used in the work.
1.02 REFERENCES
A Code of Federal Regularions (CFR)
1 Title 29 Part 1910: Occupational Safety and Health Standards
2 Title 29 Part 1926: Safety and Health Regulations for Construction
B Oregon Occupational Safety and Health Administration
1 OSHA’s Construction Rules, Division 3, Subdivision T, Demolition
1.03 ADMINISTRATIVE REQUIREMENTS
A Coordination – Coordinate demolition activities with the abatement contractor.
1.04 SUBMITTALS
A Shop Drawings: Provide shop drawings indicating the location and extent of all demolition. The shop drawings
should include the type of demolition proposed, tools proposed for use, protection for adjacent areas, and any
temporary shoring required for structural stability.
B Test and Evaluation Reports: Prior to the start of work, an engineering survey shall be made by a structural
engineer licensed in Washington State to determine the structural integrity and the possibility of unplanned
collapse of any portion of the structure. Any adjacent structure where employees may be exposed shall also be
similarly checked. A copy of the engineering report shall be provided for review prior to the start of work.
C Provide Shoring Engineering if proposed.
1.05 QUALITY ASSURANCE
A Shoring – If required, provide temporary shoring designed by a structural engineer licensed in the State of
Oregon.
PART 3 - EXECUTION
3.01 EXAMINATION
A The General Contractor is responsible, in coordination with the Owner, for verifying that the project is free of
hazardous materials, and if present for having them properly abated.
B Survey existing conditions prior to beginning on-site demolition operations. The survey must be performed by
the General Contractor.
C Identify utilities in the affected area to be disconnected and capped or moved.
D Identify items that are scheduled to remain and either be temporarily removed from the work area or sufficiently
protected to prevent damage.
E If unanticipated mechanical, electrical or structural elements are found to conflict with the intended scope of the
demolition, investigate and measure the nature and extent of the conflict and notify the architect prior to starting
work.
3.02 PREPARATION
A Schedule any utility outages with the relevant utility providers.
B Provide protective measures:
1 Provide temporary barricades around work areas.
2 Provide signage per CFR Title 29 Part 1910.
3 Provide temporary weather protection during interval between demolition and removal of existing
construction on exterior surfaces and installation of new construction to ensure no water leakage or damage
occurs to structure or interior areas of existing building.
4 Protect all adjacent elements that are to remain in place.
END OF SECTION
1.01 SUMMARY
A Section Includes cast-in-place concrete, formwork, including reinforcing steel, wire fabric, mix design, placement
procedures, accessories and finishes. Cast-in-place concrete, generally, includes all foundations and footings,
slabs-on-grade, sidewalks and patios, foundation walls, equipment pads and bases, thrust blocks and manholes.
1.02 REFERENCES
A Reference Standards
1 American Concrete Institute (ACI)
a ACI 117 – Standard Specification for Tolerances for Concrete Construction and Materials
b ACI 211.1 – Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete
c ACI 301- Specifications for Structural Concrete
d ACI 301.1R – Guide for Concrete Floor and Slab Construction
e ACI 304 – Guide for Measuring, Mixing, Transporting, and Placing Concrete.
f ACI 305 – Hot Weather Concreting
g ACI 306 – Cold Weather Concreting
h ACI 308 – Guide To Curing Concrete
i ACI 309 – Guide for Consolidation of Concrete.
j ACI 318 – Building Code Requirements for Structural Concrete
k ACI 347 – Guide to Formwork for Concrete
l ACI SP-66 – ACI Detailing Manual
2 American National Standards Institute/American Society for Testing and Materials (ANSI/ASTM)
a ANSI/ASTM A82 – Standard Specification for Steel Wire, Plain, for Concrete Reinforcement
b ANSI/ASTM A185 – Standard Specification for Steel Welded Wire Reinforcement, Plain, for
Concrete.
3 American Society for Testing and Materials (ASTM)
a ASTM A615 – Standard Specification for Deformed and Plain Carbon Steel Bars for Concrete
Reinforcement.
b ASTM A706 – Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete
Reinforcement
c ASTM 1155 - Standard Method for Determining Floor Flatness and Floor Levelness.
d ASTM C33 – Standard Specification for Concrete Aggregates
e ASTM C39 – Standard Test Method for Concrete Aggregates
f ASTM C150 – Standard Specification for Portland Cement
g ASTM C173 – Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric
Method
h ASTM C260 – Standard Specfication for Air-Entraining Admixtures in Concrete
i ASTM C618 – Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use
in Concrete.
j ASTN C881 – Standard Specification for Epoxy Resin Base Bonding Systems for Concrete
k ASTM C1059 – Standard Specification for Latex Agents for Bonding Fresh Hardened Concrete.
l ASTM D994 – Standard Specification for Pre-Formed Expansion Joint Filler for Concrete
4 Concrete Reinforcing Steel Institute (CRSI)
a CRSI –Manual of Standard Practice
b CRSI 63 – Recommended Practice for Placing Reinforcing Bars
c CRSI 65 – Recommended Practice for Placing Bar Supports, Specifications and Nomenclature
1.03 ADMINISTRATIVE REQUIREMENTS
A Coordination
1 Coordinate formwork, reinforcing and concrete pours to allow sufficient time for each activity, as well as
required inspections.
2 Coordinate any openings, sleeves or areas designated to be blocked out for future work with the placement
of reinforcing in those areas.
3 Coordinate scheduling of inspections prior to pouring concrete.
1.04 SUBMITTALS
PART 2 - PRODUCTS
2.01 PRODUCTS:
A Formwork
1 Form Materials: Contractor’s choice of standard products with sufficient strength to withstand hydrostatic
head without distortion in excess of permitted tolerances.
a Form Coating: Release agent that will not adversely affect concrete or interfere with application of
coatings.
2 Forms shall be substantial, sufficiently tight, and properly braced to prevent leakage and maintain position
and shape.
3 Forms and shoring shall not be removed until the structure has sufficient strength to support safely its
weight and all loads placed thereon.
B Concrete:
1 Provide structural grade standard weight concrete.
2 Cement: ASTM C150, Type I – Normal Portland type
3 Fine and Coarse Aggregates: ASTM C33
4 Fly Ash: ASTM C 618, Class C or F. Minimum 15% at footings and slab on grade.
5 Water-cement ratio: Comply with ACI 211.1. See Structural notes for more information.
6 Air entrainment:
a <1% for interior applications, or locations not subject to a temperature variation of more than 35
degrees F.
b 5% for exterior applications where temperature variations over 35 degrees F are expected.
C Reinforcement
1 Reinforcing Steel: ASTM A615, 60 ksi yield grade, deformed billet steel bars, plain finish.
2 Stirrup Steel: ANSI/ASTM A82, plain finish
3 Welded Steel Wire Fabric: ASTM A185 plain type.
a Mesh Size: 6x6
b Wire Gage: W 4 x W 4
4 Reinforcing Steel to be Welded: ASTM A706, 60 ksi yield grade.
D Admixtures
1 Do not use chemicals that will result in soluble chloride ions in excess of 0.1 percent by weight of concrete.
2 Air Entrainment Admixture: ASTM C260
E Bonding and Jointing Products
1 Latex Bonding Agent: Non-redispersable acrylic latex, complying with ASTM C1059 Type II.
2 Epoxy Bonding System: Complying with ASTM C881 and of Type required for specific application.
3 Waterproofing Admixture Slurry: Slurry coat of Portland Cement, sand, and crystalline waterproofing
additive, mixed with water in proportions recommended by manufacturer to achieve waterproofing at cold
joints in concrete.
4 Reglets: Formed steel sheet, galvanized, with temporary filler to prevent concrete intrusion during
placement.
5 Slab Isolation Joint Filler: ½-inch thick, height equal to slab thickness, with removable top section that will
form ½-inch deep sealant pocket after removal.
6 Joint Filler: Compressible asphalt mastic with felt facers, complying with ASTM D 994, ¼-inch thick and 4-
inches deep.
7 Slab Construction Joint Devices: Combination keyed joint form and screed, galvanized steel, with minimum
1-inch diameter holes for conduit or rebar to pass through at 6-inches on center; ribbed steel stakes for
setting.
2.02 PERFORMANCE REQUIREMENTS:
A Concrete:
PART 3 - EXECUTION
3.01 EXAMINATION
A Verification of Conditions: Visually inspect the formwork, reinforcing and other installed items to verify they are
ready to accept concrete.
B Verify dimensions, including distances to property lines, lengths of runs, locations and sizes of footings.
C Review the placement of the vapor barrier. Ensure it is continuous and free from holes, punctures, gaps or
otherwise has compromised vapor retarding capacity.
D Review the Special Inspection report on reinforcing and verify that all non-conforming conditions have been
corrected.
3.02 PREPARATION
A Adjusting Mix Design: Mix design adjustment may be requested by the Contractor when characteristics of
materials, job conditions, weather, test results, or other circumstances warrant, as accepted by the Architect.
Laboratory test data for revised mix design and strength results must be submitted to and accepted by Architect
before using in Work.
B Protection of In-Place Conditions: Take care not to damage existing concrete foundations/footings, or adjacent
framing beyond the scope of the demolition plan.
1 Where work involves cutting or drilling into existing concrete, make cuts straight and plumb to avoid over
cutting or stressing the concrete.
2 Inspect existing concrete for damage that would negatively impact the structural capacity of the concrete.
C Demolition/Removal: Cut concrete scheduled for removal cleanly to limit over removal. Use tools appropriate
for the work.
END OF SECTION
1.01 SUMMARY
A Section Includes: Materials, fabrication and erection of structural steel framing.
B Related Requirements
1 SECTION 05 40 00 – Cold Formed Metal Framing
1.02 REFERENCES
A Reference Standards: ASTM International (ASTM)
1 ASTM A36 – Specification for Carbon Structural Steel
2 ASTM A53 – Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless.
3 ASTM A123 – Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
4 ASTM A307 – Specification for Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength
5 ASTM A325 – Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile
Strength.
6 ASTM A385 – Practice for Providing High Quality Zinc Coatings (Hot Dip)
7 ASTM A490 – Specification for Heat-Treated Steel Structural Bolts, 150 ksi Minimum Tensile Strength
8 ASTM A500 – Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in
Rounds and Shapes.
9 ASTM A501 – Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing.
1.03 SUBMITTALS
A Shop Drawings: Provide complete metal shop drawings with quantities of materials, dimensions, fasteners, steel
sizes and other information necessary for a complete steel assembly.
1 Shop drawings shall be prepared by a structural engineer licensed in the state where the work will take
place.
B Erection Drawings: Provide erection drawings showing the complete installation work for structural steel.
Drawings should include temporary erection aids (bolts, clips, shims, seats, etc) required to facilitate construction.
C Delegated Design Submittals: Provide submittals for temporary shoring design, along with other construction aids
such as scaffolding, crane foundations, and other related items.
1.04 QUALITY ASSURANCE
A American Institute of Steel Construction, Inc (AISC): Manual of Steel Construction, latest edition.
B American Welding Society (AWS): Structural Welding Code, AWS D1.1
a Qualify all welders under AWS and WABO specifications for cold-formed metal welding.
C Steel Structures Painting Council (SSPC)
PART 2 - PRODUCTS
2.01 MATERIALS
A Rolled shapes and plates: ASTM A36
B W and WT Shapes: ASTM A992; Fy=50 ksi
C M, MT, S, ST, HP, C, MC and L Shapes: ASTM A36; Fy=36 ksi
D Steel Plates:
1 ASTM A36; Fy=36 ksi
2 ASTM A529; Gr 50; Fy=50 ksi
E Anchor bolts: ASTM A307, with regular series hexagonal head nuts, unless otherwise specified, hot dipped
galvanized where noted.
F Nuts and Bolts Except Anchor Bolts: ASTM A325, washers as required. Bolts connecting galvanized members
shall also be galvanized.
G Shop Paint: Manufacturer’s standard, compatible with finish coats. Refer to Section 09 90 00
H Structural Tubing (HSS): ASTM A500 (Cold Rolled), Grade C
1 Fy=50 ksi (Square, Rectangular)
2 Fy=36 ksi (Round)
I Pipe: ASTM A501, Fy=36 ksi or ASTM A53, type E or S, Grade B, Fy=35 ksi.
PART 3 - EXECUTION
Wilson Associates Architects and Planners Section 05 12 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
3.01 EXAMINATION
A Verification of Conditions: Visually inspect all areas that will receive work prior to starting. Do not start work
until all deficiencies have been corrected.
B Evaluation and Assessment: If required, evaluate existing substrates to receive work to assess their suitability for
proper installation/application of products. Proceeding with the work will be understood as acceptance of the
preexisting conditions.
3.02 ERECTION
A Connect all Members with High-Strength Bolts
1 Bearing Type Connections, Type N
a Provide ASTM A325, Type N Bolts at all locations not noted on drawings as Type SC
b Provide hardened washers conforming to ASTM F436 under elements to be tightened. Provide nuts
conforming to ASTM A563.
c Tighten Type N bearing bolts to a snug tight condition.
2 Slip Critical Connections (Type SC), for use only where noted on drawings
a Provide ASTM A325 load-indicating bolt assemblies. Install according to manufacturer’s
recommendations.
b In lieu of load-indicating bolts, provide standard type aSTM A325 SC bolts (Class A) with load-
indicating washers. Washers to conform with ASTM F959.
c Fully tension type SC Bolts.
d Remove all paint at slip critical bolt contact surfaces, or provide class A contact surface.
B Galvanized Bolts (where shown on drawings): Hot-dipped galvanized according to ASTM A153, Class C
C Anchor Rods:
1 ASTM F1554
a GR, 36; Fy=36 ksi
b GR, 105; Fy=105 ksi
2 Provide with standard washers and nuts
3 Galvanize rods (where noted on drawings) according to ASTM A153, Class C. Over-tap nuts to Class 2A
fit before galvanizing, according to ASTM A563.
D Provide beveled washers at bolt heads or nuts bearing on sloping surfaces.
E Welding:
1 Conform with AWS Specifications
2 Welders to be qualified under AWS and WABO specifications
3 Welds material: 70 ksi filler metal, unless noted otherwise. Provide low-hydrogen filler metals at moment
frame welds.
a At demand critical welds (DCW), welds shall be made with filler metals meeting the requirements
specified in AWS D1.8 clause 6.3, with minimum mechanical properties as follows:
1) 58 ksi yield strength
2) 70 ksi tensile strength
3) 22-percent elongation
4) 20 ft-lb CVN toughness at 70-degrees F
b In addition, all DCW are to be made with filler metals receiving heat input envelope testing that will
achieve the following mechanical properties in the weld metal:
1) 58 ksi yield strength
2) 70 ksi tensile strength
3) 22-percent elongation
4) 40 ft-lb CVN toughness at 70-degrees F.
4 Welds to metal deck, metal studs or other cold-formed metals: Conform to AWS D1.3
5 Welding or reinforcing steel: As noted in Concrete Reinforcing Steel portion of structural notes.
6 Welds to Galvanized Steel and Areas Damaged by Welding, Flame Cutting or Handling: Clean, dry and
remove oil, grease, salt, and corrosive products. Apply organic cold galvanizing compound with a
minimum of 94-percent zinc-dust in the dry film. Apply in multiple coats to achieve an 8-mil thickness.
F Install and inspect headed studs and shear connectors according to chapter 7 of AWS D1.1 “Structural Welding
Code-Steel.”
G Embedded steel assemblies: Hot-dip galvanize according to ASTM A123, where noted on drawings.
H Metal Roof and Floor Decking
1 Conform with the provisions of the American Iron and Steel Institute’s “Specifications for the Design of
Cold Formed Steel Structural Members.”
2 Metal roof decking and floor decking:
Wilson Associates Architects and Planners Section 05 12 00 - 2
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
a Material: Verco Type W3, 20 Ga, 36” wide sheets, galvanized deck or approved equal.
b Connections:
1) Decking to supporting members: ¾-inch diameter fusion welds with 4 welds per sheet.
2) Decking to beams or walls (where decking span is parallel to member): ¾-inch diameter fusion
welds at 12-inches on center.
3) Deck to deck side laps: Button punch at 24-inches on-center maximum.
c Provide decking continuous over 3 or more spans. Where 1 or 2 span conditions are required, provide
decking with sufficient section properties to equal load and deflection capacity of a 3 span condition.
d Furnish all accessories (opening reinforcing angles, closures, etc) to provide a complete diaphragm.
e Extend decking a minimum of 2-inches onto supports.
3.03 FINISHES
A Exterior Steel (non-exposed): Galvanize
B Exterior Steel (exposed): Galvanize and paint.
C Interior Steel: Paint.
END OF SECTION
1.01 DESCRIPTION
A Work included: Provide metal studs, resilient channels and related accessories as indicated on the drawings, as
specified herein, and as needed for a complete and proper installation.
1.02 QUALITY ASSURANCE
A Contractor shall provide effective, full time quality control over all fabrication and erection complying with the
pertinent codes and regulations of government agencies having jurisdiction.
1.03 SUBMITTALS
A Materials list of items proposed to be provided under this section.
B Manufacturer’s product information and other data needed to provide compliance with the specified requirements.
C Manufacturer’s recommended installation procedures which, when approved by the Architect, will become the
basis for accepting or rejecting actual installation procedures on the Work.
PART 2 - PRODUCTS
PART 3 - EXECUTION
1.01 SUMMARY
A Section includes: Bidder design steel pipe and tube handrails and railing systems for use at exterior stairs and
hallways.
1.02 REFERENCES
A Reference Standards
1 American Society of Testing and Materials (ASTM)
a ASTM A 500/ A500M-10a “Standard Specification for Cold-Formed Welded and Seamless Carbon
Steel Structural Tubing in Rounds and Shapes.”
b ASTM A 53/ A53M “Standard Specification for Pipe, Steel, Black and Hot Dipped, Zinc Coated,
Welded and Seamless.”
c ASTM A 36/A36M “Standard Specification for Carbon Structural Steel”
d ASTM A 48/A48M “Standard Specification for Gray Iron Castings.”
e ASTM A 47/A 47M “Standard Specification for Ferritic Malleable Iron Castings”
f ASTM F 1267 “Standard Specification for Metal, Expanded, Steel”
g ASTM A 510/ A510M “Standard Specification for General Requirements for Wire Rods and Coarse
Round Wire, Carbon Steel”
h ASTM B 633 “Standard Specification for Electroplated Coatings of Zinc on Iron and Steel.”
i ASTM E 488 “Standard Test Method for Strength of Anchors in Concrete Elements.”
j ASTM C 1107/C1107M “Standard Specification for Packaged Dry, Hydraulic Cement Grout
(Nonshrink).”
k ASTM A 123/A123M “Standard Specification for Zinc (Hot Dip Galvanized) Coatings on Iron and
Steel Products”
l ASTM A 780 “Standard Practice for Repair of Damaged and Uncoated Areas of Hot Dip Galvanized
Coatings.”
1.03 SUBMITTALS
A Product Data: for mechanically connected railings, grout, anchoring cement, and paint products.
B Shop Drawings: indicate plans, elevations, sections, details, and attachments.
1 For installed products indicated to comply with design loads, include structural analysis data signed and
sealed by the qualified professional engineer responsible for their preparation. Engineer must be licensed in
the State of Washington.
The Owner may, at its option, engage the services of a qualified professional structural engineer to prepare
the structural analysis data and provide such information to the Contractor. The Contractor’s shop drawings
shall demonstrate compliance with the structural engineer’s direction and shall be presented to the Owner
for review.
C Samples: For each exposed finish.
D Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency,
according to ASTM E 894 and ASTM E 935.
1.04 QUALITY ASSURANCE
A Qualifications – Structural design must be done by a licensed Professional Engineer in the State of Washington.
PART 2 - PRODUCTS
2.01 GENERAL
A Hallway Handrails: Match existing aluminum handrails so that new handrails match salvaged handrails.
B Exterior Railings: Bidder Design steel railing system.
2.02 PRODUCTS
A Metals
1 Brackets, flanges, and anchors: Cast or formed metal of same type of material and finish as supported rails,
unless otherwise indicated.
2 Steel and iron:
a Tubing: ASTM A 500 (cold formed) or ASTM A 513 (mandrel drawn).
PART 3 - EXECUTION
3.01 INSTALLATION
A General: Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in location,
alignment, and elevation.
1 Set posts plumb within a tolerance of 1/16-inch in 3-feet.
2 Align rails so variations from level for horizontal members and variations from parallel with rake of steps
and ramps for sloping members do not exceed ¼-inch in 12-feet.
B Finishes:
1 Exterior steel railings: Galvanized with painted finish.
2 Interior steel railings: Paint
3.02 ADJUSTING/CLEANING
A Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint
exposed areas with the same material as used for shop painting.
B Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply
with ASTM A 780.
END OF SECTION
1.01 SUMMARY
A Section Includes: wood blocking, framing, sheathing, furring, nailers, sub-flooring, rough hardware, and light
wood connections.
1.02 REFERENCES
A American Forest and Paper Association (AFPA)
1 NDS-06 National Design Specification for Wood Construction
B American Institute of Timber Construction (AITC)
1 A190.1 Structural Glued Laminated Timber
C American Society of Mechanical Engineers (ASME)
1 B18.2.1 Square and Hex Bolts and Screws
2 B18.2.2 Square and Hex Nuts
3 B18.6.1 Wood Screws
4 B18.6.4 Thread Forming and Thread Cutting Tapping Screws and Metallic Drive Screws
D American Plywood Association (APA):
1 E30 Engineered Wood Construction Guide
E American Society for Testing and Materials (ASTM)
1 A47-99 Ferritic Malleable Iron Castings
2 A48-03 Gray Iron Castings
3 A653/A653M Steel Sheet Zinc-Coated (Galvanized) or Zinc Iron Alloy Coated (Galvannealed) by the Hot
Dipped Process
4 C954 Steel Drill Screws for the Application of Gypsum Board or Metal Plaster Bases to Steel Studs
from 0.033-inch to 0.112-inch in thickness.
5 C1002 Steel Self-Piercing Tapping Screws for the Application of Gypsum Panel Products or Metal
Plaster Bases to Wood Studs or Metal Studs.
6 D143 Small Clear Specimens of Timber, Method of Testing
7 D1760 Pressure Treatment of Timber Products
8 D2559 Adhesives for Strucrtural Laminated Wood Products for Use Under Exterior (Wet Use)
Exposure Conditions.
9 D3498 Adhesives for Field-Gluing Plywood to Lumber Framing for Floor Systems
10 F844 Washers, Steel, Plan (Flat) Unhardened for General Use
11 F1667 Nails, Spikes, and Staples
F Federal Specifications (Fed Spec)
1 MM-L-736C Lumber; Hardwood
G Commercial Item Description (CID)
1 A-A-55615 Shield, Expansion (Wood Screw and Lag Bolt Self Threading Anchors)
H Military Specification (Mil Spec)
1 MIL-L-19140E Lumber and Plywood, Fire-Retardant Treated
I Truss Plate Institute (TPI):
1 TPI-85 Metal Plate Connected Wood Trusses
J US Department of Commerce Product Standard (PS)
1 PS 1-95 Construction and Industrial Plywood
2 PS 20-05 American Softwood Lumber Standard
1.03 SUBMITTALS
A Shop Drawings showing framing connection details, fasteners, connections and dimensions.
1.04 CLOSEOUT SUBMITTALS
A Maintenance Contracts
B Operation and Maintenance Data
C Warranty Documentation
D Record Documentation
E Sustainable Design Documentation
F Software
1.05 MAINTENANCE MATERIAL SUBMITTALS
A Spare Parts
Wilson Associates Architects and Planners Section 06 10 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
B Extra Stock Materials
C Tools
1.06 DELIVERY, STORAGE AND HANDLING
A Protect lumber and other products from dampness both during and after delivery at site.
B Pile lumber in stacks in such manner as to provide air circulation around surfaces of each piece.
C Stack plywood and other board products so as to prevent warping.
D Locate stacks on well drained areas, supported at least 6-inches above grade and cover with well ventilated sheds
having firmly constructed over hanging roof with sufficient end wall to protect lumber from driving rain.
PART 2 - PRODUCTS
2.01 LUMBER
A Unless otherwise specified, each piece of lumber is to bear the grade mark, stamp or other identifying marks
indicating the grades of material, and rules or standards under which it was produced.
1 Identifying marks in accordance with the rule or standard under which the material is produced, including
the requirements for qualifications and authority of the inspection organization, usage of authorized
identification, and information included in the identification.
2 Inspection agency for lumber approved by the Board of Review, American Lumber Standards Committee, to
grade species used.
B Structural Members: Species and grade as listed in the AFPA, National Design Specification for Wood
Construction having design stresses shown.
C Lumber Other Than Structural:
1 Unless otherwise specified, species graded under the grading rules of the inspection agency approved by the
Board of Review, American Lumber Standards Committee.
2 Framing Lumber: Minimum Extreme Fiber Stress in Bending of 1100.
3 Furring, blocking, nailers, and similar items 4-inches and narrower Standard Grade; and members 6-inches
and wider Number 2 Grade.
D Moisture Content: 19 percent or less.
E Preservative Treatment:
1 Do not treat Heart Redwood or Western Red Cedar.
2 Treat wood members and plywood exposed to weather or in contact with plaster, masonry or concrete,
including framing of open roofed structures; sills, sole plates, furring and sleepers that are less than 24-
inches from ground, nailers, edge strips, blocking, crickets, curbs, cant, vent strips and other members used
in connection with roofing and flashing materials.
3 Treat other members specified as preservative treated (PT).
4 Preservative treatment by the pressure method complying with ASTM D1760, except any process involving
the use of Chromated Copper Arsenate (CCA) for pressure treating wood is not permitted.
2.02 PLYWOOD
A Comply with Prod Std PS1
B Bear the mark of a recognized association or independent inspection agency that maintains continuing control
over quality of plywood which identifies compliance by veneer grade, group number, span rating where
applicable and glue type.
C Sheathing
1 APA Rated Exposure 1 or Exterior; panel grade CD or better
2 Wall sheathing:
a Minimum 11/32-inch thick with supports 16-inches on center and 15/32-inch thick with supports 24-
inches on center unless specified otherwise.
b Minimum 48-inches wide at corners without corner bracing of framing.
3 Roof sheathing:
a Minimum 11/32-inch thick with span rating 24/0 or 15/32-inch thick with span rating for supports 16-
inches on center unless otherwise specified.
b Minimum 19/32-inch thick or span rating of 40/20 or 23/32 –inch thick or span rating of 48/24 for
supports 24-inches on center.
D Sub-Flooring:
1 Under finish wood flooring or underlayment:
a APA Rated sheathing, Exposure 1, panel grade CD
PART 3 - EXECUTION
END OF SECTION
1.01 SUMMARY
A This section specifies interior millwork. Items specified:
1 Counters
2 Built-in desks and work spaces
3 Wall trim and detailing
4 Base
5 Moldings and Staff Beads
B Related Sections:
1 See Interior Design manual for more information. Follow interior design drawings where a conflict exists
between this section and Interior Design manual.
1.02 SUBMITTALS:
A Shop Drawings: Millwork items to scale with sections, plans, elevations and details
B Installation instructions
C Samples of:
1 Plastic Laminate
2 Finished plywood with preservative treatment and moisture content labeled
3 Manufacturer’s literature with hardware, sinks with fittings and electrical components.
1.03 QUALITY ASSURANCE
A Quality Standards: Conform to “Quality Standards” of the Architectural Woodwork Institute (AWI), latest
edition, “Custom” Grade and per WCLIB Standard Grading and Dressing Rules No. 16.
1.04 REFERENCE STANDARDS
A American Hardboard Association (AHA)
1 AHA A135.4-95 – Basic Hardboard
B Builders Hardware Manufacturer’s Association (BHMA)
1 BHMA A156.9-03 – Cabinet Hardware
2 BHMA A156.11-99 – Cabinet Locks
3 BHMA A156.16-02 – Auxiliary Hardware
C National Particleboard Association (NPA)
1 NPA A208.1-93 – Wood Particleboard
D American Wood Preservers Association (AWPA)
1 U1-07 – User Specification for Treated Wood
E Architectural Woodwork Insitute (AWI)
1 AWI 2009 – Architectural Woodwork Standards
PART 2 - PRODUCTS
2.01 LUMBER:
A Grading and Marking:
1 Lumber shall bear the grade mark, stamp, or other identifying marks indicating grades of materials.
2 Such identifying marks on a material shall be in accordance with the rule or standard under which the
material is produced, including requirements for qualifications and authority of the inspection organization,
usage of authorized identification, and information included in the identification.
3 The inspection agency for lumber shall be approved by the Board of Review, American Lumber Standards
Committee, to grade species used.
B Sizes:
1 Lumber size references, unless otherwise specified, are nominal sizes, and actual sizes shall be within
manufacturing tolerances allowed by the standard under which the product is produced.
2 Millwork, standing and running trim, and rails: Actual size as shown or specified.
C Hardwood: MM-L-736, species as specified for each item
D Softwood: PS-20, exposed to view appearance grades:
1 Use C select or D select, vertical grain for transparent finish including stain transparent finish.
PART 3 - EXECUTION
3.01 GENERAL
A Do not install finish lumber or millwork in any room or space where wet process systems such as concrete,
masonry or plaster work is not complete and dry.
B Millwork receiving transparent finish shall be primed and back-painted on concealed surfaces. Set no millwork
until primed and back-painted.
C Secure trim with fine finishing nails, screws, or glue as required.
D Set nails for putty stopping. Use washers under bolt heads where no other bearing plate occurs.
E Seal cut edges of preservative and fire treated wood materials with a certified acceptable sealer.
F Coordinate with plumbing and electrical work for installation of fixtures and service connections in millwork
items.
G Plumb and level items unless shown otherwise.
H Nail finish at each blocking, lookout, or other nailer and intermediate points; toggle or expansion bolt in place
where nails are not suitable.
I Exterior work: Joints shall be close fitted, metered, tongue and grooved, rebated or lapped to exclude water and
made up in thick white lead paste in oil.
J Interior Counters: Secure framing to walls and floor with wood cleats or metal angles (as shown) screwed on 6”
centers. Conceal all exposed fasteners EXCEPT under counter tops and in knee spaces on staff side.
K Interior Trim: Install trim with end joints butted and blind nail each board.
L Fixed Shelves: Install mounting strip at back wall and end walls for shelves and secured with toggle bolts at each
end.
1 Nail shelf to mounting strip at ends and to back wall strip at not over 36” o.c.
M Handrails: Install in one piece and one length when practical. Where rails change slope, install special curved
sections and ends of rails to return to wall. Glue all field joints. Install brackets within 12” of ends of handrails
and at every spaced intervals between not exceeding 5’-0” on centers at intervals between as shown. Anchor
brackets as detailed and rails to brackets with screws. Install with butt joints in straight runs and miter at corners.
END OF SECTION
1.01 SUMMARY
A Section includes glass fiber batt and roll insulation.
1.02 REFERENCES
A American Society for Testing and Materials (ASTM).
1 E 84 Test Method for Surface Burning Characteristics of Building Materials.
2 E 96 Test Method for Water Vapor Transmission of Materials.
3 E 136 Test Method for Behavior of Materials in a Vertical Tube Furnace at 750°C.
4 C 518 Test Method for Steady-State Thermal Transmission Properties by Means of the Heat Flow Meter.
5 C 665 Specification for Mineral Fiber Blanket Thermal Insulation for Light Frame Construction and
Manufactured Housing.
1.03 SUBMITTALS
A Product Data: Submit product literature, samples and installation instructions for specified insulation. Submittal
should show:
1 Warranted R-value of insulation per inch of thickness.
2 Shop drawings showing installed thickness at each location
3 Type of insulation including faced, integral vapor-barriers, composition
4 MSDS sheets.
a Verification that insulation contains no urea-formaldehyde
1.04 DELIVERY STORAGE AND HANDLING
A Blanket insulation is particularly susceptible to contamination via absorption of airborne or liquid toxins. Protect
insulation at all times.
B Protect insulation from physical damage and from becoming wet, soiled, or covered with ice or snow. Comply
with manufacturer’s recommendations for handling, storage and protection during installation.
C Label insulation packages to include material name, production date and/or product code.
1.05 LIMITATIONS
A Do not use unfaced insulation in exposed applications where there is potential for skin contact and irritation.
B Kraft and standard foil facings will burn and must not be left exposed. The facing must be installed in substantial
contact with an approved construction material. Protect facing from any open flame or heat source.
C Do not rely on insulation or facing to provide an air barrier. Building envelope must block the movement of air.
D Do not use insulation in buildings with high inside relative humidity, especially those located in cold climates,
without evaluating the potential for moisture accumulation.
PART 2 - PRODUCTS
2.01 GENERAL
A The rated R-Value of insulation shall be clearly identified by an identification mark applied by the manufacturer
to each piece of building envelope insulation.
2.02 THERMAL BATT INSULATION
A Type: Unfaced glass fiber thermal insulation complying with ASTM C 665, Type I and ASTM E 136.
B Type: Kraft-faced glass fiber thermal insulation complying with ASTM C 665, Type II, Class C.
C Type: Foil-faced glass fiber thermal insulation complying with ASTM C 665, Type III, Class B and C.
D Thickness: as required to meet minimum R-Values.
1 R-Values listed on plans are minimum values. Insulation averaging will not be allowed.
2.03 ACOUSTIC BATT INSULATION
A QuietZone Eco Touch Pink insulation by Owens Corning or approved.
2.04 WOOD FRAME INSULATION
A Provide a vapor barrier on warm side (in winter) of framing.
B NOTE: Blown-in or poured loose filled insulation is not allowed.
2.05 PERFORMANCE CHARACTERISTICS
A Vapor Retarder Perm Rating:
1 Foil-facing Perms Maximum 0.50
2 Kraft-facing Perms Maximum 1.00
Wilson Associates Architects and Planners Section 07 21 16 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
3 When tested in accordance with ASTM E 96.
B Surface Burning Characteristics:
1 Unfaced Insulation
a Maximum flame spread: 10
b Maximum smoke developed: 10
2 Foil-Faced Insulation
a Maximum flame spread: 75
b Maximum smoke developed: 150
c When tested in accordance with ASTM E 94*.
C Combustion Characteristics:
1 Unfaced Insulation
a Passes ASTM E 136 test.
D Dimensional Stability:
1 Linear shrinkage less than 0.1%.
2.06 OTHER MATERIALS
A Provide materials, not specifically described but required for a complete and proper installation of the work in this
section.
PART 3 - EXECUTION
END OF SECTION
1.01 SUMMARY
A Furnish all labor, materials, equipment, and services necessary for and incidental to the application of membrane
roofing materials necessary for a complete weathertight installation.
1.02 REFERENCES STANDARDS
A Reference Standards
1 American Society for Testing and Materials (ASTM)
2 Factory Mutual Engineering and Research (FM)
a “Wind Force on Buildings and Other Structures” Loss Prevention Data Sheet 1-7
b “Wind Loads to Roof Systems and Roof Deck Securement” Loss Prevention Data Sheet 1-28.
c “Roof Systems” Loss Prevention Data Sheet 1-28/1-29R.
d “Above Deck Roof Components” Loss Prevention Data Sheet 1-29
e “Perimeter Flashing” Loss Prevention Data Sheet 1-49.
3 Federal Testing Material Standard (FTMS).
4 National Roofing Contractors Association (NRCA) Roofing and Waterproofing Manual, current edition.
5 Underwriter’s Laboratories (UL).
a Building Materials Directory, 2006 Edition
b Fire Resistance Directory, 2006 Edition
c UL 214 Flame Test
6 International Code Council (ICC).
1.03 SUBMITTALS
A The following information shall be submitted to Architect for review. Additional submittal requirements may be
required by the manufacturer for warranty compliance.
1 Product Data: Provide current manufacturer product data sheets including:
a Standard guide specification for the material
b Test reports and certifications for compliance with reference standards.
c Copy of the manufacturer’s warranty and installers guarantee.
d List of all accessories that will be used as part of the installation. Where accessories are not part of a
single source system by the roof membrane manufacturer, provide verification from the manufacturer
that the accessories are acceptable for use as part of the system and won’t violate warranty conditions
or exclusions.
e MSDS sheets for the roof membrane and all accessories, including adhesives and primers that will be
used. List VOC content on the MSDS sheets.
2 Shop Drawings: Provide field verified shop drawings showing:
a Dimensioned plans for the entire installation. Include roof slopes and drain locations.
b Manufacturer’s details showing terminations, edge detailing, penetrations, flashing, and standard
attachment requirements. Modify details to conform to the specific job site conditions of the project,
including but not limited to:
1) Deck type
2) Insulation or backer board material proposed for use.
3) Fasteners proposed for use.
3 Samples: Provide a sample of the roof membrane material, finished sheet metal that will be visible.
4 Manufacturer’s Instructions:
a Manufacturer’s standard installation instructions.
b Routine maintenance instructions.
5 Certifications: Provide certification that the membrane applicator is approved by the membrane
manufacturer for the application of warranted membrane.
1.04 CLOSEOUT SUBMITTALS
A Product Data: Provide product data information including the name and model of the product, the color and the
manufacturer’s contact information.
B Operation and maintenance data.
C Executed warranty agreement.
D Record documentation of the installation.
1.05 QUALITY ASSURANCE
Wilson Associates Architects and Planners Section 07 54 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
A Roofing Contractor: The roofing contractor shall designate a single individual to be the primary contact for all
roof related issues. The contact person shall be available for any questions about the installation, impacts to the
building occupants, job site safety, storage and staging locations, parking, site access and other issues related to
the Work.
B Manufacturer – Company specializing in the membrane installation proposed. The manufacturer shall certify the
knitted fabric reinforced KEE membrane meets the physical properties specified.
C Roofing System shall be installed only by a roofing contractor, authorized by manufacturer prior to bid, to install
selected roofing system.
D Roofing contractor’s key personnel shall have been trained by the Manufacturer.
E Product shall demonstrate a proven 25 year installed service life.
F Roofing Systems shall be installed in accordance with the most current guide specifications and details as
amended and authorized by Manufacturer for specific project requirements.
G There shall be no deviations from approved Contract Documents or reviewed shop drawings without prior written
approval by the Owner and Manufacturer.
H Unauthorized deviations may subject the roof system to warranty ineligibility, which then be considered
substandard.
I Work found to be substandard or in violation of the Contract Documents or Manufacturer’s Specifications shall
be subject to rejection including complete removal and replacement with new materials at the expense of the
Contractor.
J Upon completion and certification by the Contractor that a quality installation has been completed in accordance
with the Contract Documents and all field welds have been probed and inspected, quality assurance inspection of
the roof system shall be performed by manufacturer for acceptance and approval of appropriate warranty. All
field seams must be available for inspection. The warranty will not be issued until Substantial Completion, when
the membrane will be reinspected by the membrane manufacturer. Damaged membrane shall be repaired prior to
issuing warranty.
K Pre-Roofing Membrane: schedule a pre-roofing meeting for each location where Work will occur to review the
proposed system, application, compatibility, scheduling, interface coordination, warranty/guarantee requirements
and quality standards. Notify the Architect and the Owner of the date, time and location of the meeting.
Notification must be given at least 48 hours in advance of the meeting’s scheduled time. Invitations shall also be
made to the roof membrane manufacturer’s representative.
1 Record minutes of the Meeting and distribute to all attendees.
2 Satisfactory adoption of the minutes of the Meeting by all will be automatic when no written amendments to
the minutes are received within 7 days after the Meeting.
L Roof system shall meet requirements of a UL Class B Roof System.
M Roof shall comply with all requirements of the current edition of the IBC at the time of permit issuance.
N Product Compatibility: Provide products which are components of a single manufacturer, or are certified by the
membrane manufacturer as compatible and included in a manufacturer’s warranty. No product shall be used that
the membrane manufacturer considers unacceptable and their performance excluded from the warranty.
O Manufacturer’s Requirements: Where any provision or requirement of product installation called for in these
Specifications is in conflict with the membrane manufacturer’s printed installation procedures, the manufacturer’s
instructions shall prevail.
1.06 DELIVERY, STORAGE AND HANDLING
A Comply with all manufacturer’s written requirements for Delivery, Storage and Handling.
B Deliver all materials to the job site in their original, unopened containers, with legible labels and in sufficient
quantity to allow continuity of the Work.
C Materials, having been determined by an Owner’s Representative to be damaged, shall be immediately removed
from the construction site and replaced at no cost to the Owner.
D See Section 01 74 00 for Cleaning and Waste Management of packaging materials.
1.07 WARRANTY
A Contractor’s Guarantee:
1 Furnish a written notarized guarantee cosigned by the membrane installer covering both roofing and sheet
metal for a period of two years from Substantial Completion, guaranteeing that all surfaces exposed to the
weather are watertight and free from defective materials and deficiencies in workmanship, and that the
membrane installer will correct or replace any portion of the Work which fails in the performance of its
purpose.
2 Emergency leaks will be attended to within 24 hours from receipt of notice from Owner. As soon as
weather permits, Contractor will restore affected areas to standards of this contract without voiding the
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 INSTALLERS
A Roofing system must be installed by an authorized roofing applicator in compliance with the drawings and
specifications.
3.02 EXAMINATION
A Verification of Conditions: Visually inspect areas that will receive work prior to starting. Do not start work until
deficiencies have been corrected.
B Field verify dimensions.
C Evaluation and Assessment: If required, evaluate existing substrates to receive work to assess their suitability for
proper installation/application of products. Proceeding with the work will be understood as acceptance of the
preexisting conditions.
3.03 PREPARATION
A Protection of In-Place Conditions:
1 Protect parts of the roof that are outside the area of work being completed that day. This includes, but is not
limited to, HVAC equipment, vents, roof access hatches, weatherheads, flashing and other installed and
complete items.
B Demolition/Removal:
1 Where existing utility lines, such as gas, water and power, are impacted, properly cap the lines to protect the
service during the course of the work. Notify the related utility of service disruptions and comply with
requirements.
END OF SECTION
1.01 SUMMARY
A Section Includes: Sheet metal and flashing and trim in the following categories:
1 Roof-drainage systems
2 Exposed trim and fascia
3 Metal flashings
1.02 REFERENCES
A American Society of Testing and Materials (ASTM)
1 ASTM A 653/A 653M – Standard Specification for Steel Sheet, Zinc Coated (Galvanized) or Zinc-Iron
Alloy Coated (Galvannealed) by the Hot-Dip Process.
2 ASTM A 527/A 527M – Specification for Steel Sheet, Zinc Coated (Galvanized) by the Hot Dip Process,
Lock Forming Quality
3 ASTM A 755/ A 755M – Standard Specification for Steel Sheet, Metallic Coated by the Hot Dip Process
and Prepainted by the Coil Coating Process for Exterior Exposed Building Products
4 ASTM B 32 – Standard Specification for Solder Metal
5 ASTM D 4397 – Standard Specification for Polyethylene Sheeting for Construction, Industrial, and
Agricultural Applications
6 ASTM D 4586 – Standard Specification for Asphalt Roof Cement, Asbestos Free
7 ASTM E 154 – Standard Test Methods for Water Vapor Retarders Used on Contact with Earth Under
Concrete Slabs, on Walls, or as Ground Cover
B The Society for Protective Coatings (SSPC)
C Federal Specifications (FS)
1 FS UU-B-790A – Building Paper, Vegetable Fiber: Kraft, Waterproofed, Water Repellent and Fire Resistant
D Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA)
1.03 SUBMITTALS
A General: Submit all items within this category as part of a single submittal.
B Product Data: Include manufacturer’s material and finish data, installation instructions, and general
recommendations for each specified flashing material and fabricated product.
C Shop Drawings: Provide field verified shop drawings showing dimensions, layout, profiles, methods of joining
and anchorage.
D Samples: Provide samples of the finished sheet metal with the same color and texture as the proposed installation.
1.04 QUALITY ASSURANCE
A Installer Qualifications: Engage an experienced Installer who has completed sheet metal flashing and trim work
similar in material, design, and extent to that indicated for this Project and with a record of successful in-service
performance.
PART 2 - PRODUCTS
2.01 PRODUCTS:
1 Metals
a Galvanized Steel Sheet: ASTM A 653, G 90 (ASTM A 653M, Z 275), commercial quality, or ASTM
A 527, G 90 (ASTM A 527M, Z275), lock-forming quality, hot-dipped galvanized steel sheet with
0.20 percent copper, mill phosphorized where indicated for painting, not less than 0.0396-inch thick,
unless otherwise indicated.
b Coil-Coated Galvanized Sheet Steel: Zinc-coated, commercial quality steel sheet conforming to ASTM
A 755, G 90 (ASTM A 755M, Z 275) coating designation, coil coated with high performance
fluoropolymer coating as specified in ‘Coil-Coated Galvanized Steel Sheet Finish’ Article; not less
than 0.0366 inch thick, unless otherwise indicated.
2 Gutters and Downspouts:
a General: Gutters must be single piece gutters with no seams.
b 26 gauge prefinished metal gutter
c Size: 6” x 6”
d Style: K
e Fasteners: 16 gauge galvanized metal straps @ 36” o.c.
Wilson Associates Architects and Planners Section 07 62 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
f Downspouts: 3”x4” 24 gauge rectangular
g Color: Provide Kynar 500 paint by architect.
3 Miscellaneous Materials and Accessories
a Burning Rod for Lead: Same composition as lead sheet
b Solder: ASTM B 32, Grade Sn5O, used with rosin flux
c Fasteners: Same metal as sheet metal flashing or other non-corrosive metal as recommended by sheet
metal manufacturer. Match finish of exposed heads with material being fastened.
d Asphalt Mastic: SSPC-Paint 12, solvent-type asphalt mastic, nominally free of sulfur and containing
no asbestos fibers, compounded for 15-mil dry film thickness per coat.
e Mastic Sealant: Polyisobutylene; nonhardening, nonskinning, nondrying, nonmigrating sealant
f Elastomeric Sealant: Generic type recommended by sheet metal manufacturer and fabricator of
components being sealed and complying with requirements for joint sealants.
g Adhesives: type recommended by flashing and sheet metal manufacturer for waterproof and weather-
resistant seaming and adhesive application of flashing sheet metal.
h Paper Slip Sheet: 5-lb/square red rosin, sized building paper conforming to FS UU-B790, Type 1, Style
1b.
i Polyurethane Underlayment: ASTM D 4397, minimum 6-mil thick black polyethylene film, resistant
to decay when tested according to ASTM E 154.
j Metal Accessories: Provide sheet metal clips, straps, anchoring devices, and similar accessory units as
required for installation of Work, matching or compatible with material being installed; non-corrosive;
size and thickness required for performance.
k Gutter Screen: ¼-inch hardware cloth installed in sheet metal frames. Fabricate screen and frame of
same basic material as gutter and downspout.
l Roofing Cement: ASTM D 4586, Type I, asbestos free, asphalt based.
2.02 FABRICATION
A Sheet Metal Fabrication General: Fabricate sheet metal flashing and trim to comply with recommendations of
SMACNA’s “Architectural Sheet Metal Manual” that apply to the design dimensions, metal, and other
characteristics of the item indicated.
1 Comply with details shown to fabricate sheet metal flashing and trim that fit substrates and result in
waterproof and weather-resistant performance once installed. Verify shapes and dimensions of surfaces to
be covered before fabricating sheet metal.
2 Form exposed sheet metal Work that is without excessive oil canning, buckling, and tool marks and that is
true to line and levels indicated, with exposed edges folded back to form hems.
3 Seams: Fabricate nonmoving seams in sheet metal with flat-lock seams. Tin edges to be seamed; form
seams, and solder.
4 Expansion Joints: Space movement joints at maximum of 10 feet with no joints allowed within 24 inches of
corner or intersection. Where lapped or bayonet-type expansion provisions in Work cannot be used or
would not be sufficiently weatherproof and waterproof, form expansion joints of intermeshing hooked
flanges, not less than 1-inch deep, filled with mastic sealant (concealed within joints).
5 Sealed Joints: Form non-expansion, but moveable, joints in metal to accommodate elastomeric sealant to
comply with SMACNA standards.
6 Separated from noncompatible metal or corrosive substrates by coating concealed spaces at locations of
contact with asphalt mastic or other permanent separation as recommended by manufacturer.
7 Conceal fasteners and expansion provisions where possible. Exposed fasteners are not allowed on faces of
sheet metal exposed to public view.
8 Fabricate cleats and attachment devices from same material as sheet metal component being anchored or
from compatible, non-corrosive metal.
a Size: As recommended by SMACNA manual or sheet metal manufacturer for application but never
less than thickness of metal being secured.
B Sheet Metal Fabrications:
1 General: Fabricate sheet metal items in thickness or weight needed to comply with performance
requirements but not less than that listed below for each application and metal:
a Conductor Heads: Galvanized steel, 0.0276-inch thick
b Roof-Drain Flashing: Lead, 4.0 lb/s.f. hard tempered.
c Scuppers:
1) Galvanized Steel: 0.0276-inch thick
2) Coil-Coated Galvanized Steel: 0.0276 thick
d Exposed Trim, Gravel Stops, and Fascia: Galvanized steel 0.0276-inch thick
Wilson Associates Architects and Planners Section 07 62 00 - 2
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
e Copings: Galvanized steel, 0.0396-inch thick
f Counterflashing:
1) Galvanized steel, 0.0217-inch thick
2) Coil-Coated Galvanized Steel: 0.0217-inch thick
g Valley Flashing: Lead-coated copper, 16 oz/s.f.
h Drip Edges: Galvanized steel, 0.0217-inch thick
i Equipment Support Flashing: Galvanized steel, 0.0276-inch thick
j Roof-Penetration Flashing:
1) Lead-Coated Copper: 16 oz/s.f.
2) Galvanized Steel: 0.0276-inch thick
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine substrates and conditions under which sheet metal flashing and trim are to be installed and verify that
Work may properly commence. Do not proceed with installation until unsatisfactory conditions have been
corrected.
1 Where existing flashing is being removed and replaced, completely remove the existing flashing and inspect
the underlying framing. Replace damaged wood, re-setting drainage pathways.
3.02 INSTALLATION
A General: Unless otherwise indicated, install sheet metal flashing and trim to comply with performance
requirements, manufacturer’s installation instructions, and SMACNA’s “Architectural Sheet Metal Manual.”
Anchor units of Work securely in place by methods indicated, providing for thermal expansion of metal units;
conceal fasteners where possible, and set units true and level as indicated. Install Work with laps, joints, and
seams that will be permanently watertight and weathertight.
B Install exposed sheet metal work that is without excessive oil canning, buckling, and tool marks and that is true to
line and levels indicated, with exposed edges folded back to form hems. Install sheet metal flashing and trim to
fit substrates and to result in waterproof and weather resistant performance. Verify shapes and dimensions of
surfaces to be covered before fabricating sheet metal.
C Roof-Edge Flashings: Secure metal flashings at roof edges according to FM Loss Prevention Data Sheet 1-49 for
specified wind zone.
D Expansion Provisions: Provide for thermal expansion of exposed sheet metal work. Space movement joints at
maximum of 10-feet with no joints allowed within 24-inches of corner or intersection. Where lapped or bayonet-
type expansion provisions in work cannot be used or would not be sufficiently weatherproof and waterproof, form
expansion joints of intermeshing hooked flanges, not less than 1-inch deep, filled with mastic sealant (concealed
within joints).
E Soldered Joints: Clean surfaces to be soldered, removing oils and foreign matter. Pretin edges of sheets to be
soldered to a width of 1-1/2 inches, except where pretinned surface would show in finished Work.
1 Do not solder the following materials:
a Aluminum
b Coil-Coated galvanized steel sheet
2 Pretinning is not required for the following metals:
a Lead
b Lead-coated copper
3 Do not use torches for soldering. Heat surfaces to receive solder and flow solder into joint. Fill joint
completely. Completely remove flux and spatter from exposed surfaces.
F Sealed Joints: Form nonexpansion, but moveable, joints in metal to accommodate elastomeric sealant to comply
with SMACNA standards. Fill joint with sealant and form metal to completely conceal sealant.
1 Use joint adhesive for nonmoving joints specified not be soldered.
G Concealed Seams: Fabricate nonmoving scams in sheet metal with flat-lock seams. Tin edges to be seamed, form
seams, and solder.
H Exposed Seams: Butt join seams with 1-foot wide backer flashing in all exposed locations, including parapet
copings and other exposed break shape metal detailing.
I Separations: Separate metal from noncompatible metal or corrosive substrates by coating concealed surfaces, at
locations of contact, with asphalt mastic or other permanent separation as recommended by manufacturer.
1 Underlayment: Where installing stainless steel or aluminum directly or cementitious or wood substrates,
install a slip sheet or red-rosin paper and a course of polyethylene underlayment.
END OF SECTION
1.01 SUMMARY
A Section Includes: Through penetration firestopping and fire resistive joint systems.
1.02 REFERENCES
A Reference Standards:
1 American National Standards Institute (ANSI)
a ANSI/UL 263 – Fire Tests of Building Construction and Materials
b ANSI/UL 723 – Surface Burning Characteristics of Building Materials
c ANSI/UL 1479 – Standard for Fire Tests of Through-Penetration Firestops
d ANSI/UL 2079 – Tests for Fire Resistance of Building Joint Systems
2 ASTM International (ASTM)
a ASTM E 84 – Standard Test Method for Surface Burning Characteristics of Building Materials
b ASTM E 119 – Standard Test Method for Fire Tests of Building Construction and Materials
c ASTM E 1399 – Standard Test Method for Cyclic Movement and Measuring the Minimum and
Maximum Joint Widths of Architectural Joint Systems
d ASTM E 1966 – Standard Test Method for Fire Resistive Joint Systems
e ASTM E 2174 – Standard Practice for On-Site Inspection of Installed Firestops
f ASTM E 2307 – Fire Tests of Perimeter Fire Barrier Systems Using Intermediate Scale, Multi-Story
Test Apparatus
g ASTM E 2393 – Standard Practice for On-Site Inspection of Installed Fire Resistive Joint Systems and
Perimeter Fire Barriers
3 Factory Mutual (FM)
a FM4991 – Standard for Approval of Firestop Contractors
4 National Fire Protection Association (NFPA)
a NFPA 70 – National Electric Code
b NFPA 80 – Standard for Fire Doors and Other Opening Protectives
c NFPA 96 – Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations
d NFPA 101 – Life Safety Code
e NFPA 5000 – Building Construction and Safety Code
5 American Society of Sanitary Engineering (ASSE)
a ASSE Series 9000 – Professional Qualification Standard for Firestop Systems and Device Installers,
Inspectors and Surveyors
6 International Standards Organization (ISO)
a ISO 6944
b ISO 10295-1
c ISO 10295-2
d ISO 10295-3
1.03 SUBMITTALS
A Shop Drawings: For each firestopping system, provide the following:
1 Listing of agency’s detailed drawing showing opening, penetrating item(s), and firestopping materials,
identified with listing agency’s name and number or designation and fire rating achieved.
2 For proposed systems that do not conform strictly to the listing, submit written instructions showing
modifications and approved by firestop system manufacturer.
3 Submit under provisions of the International Building Code (IBC) section 107 and 703 requiring a submittal
package for fire-resistance ratings and fire tests.
B Product Certificates – Submit certificates of conformance signed by firestop system manufacturer certifying that
materials furnished comply with requirements.
C Product Data: Furnish manufacturer’s product data sheets on each material to be used in firestop systems.
Information on manufacturer’s product data sheet should include:
1 Product characteristics including compliance with appropriate ASTM/UL/ANSI test standard.
2 Storage and handling requirements and recommendations.
D Installation Instructions
1.04 QUALITY ASSURANCE
A Provide systems that are listed by at least one of the following:
Wilson Associates Architects and Planners Section 07 84 43 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
1 Underwriters Laboratories Inc
2 Intertek Testing Service
3 Factory Mutual (FM) in FMRC Approval Guide
4 Other qualified independent testing agency that is acceptable to authorities having jurisdiction.
1.05 DELIVERY, STORAGE AND HANDLING
A Comply with all manufacturer’s written requirements for Delivery, Storage and Handling.
1.06 WARRANTY
A Provide manufacturer’s standard warranty against manufacturing defects, outlining its terms, conditions, and
exclusions from coverage, starting from the date of Substantial Completion.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
1 General: To maintain control and integrity of the firestop applications a single manufacturer should be used.
Specific UL or approved listing agencies systems applicable to each type of firestop condition should be
supplied by one manufacturer.
2 Acceptable Manufacturer:
a 3M Fire Protection Products
b HILTI Firestop Systems
2.02 PERFORMANCE CRITERIA
A Firestopping materials must be flexible enough to allow for pipe vibration in a through-penetration application.
B Provide fire-resistive sealants and sprays for construction joint applications that are flexible enough to satisfy the
movement criteria per the test standards ASTM E 1399, ASTM E 1966 or ANSI/UL 2079
C Provide products with appropriate flame spread index and smoke develop index, when tested in accordance with
ASTM E 84
D Provide products that meet the intent of the L rating classification for the movement of smoke per ANSI/UL 1479
for through penetrations and ANSI/UL 2079 for construction joints.
E Provide products identical to those tested and listed for classification by UL, Intertek or any other qualified
independent testing agency.
F Provide products that bear classification marking of qualified independent testing agency.
G Where firestop systems not listed by any listing agency are required due to project conditions, submit a
substitution proposal with evidence specified.
H Use only products specifically listed for use in listed system.
I Provide products that are compatible with each other, with the substrates forming openings, and with the items, if
any, penetrating the firestopping, under the conditions represented by this project, based on testing and field
performance demonstrated by the manufacturer.
J Firestopping materials must meet and be acceptable for use by all building codes and NFPA codes in affect at the
project site.
K Provide products that meet the intent of the state or local guidelines on volatile organic compounds (VOC)
L Where applicable provide products that meet the intent of the F rating classification for passage of flame per
ANSI/UL 1479 for through penetrations
M Where applicable provide products that meet the intent of the T rating classification for the transfer of
temperature per ANSI/UL 1479 for through penetrations.
N Provide products that meet the intent of the L rating classification for the movement of smoke per ANSI/UL 1479
for through penetrations and ANSI/UL 2079 for construction joints.
O Where applicable provide products that meet the intent of the W rating classification for passage of water per
ANSI/UL 1479 for through penetrations.
2.03 SCOPE/APPLICATION
A Provide installed firestop products that limit the spread of fire, heat, smoke, and gasses through otherwise
unprotected openings in rated assemblies, including walls, partitions, floors, roof/ceilings, and similar locations,
restoring the integrity of the fire rated construction to its original fire rating.
B Provide firestop systems listed for the specific combination of fire-rated construction, type of penetrating item,
annular space requirements, and fire rating, and the following criteria:
1 F-Rating: Equal to or greater than the fire-resistance rating of the assembly in which the firestopping will be
installed.
2 T-Rating: In habitable areas where penetrating items are exposed to potential contact with materials on fire
side(s) of rated assembly, T-rating must equal its F-rating.
PART 3 - EXECUTION
3.01 EXAMINATION
A Do not begin installation until substrates have been properly prepared.
B Conduct tests according to manufacturer’s written recommendations to verify that substrates are free of oil,
grease, rolling compounds, incompatible primers, loose mill scale, dirt and other foreign substances capable of
impairing bond of firestopping.
C Verify that items penetrating fire rated assemblies are securely attached, including sleeves, supports, hangers, and
clips.
D Verify that openings and adjacent areas are not obstructed by construction that would interfere with installation of
firestopping, including ducts, piping, equipment, and other suspended construction.
E Verify that environmental conditions are safe and suitable for installation firestopping.
3.02 PREPARATION
A Prepare substrates in accordance with manufacturer’s instructions and recommendations
B Install masking and temporary coverings as required to prevent contamination or defacement of adjacent surfaces
due to firestopping installation.
3.03 INSTALLATION
A Install in strict accordance with manufacturer’s detailed installation instructions and procedures.
B Install so that openings are completely filled and material is securely adhered.
C Where firestopping surface will be exposed to view, finish to a smooth, uniform surface flush with adjacent
surfaces.
D After installation is complete, remove combustible forming materials and accessories that are not part of the listed
system.
E Repair or replace defective installations in accordance with manufacturer’s recommendations, listed systems
details and applicable code requirements.
F At each through penetration or fire-resistive joint system, attach identification labels on both sides in location
where label will be visible to anyone seeking to remove penetrating items or firestopping.
G Clean firestop materials off surfaces adjacent to openings as work progresses, using methods and cleaning
materials approved in writing by firestop system manufacturer and which will not damage the surfaces being
cleaned.
H Notify Authority Having Jurisdiction when firestopping installation is ready for inspection; obtain advance
approval of anticipated inspection dates and phasing, if any, required to allow subsequent construction to proceed.
I Do not cover firestopping with other construction until approval of authority having jurisdiction has been
received.
3.04 CLEANING
A Remove left over material and debris from Work area. Use necessary means to protect fire protection products
before, during, and after installation.
B Touch-up, repair or replace damaged products before Substantial Completion.
C Install identification labels for through-penetration and construction joint systems. Use the following labels:
END OF SECTION
1.01 SUMMARY
A Section Includes:
1 Architectural grade sealants
2 Construction adhesives and sealants
3 General purpose grade sealants
1.02 REFERENCES
A Reference Standards
1 American Architectural Manufacturer’s Association (AAMA)
a AAMA 808.3 – Exterior Perimeter Sealing Compound
2 American Society of Testing and Materials (ASTM)
a ASTM C 639 – Standard Test Method for Rheological Properties of Elastomeric Sealants
b ASTM C 719 – Standard Test Method for Adhesion and Cohesion of Elastomeric Joint Sealants Under
Cyclic Movement
c ASTM C 794 – Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants
d ASTM C 920 – Standard Specification for Elastomeric Joint Sealants
e ASTM C 1135 – Standard Test Method for Determining Tensile Adhesion Properties of Structural
Sealants
f ASTM C 1184 – Standard Specification for Structural Silicone Sealants
g ASTM C 1193 – Standard Guide for Use of Joint Sealants
h ASTM C 1248 – Standard Test Method for Staining Porous Substrate by Joint Sealants
i ASTM C 1311 – Standard Specification for Solvent Release Sealants
3 Military Specifications and Standards (MIL)
a MIL-A-46106 – Adhesive-Sealants, Silicone, RTV, One-Component
1.03 SUBMITTALS
A Product Data – Manufacturer’s technical data sheets on each product to be used, including:
1 Preparation instruction and recommendations
2 Storage and handling requirements and recommendations.
3 Installation methods including joint design, surface preparation, and application methods.
4 Submit manufacturer’s test reports indicating test results of adhesion and/or compatibility testing of samples
of substrates which either come in contact with or are in close proximity to sealants.
1.04 CLOSEOUT SUBMITTALS
A Maintenance Contracts
B Operation and Maintenance Data
C Warranty Documentation
D Record Documentation
E Sustainable Design Documentation
F Software
1.05 WARRANTY
A Manufacturer’s Warranty
PART 2 - PRODUCTS
2.01 PRODUCTS:
A Elastomeric Sealants: Used for sealing window and door frames from the interior.
1 Basis of Design: Sonolastic 150
2 Performance Requirements:
a Movement Capability ASTM C 719 +/-50%
b Extension ASTM C 1382 100%
c Tensile Strength ASTM D 412 220 psi
d Tear Strength ASTM D 1004 40 lb/in
e Ultimate Elongation ASTM D 412 1,200%
f Rheologial ASTM C 639 No sag
g Extrudability ASTM C 603 203 sec
Wilson Associates Architects and Planners Section 07 90 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
h Hardness ASTM C 661 17 Shore A, at standard condition
i Weight Loss ASTM C 792 <10 after heat aging
j Stain and color change ASTM C 510 Passes
k Bond durability ASTM C 719 Passes
B Silicone Sealant: For wet areas such as bathrooms and kitchens and exterior sealing.
1 Basis of Design: Dow Corning 795 Silicone Building Sealant
2 Performance Requirements:
a Joint Movement Capability ASTM C 719 +/- 50%
b Hardness ASTM C 2240 35 Shore A
c Max Peel Strength ASTM C 794 32 ppi
d Tensile Adhesion ASTM C 1135 45 psi at 25% extension
C Flexible Foam Sealants: For gaps and cracks, such as sill plates and around plumbing and electrical penetrations
on the interior of the house where air leakage is a concern.
1 Basis of Design:
a Dow Corning Great Stuff
b Owens Corning ProPink ComfortSeal Gun Foam
2 Product Description: Closed-cell polyurethane foam sealant. Foam expands to thoroughly fill all voids and
cavities.
2.02 ACCESSORIES
A Accessories shall be provided as recommended by the sealant manufacturer for a complete installation.
Accessories include, but are limited to:
1 Substrate primers
2 Backing rods
3 Bond breaker tape
4 Caulking guns or other applicators
5 Seals and spacers
6 Masking tape
PART 3 - EXECUTION
3.01 EXAMINATION
A Ensure surfaces are clean, dry, and free of frost, dust, dirt, grease, oil, curing compounds, form release agents,
laitance, efflorescence, mildew, and previous films and coatings.
B Mill finish aluminum is not a suitable substrate for silicone sealants.
3.02 PREPARATION
A Prepare substrates and apply joint sealants in accordance with manufacturer’s instructions.
B For joints over 3/4-inch, get permission from the project architect prior to sealing. Modified joint details may be
required.
C Apply masking tape as required to ensure straight bead line and facilitate cleaning.
D Install sealant backing without gaps, twisting, stretching or puncturing backing material. Use gage to ensure
uniform depth to achieve correct profile, coverage and performance.
E Bond breaker: install on backside of joint where backing is not feasible.
3.03 SILICONE AND ELASTOMERIC JOINT SEALANT APPLICATION
A Use sealant-dispensing equipment to push sealant bead into opening. Fill joint opening to full and proper
configuration. Apply in continuous operation. Ensure sealant fills entire joint and firmly contacts all surfaces.
B Tooling: Before skinning or curing begins, tool sealant with metal spatula.
1 Provide concave, smooth, uniform, sealant finish. Eliminate air pockets and ensure complete contact on
both sides of joint opening.
2 Tool joints with one continuous stroke.
3 Do not use water, soap, or alcohol to facilitate tooling.
C Complete horizontal joints prior to vertical joints. Lap vertical sealant over horizontal joints.
D Cleaning: Remove masking tape and excess sealant.
1 Uncured sealant: Within 10 minutes of application, remove uncured sealant with solvent-dampened cloth,
wearing solvent-resistant gloves.
2 Completely cured sealant: Carefully cut or scrape away.
E Allow sealant to fully cure before adhesive is stressed. Use test specimens formed at time of sealant application
to verify curing time.
END OF SECTION
1.01 SUMMARY
A Work includes:
1 New interior hollow-metal doors and replacement exterior steel doors.
2 Hardware attachment and finishing of existing hollow metal doors to be salvaged and reused.
B This Section includes the following products manufactured in accordance with SDI Recommended Standards:
1 Doors: Flush, hollow or composite construction standard steel doors for interior and exterior locations.
2 Frames: Pressed steel frames for doors, sidelights, mullions, interior glazed panels, and other interior and
exterior openings of following type:
a Welded unit type, factory primed for field painting.
b Drywall Slip-On type, factory prefinished.
3 Assemblies: Provide standard steel door and frame assemblies as required for the following:
a Labeled and fire rated.
C Related Sections:
1 See interior design drawings for additional information on door finishes.
1.02 REFERENCES
A Reference Standards:
1 American National Standards Institute (ANSI)
a A250.3 – Test Procedure and Acceptance Criteria for Factory Applied Finish Coatings for Steel Doors
and Frames.
b A250.4 – Test Procedure and Acceptance Criteria for Physical Endurance for Steel Doors, Frames and
Frame Anchors
c A250.6 – Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames
d A250.7 – Nomenclature for Standard Steel Doors and Steel Frames
e A250.8 – Recommended Specifications for Standard Steel Doors and Frames
f A250.10 – Test Procedure and Acceptance Criteria for Prime Painted Steel Surfaces for Steel Doors
and Frames
g A250.11 – Recommended Erection Instructions for Steel Frames
h A250.13 – Testing and Rating of Severe Windstorm Resistant Components for Swinging Door
Assemblies.
2 American Society of Testing and Materials (ASTM)
a A653 – Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy Coated (Galvanized) by the Hot-Dip
Process,k General Requirements
b A569 – Steel, Carbon, Hot Rolled Sheet and Strip, Commercial Quality.
c A591 – Steel Sheet, Cold-Rolled, Electrolytic Zinc-Coated.
d A366 – Steel, Carbon, Cold-Rolled Sheet, Commercial Quality
3 Steel Door Institute (SDI)
a 117 - Manufacturing Tolerances Standard Steel Doors and Frames.
1.03 SUBMITTALS
A Product data for each type of door and frame specified, including details of construction, materials, dimensions,
hardware preparation, core, label compliance, profiles, and finishes.
B Shop drawings showing fabrication and installation of standard steel doors and frames. Include details of each
frame type, elevations of door design types, conditions at openings, details of construction, location and
installation requirements of door and frame hardware and reinforcements, and details of joints and connections.
Show anchorage and accessory items.
1 Provide schedule of doors and frames using same reference numbers for details and openings as those on
contract drawings.
1.04 QUALITY ASSURANCE
A Provide doors and frames complying with Steel Door Institute "Recommended Specifications Standard Steel
Doors and Frames" ANSI/SDI-100 and as herein specified.
B Fire-Rated Door Assemblies: Units that comply with NFPA 80, are identical to door and frame assemblies whose
fire resistance characteristics have been determined per ASTM E 152 and which are labeled and listed by UL,
Factory Mutual, Warnock Hersey, or other testing and inspecting organization acceptable to authorities having
jurisdiction.
Wilson Associates Architects and Planners Section 08 11 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
1 Oversize Fire-Rated Door Assemblies: For units exceeding sizes of tested assemblies, provide
manufacturer's certification that doors conform to all standard construction requirements of tested and
labeled fire-rated door assemblies except for size.
1.05 WARRANTY
A Provide a manufacturer’s and installer’s warranty, warranting all products and workmanship for a period of 2
years from the date of substantial completion. Warranty shall cover standard operation of the door, air leakage,
thermal protection, fire and smoke protection and other performance requirements as listed herein.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Field verify all rough opening widths and frame attachment points.
3.02 PREPARATION
A Advise Installers of other work about specific requirements relating to access door installation, including sizes of
openings to receive access door and frame, as well as locations of supports, inserts, and anchoring devices.
Furnish inserts and anchoring devices for access doors that must be built into other construction. Coordinate
delivery with other work to avoid delay.
B Coordination
1 Review hardware schedule for door and strike prep requirements.
2 Field verify all door locations and rough opening sizes.
3.03 INSTALLATION
Wilson Associates Architects and Planners Section 08 11 00 - 4
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
A Erect frames in accordance with ANSI A250.11.
1 Install frames plumb, rigid and in true alignment, and fasten them so as to retain their position and clearance
during construction of partitions.
2 Fill frames in masonry walls with mortar as wall is laid up.
3 Frames in solid plaster shall be completely filled with plaster.
4 When an additive is used in the plaster or mortar to prevent freezing, frames shall be coated on the inside
with a corrosion inhibiting bituminous material.
B Install doors plumb and in true alignment in a prepared opening and fasten them to achieve the maximum
operational effectiveness and appearance of the unit.
1 Coordinate installation of hardware, glass, and glazing.
C Finish Painting
1 Unless factory finish is specified herein, finish painting of doors and frames will be performed in the field.
There are to be no hi-lights.
3.04 ADJUST AND CLEAN
A Adjust hardware and panels after installation for proper operation.
B Remove and replace panels or frames that are warped, bowed, or otherwise damaged.
C Touch-up scratched, rusted or damaged surfaces. Use type of primer recommended for galvanized surfaces or
identical to that used for shop coat.
1 Clean doors and frames and protect from damage until completion of project.
2 Damaged work will be rejected and shall be replaced.
END OF SECTION
1.01 SUMMARY
A This Section includes the following:
1 Solid core doors with hardboard faces, embossed grain, and paint grade.
2 Hardware installation and finishing existing wood doors salvaged for re-use.
B Related Sections:
1 See interior design drawings for additional information on door finishes.
1.02 REFERENCE STANDARDS
A Wood Door Manufacturers Association (WDMA)
1 WDMA IS 1A – Interior Architectural Wood Flush Doors
2 WDMA IS 6A – Interior Architectural Stile and Rail Doors
1.03 SUBMITTALS
A General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification
Sections.
B Submit product data for each type of door, including details of core and edge construction and trim for openings.
C Submit copy of standard warranty.
D Submit shop drawings indicating location and size of each door, elevation of each kind of door, details of
construction, location and extent of hardware blocking, fire ratings, requirements for veneer matching and factory
finishing and other pertinent data.
1 For factory-machined doors, indicate dimensions and locations of cutouts for locksets and other cutouts
adjacent to light and louver openings.
E Submit samples for verification in the form and size indicated below:
1 Comer sections of doors approximately 12 inches (300 mm) square with door faces and edgings
representing the typical range of color and grain for each species of veneer and solid lumber required.
Finish sample with same materials proposed for factory-finished doors,
2 Frames for light openings, 6 inches (150 mm) long, for each material, type, and finish required.
1.04 QUALITY ASSURANCE
A Quality Standard: Comply with the following standard:
1 AWI Quality Standard: "Architectural Woodwork Quality standards,, of the Architectural Woodwork
Institute for grade of door, core, construction, finish, and other requirements.
2 Single-Source Responsibility: Obtain doors from one source and by a single manufacturer.
1.05 WARRANTY
A Door Manufacturer's Warranty: Warranty shall cover defective doors that warp (bow, cup, or twist) more than 1/4
inch (6.35 mm) in a 42-by-84-inch (1067-by-2134-mm) section or that show telegraphing of core construction in
face veneers exceeding 0.01 inch in a 3-inch (0.25 min in a 75-mm) span, or do not conform to tolerance
limitations of referenced quality.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine installed door frames prior to hanging door:
B Verify that frames comply with indicated requirements for type., size, location, and swing characteristics and
have been installed with plumb jambs and level heads.
C Reject doors with defects.
D Do not proceed with installation until unsatisfactory conditions have been corrected.
3.02 INSTALLATION
A Hardware: For installation see Division 8 Section "Door Hardware.”
B Manufacturer's Instructions: Install wood doors to comply with manufacturer's instructions and referenced quality
standard and as indicated.
1 Install fire-rated doors in corresponding fire-rated frames according to requirements of NFPA 80.
2 Fitting Clearances for Non-Fire-Rated Doors: Provide 1/8 inch (3.2 mm) at jambs and heads, 1/16 inch (1.6
mm) per leaf at meeting Stiles for pairs of doors, and 1/8 inch (3.2 mm) from bottom of door to top of
decorative floor finish or covering. Where threshold is shown or scheduled, provide 1/4-inch (6.4-mm)
clearance from bottom of door to top of threshold.
3 Bevel non-fire-rated doors 1/8 inch in 2 inches (3-1/2 degrees) at lock and hinge edges.
4 Bevel fire-rated doors 1/8 inch in 2 inches (3-1/2 degrees) on lock edge; trim Stiles and rails only to extent
permitted by labeling agency.
C Factory-Fitted Doors: Align in frames for uniform clearance at each edge.
3.03 ADJUSTING AND PROTECTION
A Operation: Rehang or replace doors that do not swing or operate freely.
B Finished Doors: Refinish or replace doors damaged during installation.
C Protect doors as recommended by door manufacturer to ensure that wood doors will be without damage or
deterioration at the time of Substantial Completion.
END OF SECTION
1.01 SUMMARY
A Section Includes: Integrated door opening assemblies including metal frame, integrated doors, smoke seals and
associated finish hardware.
1.02 REFERENCES
A Reference Standards:
1 ANSI A250.4 – Steel Doors and Frames Physical Characteristics
2 ANSI A156.1 – Butts and Hinges
3 ANSI A156.2 – Bored Locks and Latches
4 ANSI A156.3 – Exit Devices
5 ANSI A156.4 – Door Controls – Door Closers
6 ANSI A156.5 – Auxiliary Locks and Associated Products
7 ANSI A156.6 – Architectural Door Trim
8 ANSI A156.7 – Template Hinge Dimensions
9 ANSI A156.8 – Door Controls – Overhead Holders
10 ANSI A156.15 – Closer Holder Release Devices
11 ANSI A156.16 – Auxiliary Hardware
12 ANSI A156.18 – Material and Finishes
13 ANSI A156.26 – Continuous Hinges
14 ANSI A156.32 -Integrated Door Opening Assemblies
15 ANSI/SDI-100 – Recommended Specification for Standard Steel Doors and Frames
16 SDI-105 – Recommended Erection Instructions for Steel Frames
17 SDI-107 – Hardware on Steel Doors (reinforcement application)
1.03 SUBMITTALS
A Product Data: Manufacturer’s catalogue cut sheets, clearly marked for each component item, including
installation details, material descriptions, dimensions of individual components and profiles and finishes.
B Shop Drawings: Hardware options, anchors, and other components. Provide electrified hardware details with
information on:
1 Sequence of operations
2 Elevation
3 Point-to-point wiring diagram
1.04 CLOSEOUT SUBMITTALS
A Operation and Maintenance Manual
1.05 QUALITY ASSURANCE
A Provide integrated door assemblies complying with the most current version of NFPA 80 and UL10C listed and
labeled by a Nationally Recognized Independent Testing Laboratory.
B Comply with all applicable accessibility guidelines.
1.06 WARRANTY
A The complete integrated opening assembly (doors, frames and locking hardware) except as noted below shall be
warranted to be free of defects in material and workmanship under normal use for a period of five (5) years from
date of substantial completion.
1 Door finishes: 3-years
2 Continuous Hinges: 10-years
3 Closers: 10-years
4 Electrical Components: 3-years
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine rough openings and other site conditions for compliance with requirements for installation tolerances,
labeled fire door assembly construction, wall and floor construction and other conditions effecting performance.
B Examine rough-in for electrical power systems to verify actual locations of wiring connections before electrified
door hardware installation.
C Proceed with installation only after unsatisfactory conditions have been corrected.
3.02 INSTALLATION
A Steel doors shall be prepared for all non-factory installed hardware per ANSI/BHMA A156.115.
B Installation shall be in accordance with DHI A115.IG.
C Install work in accordance with manufacturer’s written instructions.
D Set frames plumb and square and brace until adjacent wall or finish is constructed and securely anchored thereto.
Furnish necessary clips, fastenings and anchorages and conceal unless otherwise noted.
E Fire doors shall be installed per NFPA 80 and all other applicable building codes and regulations.
F Set units level, plumb and true to line and location. Adjust and reinforce attachment substrates as necessary for
proper installation and operation.
G Install all non-factory installed hardware items using only fasteners provided or authorized by manufacturer.
3.03 DOOR CLOSING DEVICES
A Door closing devices shall be installed in accordance with the templates and printed instructions supplied by the
manufacturer of the devices.
B Door closing devices with adjustable spring power shall be adjusted for proper door operation and compliance
with all applicable codes and regulations.
3.04 ADJUSTING
A Adjust and check each operating item of door hardware and each door to ensure proper operation or function of
every unit.
END OF SECTION
1.01 SUMMARY
A Section Includes: Replacement doors for existing dumbwaiter.
1.02 SUBMITTALS
A Product Data: For each type of product, include manufacturer’s product data including the construction details,
fire ratings, material descriptions, dimensions and profiles and manufacturer standard finish options.
1.03 CLOSEOUT SUBMITTALS
A Operation and Maintenance Data
B Warranty Documentation
1.04 WARRANTY
A Manufacturer’s Warranty: Warrant the work of this section against manufacturing defects in materials and
finishes for a period of 1-year from the date of Substantial Completion.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine substrates for compliance with requirements for installation tolerances and other conditions affecting
performance of the Work.
3.02 INSTALLATION
A Comply with manufacturer’s written instructions for installation.
B Install General Access Doors for access to the Type I hood vent and elsewhere, as required by the Mechanical
Plans, for access to HVAC equipment and ductwork.
C Install the Dumbwaiter doors in existing dumbwaiter shaft. Replace existing doors. Match existing door sizes
with replacements.
3.03 ADJUSTING
A Adjust doors and hardware, after installation, for proper operation.
END OF SECTION
1.01 SUMMARY
A Section Includes: Smoke detector activated elevator door smoke containment screen and control system designed
to provide a tight-fitting, smoke- and draft-control assembly.
1 Provide one on existing elevator, 2nd floor only.
2 Provide two on existing dumbwaiter, main floor and 2 nd floor only.
1.02 REFERENCES
A Reference Standards:
1 ASTM International (ASTM)
a ASTM A240/240M – Standard Specification for Heat Resisting Chromium and Chromium-Nickle
Stainless Steel Plate, Sheet and Strip for Pressure Vessels.
2 ICC Evaluation Service ES AC77 – Acceptance Criteria for Smoke-Containment Systems Used with Fire-
Resistive Elevator Hoistway Doors and Frames.
3 ICC Evaluation Service Report ESR-1136
4 National Fire Protection Association (NFPA)
a NFPA 70 – National Electric Code
b NFPA 105 – Recommended Practice for the Installation of Smoke-Control Door Assemblies
c NFPA 72 – National Fire Alarm Code
5 International Building Code, 2015 (IBC)
a Section 3006.1
6 Underwriters Laboratories (UL)
a UL 268 – Smoke Detectors for Fire Protective Signaling Systems
b UL 508 – Industrial Control Equipment
c UL 864 – Control Units for Fire Protective Signaling Systems
d UL 1784 – Air Leakage Tests for Door Assemblies
1.03 SUBMITTALS
A Product Data – Provide product data for assembly.
B Shop Drawings: Include door width and height, jamb width, jamb and head projection, screen width, mounting
height, and housing width. Show and identify related work performed under other sections of the specifications.
C Samples – Provide samples showing an accurate representation of the visible door and housing assembly at the
ceiling. Provide color sample options where available.
1.04 CLOSEOUT SUBMITTALS
A Operation and maintenance instructions or videos.
B Provide contact information and instructions for insepctors capable of assessing units after exposure to fire event.
C Provide instructions for painting door frame and/or auxiliary rails to avoid loss of performance.
D Manufacturer’s warranties.
1.05 QUALITY ASSURANCE
A Manufacturer shall maintain a quality control program in accordance with ICC-ES Acceptance Criteria 77.
B All materials to be UL Listed.
1.06 WARRANTY
A Manufacturer’s Warranty: 1-year standard warranty.
B Maintenance and Testing:
1 Perform minimum semi-annual maintenance and testing on each smoke containment system as required by
the manufacturer’s warranty, code agency evaluation reports, and as required by local authority having
jurisdiction.
2 Provide test documentation.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine substrates upon which work will be installed.
1 Verify related work performed under other sections is complete and in accordance with Shop Drawings.
2 Verify wall surfaces and elevator door frames are acceptable for installation of smoke containment system
components.
3 Verify existing field painted elevator door frames to be used for screen adherence have been repainted in
accordance with smoke containment system manufacturer’s instructions or they have the original factory
paint.
B Coordinate with responsible entity to perform corrective work on unsatisfactory substances.
C Commencement of work by installer is acceptance of substrate.
3.02 INSTALLATION
A Install smoke containment system components in accordance with manufacturer’s installation instructions.
3.03 QUALITY CONTROL
A Field Test: Follow manufacturer’s cycle test procedures.
1 Notify Owner’s Representative, local Fire Marshal, alarm sub-contractor and elevator sub-contractor
minimum one week in advance of scheduled testing.
2 Complete maintenance service record.
3.04 SYSTEM STARTUP
A Demonstrate required testing and maintenance procedures to Owner’s Representative.
3.05 MAINTENANCE
A Perform minimum semi-annual maintenance and testing on each smoke containment system as required by the
manufacturer’s warranty, code agency evaluation reports, and as required by local authority having jurisdiction.
B Retain permanent record of tests.
END OF SECTION
1.01 SUMMARY
A Section Includes: Pass-thru aluminum service windows as indicated on drawings.
1.02 SUBMITTALS
A Product Data: Submit manufacturer’s technical product data substantiating that products comply.
B Shop Drawings: Submit for fabrication and installation of windows. Include details, elevations and installation
requirement of finish hardware and cleaning.
1.03 WARRANTY
A Manufacturer’s Warranty: All material and workmanship shall be warranted against defects for a period of one
(1) year from the date of substantial completion.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 INSTALLATION
A Install window in accordance with manufacturer’s printed instructions and recommendations. Repair damaged
units as directed or replace with new units.
3.02 CLEANING
A Clean frame and glazing surfaces after installation, complying with requirements contained in the manufacturer’s
instructions. Remove excess glazing sealant compounds, dirt or other substances.
END OF SECTION
1.01 SUMMARY
A Section Includes: Curb-mount skylights
1.02 REFERENCES
A Reference Standards
1 American Society of Testing and Materials (ASTM)
a D542 – Standard Test Method for Index of Refraction of Transparent Organic Plastics
b D635 – Standard Test Method for Rate of Burning and/or Extent and Time of Burning of Plastics in a
Horizontal Position.
c D638 – Standard Test Method for Tensile Properties of Plastcis
d D790 – Standard Test Method for Flexural Properties of Unreinforced and Reinforced Plastics and
Electrical Insulating Materials
e D1003 – Standard Test Method for Haze and Luminous Transmittance of Transparent Plastics
f D1929 – Standard Test Method for Determining Ignition Temperature of Plastics
g D2843 – Standard Test Method for Density of Smoke from the Burning or Decomposition of Plastics.
1.03 SUBMITTALS
A Product Data – For each type of skylight specified, including details of construction relative to materials,
dimensions of individual components, profiles, finishes, and glazing light transmission and thermal
characteristics.
B Shop Drawings: Show fabrication and installation of skylights, including plans, elevations, sections, details of
components, and attachments to other units of Work.
C Samples : Manufacturer’s color charts showing full range of colors available for each type of skylight glazing,
retainer, frame, and curb indicated.
1.04 QUALITY ASSURANCE
A Thermal response characteristics: Provide verification of heat distortion temperature when tested per ASTM
D648 of at least 200 deg F.
1.05 WARRANTY
A Product Warranty: Provide a 5-year written warranty signed by the manufacturer, agreeing to repair or replace
work that exhibits defects in materials or workmanship and guaranteeing weathertight and leak-free performance,
within the tolerances specified herein. Warranty shall be valid starting the date of Substantial Completion. Items
covered under this warranty shall include:
1 Weathertight construction
2 Thermal resistance
3 Finish, including peeling, chipping and abnormal aging or deterioration.
B Installation Warranty: Provide a 2 year installers warranty covering defects in installation as well as labor replace
defective products.
PART 2 - PRODUCTS
3.01 EXAMINATION
A Examine substrates and conditions, with installer present, for compliance with requirements for installation
tolerances and other conditions affecting skylight performance.
1 Proceed with installation only after unsatisfactory conditions have been corrected.
3.02 PREPARATION
A Remove existing roofing in the area where the new skylight will be installed, down to the plywood roof deck.
B Located existing joists and align new skylight between existing joists. Verify joist spacing is appropriate for
skylight size.
C Cut hole in existing roof sheathing per skylight manufacturer’s instructions.
D Install curb per manufacturer’s instructions.
E Metal Protection:
1 Where aluminum will contact dissimilar metals, protect against galvanic action by painting contact surfaces
with primer or by applying sealant or tape recommended by manufacturer for this purpose.
2 Where aluminum will contact concrete or masonry, protect against corrosion by painting contact surfaces
with bituminous paint.
3 Where aluminum will contact pressure-treated wood, separate dissimilar materials by methods
recommended by manufacturer.
3.03 INSTALLATION
A General: Comply with manufacturer’s written instructions for protecting, handling, and installing skylight
components.
B Re-install vapor barriers, roof insulation, roofing, and flashing as required to assure that each elements are
waterproof and weathertight. Install roofing felt in a shingle type fashion from the bottom of the roof and
working up. Lap joints a minimum of 6-inches and tape.
C Anchor units securely to supporting structural curb, adequate to withstand lateral and thermal stresses as well as
inward and outward loading pressures.
D Counter Flashing: Counter flashing is required as a component of the skylight. Install to provide adequate
waterproof overlap with roofing or roof flashing (as counterflashing). Seal with thick bead of mastic sealant.
3.04 CLEANING AND PROTECTION
A Clean exposed metal and plastic surfaces according to manufacturer’s instructions. Touch up damaged metal
coatings.
B Clean and polish skylight units, inside and out, not more than 5 days prior to date of substantial completion.
END OF SECTION
1.01 SUMMARY
A Section Includes: Door hardware and related accessories including:
1 Door locks
2 Door handles and trim
3 Closers
4 Electronic Access Controls
5 Related accessories
B NOTE: New door hardware shall be applied on all doors, including existing doors that are salvaged.
C Related Sections:
1 See interior design drawings for additional information on hardware finishes.
1.02 REFERENCES
A Reference Standards
1 American National Standards Institute (ANSI)
a A117.1 – Accessible and Usable Buildings and Facilities
b A156.2 – Bored and Preassembled Locks and Latches
c A156.3 – Exit Devices
d A156.4 – Door Controls – Closers
e A156.5 – Auxiliary Locks and Associated Products
f A156.12 – Interconnected Locks
g A156.13 – Mortise Locks and Latches Series 1000
2 Underwriters Laboratories (UL)
a Fire Resistance Directory
1.03 SUBMITTALS
A Product Data – Manufacturer’s data sheets on each product to be used, including:
1 Preparation instructions and recommendations
2 Storage and handling requirements and recommendations
3 Installation methods
B Shop Drawings: Manufacturer’s approved shop drawings are required detailing the application of each product
specified.
C Schedule of Hardware: Comply with scheduling sequence and vertical format in DHI’s “Sequence and Format for
Hardware Schedule.” Prepare the schedule as follows:
1 List each opening, door size, door hand, door and frame material, door label, manufacturer’s number and
finish.
2 Any deviation in hardware listed from that specified must be approved by the Architect in writing prior to
Bid Opening.
D Samples – For each product specified, provide a selection sample representing the manufacturer’s full range of
available colors and finishes.
1.04 QUALITY ASSURANCE
A Manufacturer’s qualifications: All equipment specified in this section will be provided by a manufacturer with a
minimum of ten years experience manufacturing door hardware.
B Hardware supplier shall have and maintain a factory direct status with all manufacturer’s specified or approved
during the course of the project.
C Provide hardware from a factory authorized distributor. All components of each hardware item shall be by the
same manufacturer.
D Provide a door hardware consultant to coordinate security requirements and installation. The door hardware
consultant shall:
1 Be an employee of the supplier,
2 Be knowledgable on local, state, and federal life safety fire codes, and accessibility codes and requirements
to assist the Architect when necessary.
3 Assist in developing the keying schedule by meeting with the Owner and Architect, and make at least two
job site inspections and one final inspection to ensure that all hardware has been properly installed according
to the manufacturer’s directions.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Do not begin installation until substrates have been properly prepared.
B Where fasteners will be used, verify conditions to verify appropriate fastening devices are being used to provide a
secure anchorage.
C Coordinate electrical requirements for automatic controls.
D Evaluation and Assessment: If required, evaluate existing substrates to receive work to assess their suitability for
proper installation/application of products. Proceeding with the work will be understood as acceptance of the
preexisting conditions.
E Examine existing doors that are scheduled to be salvaged for use in the new work. Verify doors are properly
prepared for hardware installation.
3.02 PREPARATION
A Clean surfaces prior to installation, using the methods recommended by the manufacturer.
B Provide solid blocking where required for installation.
C Locate and place hardware on work accurately. Obtain templates from manufacturer where applicable. Install
permanently using proper nails, screws or bolts, matching finish of hardware. Self-tapping sheet metal screws are
not acceptable for hardware installation. All closers and exit devices on wood doors shall be thru-bolted.
D Drill holes through doors or frames shall be no larger than the minimum required for attachment. Excessively
large holes will be rejected.
E Provide reinforcement at existing doors that required additional support for hardware attachment.
3.03 INSTALLATION
A The following mounting guide is to be used for all conditions where more specific information is not provided on
the plans or schedules.
1 Top Hinge: 5-inches, header rabbet to top of hinge.
2 Bottom Hinge: 10-inch, finish floor to bottom of hinge.
3 Center Hinge(s): Equal spacing between top and bottom hinges.
4 Locks and latches: 38-inch, finish floor to center of lock case and strike.
5 Deadlocks: 48-inches finish floor to center of cylinder. Vary as necessary to avoid pulls.
6 Exit Devices: 38-inch, finish floor to center of cross bar.
7 Push Plates: 48-inches, finish floor to center of plate.
8 Door Pulls: 42-inches, finish floor to center of pull.
9 Panic Hardware: 38-inches to centerline of crossbar
B Installation Tolerances:
1 Between Doors and Frames: 1/8-inch
2 Sills (no threshold): 3/8-inch
3 Sills (threshold): ¾-inch
4 Meeting edges of dbl doors: 1/8-inch
3.04 CLOSEOUT ACTIVITIES
A Switch cores to permanent and provide all keys to Owner.
B Deliver any adjusting tools to Owner, properly tagged and identified.
END OF SECTION
Schedules
HW SET # 01
Openings
01 02 03 04 05 06
131C
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
1 EA RIM CYLINDER 20-057 ICX 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
HW SET # 02
Openings
101A
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1HW 5 X 4.5 NRP 619 IVE
1 EA ARMORED DOOR CORD K-DL38A 689 KEE
1 EA ELEC PANIC HARDWARE RX-QEL-98-NL-CON 24 VDC 719 VON
1 EA RIM CYLINDER 20-057 ICX 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA SURF. AUTO OPERATOR 9542 HL/D MS AS REQ (120/240 ANDKB LCN
VAC)
2 EA SURFACE MOUNT BOX 8310-819S LCN
2 EA ACTUATOR, WALL MOUNT 8310-853T 630 LCN
1 EA GASKETING 488SBK PSA BK ZER
1 EA DOOR SWEEP 8198BK BK ZER
1 EA WIRE HARNESS CON-192 SCH
1 EA WIRE HARNESS CON-6W SCH
1 EA DOOR CONTACT 679-05HM/WD AS REQ'D BLK SCE
1 EA POWER SUPPLY PS902 900-2RS 900-BBK 120/240 VON
VAC
1 ACCESS CONTROL - WORK OF
DIVISION 28
1 PERIMETER SEALS BY
DOOR/FRAME MANUFACTURER
HW SET # 05
Openings
102 158 159 200 228
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1 4.5 X 4.5 NRP 619 IVE
1 EA POWER TRANSFER EPT10 CON 695 VON
1 EA EU STOREROOM LOCK ND80TDEU BRW RX 12V/24V DC 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA SURFACE CLOSER SC81 REG OR PA AS REQ 619 FAL
1 EA KICK PLATE 8400 10" X 2" LDW B-CS 619 IVE
1 EA WALL STOP WS406/407CVX BLK IVE
1 EA GASKETING 488SBK PSA BK ZER
1 EA WIRE HARNESS CON-192P SCH
VERIFY LENGTH
1 EA WIRE HARNESS CON-6W SCH
1 POWER SUPPLY - WORK OF
DIVISION 28
HW SET # 07
Openings
120A
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1HW 5 X 4.5 NRP 619 IVE
1 EA ELEC PANIC HARDWARE RX-QEL-98-NL-CON 24 VDC 619 VON
1 EA RIM CYLINDER 20-057 ICX 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA OH STOP 90S 619 GLY
1 EA SURF. AUTO OPERATOR 9542 HL/D MS AS REQ (120/240 ANDKB LCN
VAC)
2 EA SURFACE MOUNT BOX 8310-819S LCN
2 EA ACTUATOR, WALL MOUNT 8310-853T 630 LCN
1 EA RAIN DRIP 11BK BK ZER
1 EA DOOR SWEEP 8198BK BK ZER
1 EA THRESHOLD 65BK BK ZER
1 EA WIRE HARNESS CON-192 SCH
1 EA WIRE HARNESS CON-6W SCH
1 EA DOOR CONTACT 679-05HM/WD AS REQ'D BLK SCE
1 EA POWER SUPPLY PS902 900-2RS 900-BBK 120/240 VON
VAC
1 ACCESS CONTROL - WORK OF
DIVISION 28
1 PERIMETER SEALS BY
DOOR/FRAME MANUFACTURER
HW SET # 09
Openings
121B 131A
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
1 EA RIM CYLINDER 20-057 ICX 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
HW SET # 10
Openings
121B 122
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
1 EA ARMORED DOOR CORD K-DL38A 689 KEE
1 EA PANIC HARDWARE LD-9827-EO-LBR 619 VON
1 EA ELEC PANIC HARDWARE RX-QEL-9827-NL-LBR 24 VDC 619 VON
1 EA RIM CYLINDER 20-057 ICX 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA WIRE HARNESS CON-192 SCH
1 EA WIRE HARNESS CON-6W SCH
1 EA DOOR CONTACT 679-05HM/WD AS REQ'D BLK SCE
1 EA POWER SUPPLY PS902 900-2RS 900-BBK 120/240 VON
VAC
1 ACCESS CONTROL - WORK OF
DIVISION 28
HW SET # 12
Openings
125 126 127 157 218 229
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1 4.5 X 4.5 NRP 619 IVE
1 EA PRIVACY WITH INDICATOR L9456T 18A L583-363 L283-722 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA SURFACE CLOSER SC81 REG OR PA AS REQ 619 FAL
1 EA KICK PLATE 8400 10" X 2" LDW B-CS 619 IVE
1 EA WALL STOP WS406/407CVX 619 IVE
1 EA GASKETING 488SBK PSA BK ZER
HW SET # 13
Openings
201
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1 4.5 X 4.5 NRP 619 IVE
1 EA PRIVACY WITH INDICATOR L9456T 18A L583-363 L283-722 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA KICK PLATE 8400 10" X 2" LDW B-CS 619 IVE
1 EA WALL STOP WS406/407CVX 619 IVE
1 EA GASKETING 488SBK PSA BK ZER
HW SET # 15
Openings
202 203
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1HW 4.5 X 4.5 NRP 619 IVE
1 EA FIRE EXIT HARDWARE F-25-R-L-BE-BRW 619 FAL
1 EA SURFACE CLOSER SC71A REG OR PA AS REQ 619 FAL
1 EA KICK PLATE 8400 10" X 2" LDW B-CS 619 IVE
1 EA WALL STOP WS406/407CVX 619 IVE
1 EA GASKETING 488SBK PSA BK ZER
HW SET # 19
Openings
235A 235C 241 242
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1 4.5 X 4.5 NRP 619 IVE
1 EA STOREROOM LOCK ALX80T BRW 619 SCH
1 EA FSIC CORE 23-030 C123 619 SCH
1 EA KICK PLATE 8400 10" X 2" LDW B-CS 619 IVE
1 EA WALL STOP WS406/407CVX 619 IVE
3 EA SILENCER SR65 GRY IVE
HW SET # 20
Openings
235B
Each door or doors to have:
QTY DESCRIPTION CATALOG NUMBER FINISH MFR
3 EA HINGE 5BB1 4.5 X 4.5 NRP 619 IVE
1 EA PASSAGE SET ND10S BRW 619 SCH
1 EA SURFACE CLOSER SC71 REG OR PA AS REQ 619 FAL
1 EA ARMOR PLATE 8400 24" X 2" LDW B-CS 630 IVE
1 EA WALL STOP WS406/407CVX 619 IVE
1 EA GASKETING 488SBK PSA BK ZER
1 EA THRESHOLD 566BK-223 619 ZER
NOTE 1: INSTALL STOP ON BASE, TOP OR BOTTOM OF DOOR, ON WALL, OR OTHER FIXTURE AS
APPROPRIATE.
VERIFY THRESHOLD DOOR SHOE DETAIL.
PROVIDE CLASSROOM FUNCTION AT MEMORY CARE, ENTRANCE FUNCTION AT INDEPENDENT
LIVING
NOTE: INSTALL STOP ON BASE, TOP OR BOTTOM OF DOOR, ON WALL, OR OTHER FIXTURE AS
APPROPRIATE.
VERIFY HINGE SIZE.
JACK AND JILL BATH OPERATION.
IF EXTERIOR OCCUPIED WHEN LIT IS OFF PERSON CAN ENTER BATHROOM.
ONCE IN PUSH TO LOCK OR MOTION SENSOR TO LOCK ELECTRIC STRIKE.
EXITING ETHER DOOR WILL RELEASE BOTH ELECTRIC STRIKES..
NOTE: INSTALL STOP ON BASE, TOP OR BOTTOM OF DOOR, ON WALL, OR OTHER FIXTURE AS
APPROPRIATE.
VERIFY HINGE SIZE. PROVIDE OVERHEAD STOP IF WALL STOP WILL NOT WORK.
1.01 SUMMARY
A Section Includes: Fixed blade louvers.
1.02 REFERENCES
A Definitions:
1 Louver terminology: Definitions of terms for metal louvers contained in AMCA 501 apply to this Section,
unless otherwise defined in this Section or in referenced standards.
2 Standard Free Area: Free area of louver 48-inches wide by 48-inches high, identical to that provided.
3 Maximum Standard Air Flow: Airflow at point of beginning water penetration through a louver 48-inches
wide by 48-inches high, identical to that provided.
4 Drainable-Blade Louver: Louver designed to collect and drain water to exterior at sill by means of gutters in
front edges of blades and channels in jambs and mullions.
5 Minimum Weather Louver Effectiveness: Weather louver effectiveness rating shall be based on tests
conducted in accordance with AMCA Standard 500-L.
B Reference Standards:
1 Air Movement and Control Association International (AMCA):
a AMCA 500-L - Laboratory Methods of Testing Louvers for Rating.
b AMCA 501 - Application Manual for Air Louvers.
c AMCA 511 - Certified Ratings Program - Product Rating Manual for Air Control Devices.
d AMCA 512 - AMCA Listing Label Program. Water and Air Certification.
e AMCA 512 - AMCA Listing Label Program. Water, Air, Wind-Driven Rain Certification.
f AMCA 512 - AMCA Listing Label Program. Air Certification.
g AMCA 540 - Test Method for Louvers Impacted by Windborne Debris.
1) K6744X - AMCA 540 Basic Lev D.
2) K6746X - AMCA 540 Basic Lev D or Enhanced Level E.
3) K6746MD - AMCA 540 Basic Lev D or Enhanced Level E.
4) SCH501X - AMCA 540 Enhanced Level E.
5) K605MD - AMCA 540 Enhanced Level E.
6) SCH601MD (w VCD-40) - AMCA 540 Enhanced Level E.
7) SCV660MD - AMCA 540 Enhanced Level E.
8) SCH601MD - AMCA 540 Enhanced Level E.
h AMCA 550 - Test Method for High Velocity Wind Driven Rain Resistant Louvers.
1) SCV501MD - AMCA 550.
2) SCC550 - AMCA 550.
3) SCC550MD - AMCA 550.
4) SCV302 - AMCA 550.
5) SCV302MD - AMCA 550.
6) SCH601MD (w VCD-40) - AMCA 550.
7) SCV660MD - AMCA 550.
2 ASTM International (ASTM):
a ASTM A 653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-
Coated (Galvannealed) by the Hot-Dip Process.
b ASTM A 666 - Standard Specification for Annealed or Cold Worked Austenitic Stainless Steel Sheet,
Strip, Plate, and Flat Bar.
c ASTM A 788 - Standard Specification for Steel Forgings, General Requirements.
d ASTM B 26 - Standard Specification for Aluminum Alloy Sand Castings.
e ASTM B 209 - Standard Specification for Aluminum and Aluminum Alloy Sheet and Plate.
f ASTM B 221 - Standard Specification for Aluminum and Aluminum Alloy Rolled or Cold Finished
Bar, Rod, and Wire.
g ASTM C 578 - Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation.
h ASTM C 612 - Standard Specification for Mineral Fiber Block and Board Thermal Insulation.
i ASTM D822 - Standard Practice for Filtered Open-Flame Carbon-Arc Exposures of Paint and Related
Coatings.
j ASTM D 1187 - Standard Specification for Asphalt Base Emulsions for Use as Protective Coatings for
Wilson Associates Architects and Planners Section 08 90 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
Metal.
k ASTM D4214 - Standard Test Methods for Evaluating the Degree of Chalking of Exterior Paint Films.
l ASTM D2244 - Standard Test Method for Calculation of Color Differences From Instrumentally
Measured Color Coordinates.
m ASTM E 90 - Standard Test Method for Laboratory Measurement of Airborne Sound Transmission
Loss of Building Partitions and Elements.
n ASTM E330 - Standard Test Method for Structural Performance of Exterior Windows, Doors,
Skylights and Curtain Walls by Uniform Static Air Pressure Difference.
o ASTM E 413 - Classification for Rating Sound Insulation.
3 American Architectural Manufacturer's Association (AAMA).
a AAMA 611 - Voluntary Specification for Anodized Architectural Aluminum.
b AAMA 2603 - Voluntary Specification. Performance Requirements and Test Procedures For.
Pigmented Organic Coatings on Aluminum Extrusions.
c AAMA 2604 - High Performance Organic Coatings on Architectural Extrusions and Panels.
d AAMA 2605 - Voluntary Specification, Performance Requirements and Test Procedures for Superior
Performing Organic Coatings on Aluminum.
4 National Association of Architectural Metal Manufacturers (NAAMM): Metal Finishes Manual for
Architectural and Metal Products.
5 Sheet Metal and Air Conditioning Contractors' National Association (SMACNA): Architectural Sheet Metal
Manual.
6 National Electrical Manufacturers Association (NEMA).
7 Underwriters Laboratories, Inc. (UL).
1.03 SUBMITTALS
A Product Data: Manufacturer’s data sheets for each product and assembly specified.
B Shop Drawings: Include plans, elevations, sections and details showing profiles, angles, and spacing of elements.
Show unit dimensions related to wall openings and adjacent construction. Show profiles of frames at jambs,
heads, and sills, along with anchorage details and locations.
1 Verify openings by field measurements before fabrication and indicate measurements on shop drawings.
2 For installed products indicated to comply with design loadings, include structural analysis data signed by a
licensed structural engineer in the jurisdiction where the project is located.
3 Wiring Diagrams: Detail power, signal and control systems for motorized adjustable louvers and
differentiate between manufacturer-installed and field-installed wiring.
C Selection Samples: Two complete color charts showing the full range of colors available for units with factory-
applied color finishes.
1.04 QUALITY ASSURANCE
A AMCA Standard 500-L: Air performance, water penetration and air leakage ratings shall be determined in
accordance with Air Movement and Control Association International Inc (AMCA) Standard 500, "Laboratory
Methods of Testing Louvers for Rating."
B AMCA Standard 511: Air performance, water penetration and air leakage ratings shall be licensed in accordance
with Air Movement and Control Association International Inc. (AMCA) Standard 511, "Certified Ratings
Program for Air Control Devices," latest edition.
C UL and NEMA Compliance: Provide motors and related components for motor-operated adjustable louvers that
are listed and labeled by UL and comply with applicable NEMA standards.
1.05 WARRANTY [Coordinate with 01 78 36 – Warranties]
A Manufacturer’s Warranty: Provide manufacturer’s standard warranty for manufacturing defects for a period of 1-
year from the date of substantial completion.
B Finish Warranty: Provide manufacturer’s standard finish warranty for a period of 5-years.
PART 2 - PRODUCTS
2.01 PRODUCTS
A Louvers shall be mechanically fastened to building construction and furnished with bird screen, insect screen, sill
pans, supports, installation hardware and all finish items.
B Louver shall be of welded construction.
C Louvers to be constructed of galvanized sheet steel, ASTM A653A 653M, G90 (Z275) zinc coating, mill
phosphatized.
D Fasteners: Of same basic metal and alloy as fastened metal or 300 series stainless steel.
END OF SECTION
1.01 SUMMARY
A Section Includes: Standard Gypsum Wallboard, Fire-Resistance Rated Gypsum Wallboard, Mold and Moisture
Resistant Gypsum Wallboard, and Cement Board.
1.02 REFERENCES
A American National Standards Institute (ANSI)
1 ANSI A 108.11 – Interior Installation of Cementitious Backer Units
2 ANSI A 118.9 – American National Standard Specification for Test Methods and Specifications for
Cementitious Backer Units
B American Society for Testing and Materials (ASTM) International
1 ASTM C 473 – Standard Test Method for Physical Testing of Gypsum Panel Products
2 ASTM C 840 – Standard Specification for Application and Finishing of Gypsum Board
3 ASTM C 919 – Standard Practice for Use of Sealants in Acoustical Applications
4 ASTM C 920 – Standard Specification for Elastomeric Joint Sealants
5 ASTM C 1002 – Standard Specification for Steel Self-Piercing Tapping Screws for the Application of
Gypsum Panel Products or Metal Plaster Bases to Wood Studs or Steel Studs
6 ASTM C 1177 – Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing
7 ASTM C 1178 – Standard Specification for Coated Glass Mat Water Resistant Gypsum Backing Panel
8 ASTM C 1280 – Standard Specification for Application of Gypsum Sheathing
9 ASTM C 1325 – Standard Specification for Non-Asbestos Fiber-Mat Reinforced Cementitious Backer Units
10 ASTM C 1396 – Standard Specification for Gypsum Board
11 ASTM C 1629 – Standard Classification for Abuse Resistant Nondecorated Interior Gypsum Panel Products
and Fiber Reinforced Cement Panels
12 ASTM C 1658 – Standard Specification for Glass Mat Gypsum Panels
13 ASTM D 3273 – Standard Test Method for Resistance to Growth of Mold on the Surface of Interior
Coatings in an Environmental Chamber
14 ASTM E 72 – Standard Test Methods of Conducting Strength Tests of Panels for Building Construction.
15 ASTM E 90 – Standard Test Method for Laboratory Measurement of Airborn Sound Transmission Loss of
Building Partitions and Elements.
16 ASTM E 96 – Standard Test Methods for Water Vapor Transmission of Materials.
17 ASTM E 119 – Standard Test Method for Fire Tests of Building Construction and Materials.
18 ASTM E 136 – Standard Test Method for Behavior of Materials in a Vertical Tub Furnace at 750.
19 ASTM G 21 – Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi.
C Gypsum Association (GA)
1 GA-214 – Recommended Levels of Gypsum Board Finish
2 GA-216 – Application and Finishing of Gypsum Panel Products
3 GA-253 – Application of Gypsum Sheathing
1.03 SUBMITTALS
A Product Data including all materials used in the finishing of gypsum wall sheathing, texture, and finish
classification.
1.04 DELIVERY, STORAGE AND HANDLING
A Comply with all manufacturer’s written requirements for Delivery, Storage and Handling.
B Gypsum Board materials are absorbent and must be stored to prevent absorption of moisture and odors, as well as
to prevent mold growth.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Verification of Conditions: Visually inspect all areas that will receive work prior to starting. Do not start work
until all deficiencies have been corrected.
1 Verify walls are installed straight. Wood studs should be straight, #2 grade or better.
2 Verify window and door jambs are plumb, especially where window treatments are being placed over them.
3 Verify electrical outlet boxes and switch boxes are installed level.
4 Identify locations where fire rated assemblies are penetrated, and provide appropriate penetration detailing.
B Evaluation and Assessment: If required, evaluate existing substrates to receive work to assess their suitability for
proper installation/application of products. Proceeding with the work will be understood as acceptance of the
preexisting conditions.
END OF SECTION
1.01 SUMMARY
A This Section includes ceilings composed of acoustical panels and suspension systems.
1.02 SUBMITTALS
A General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification
Sections.
B Product data for each type of product specified.
C Samples for verification of each type of exposed finish required, prepared on samples of size indicated below.
Where finishes involve normal color and texture variations, include sample sets showing the full range of
variations expected.
1 6-inch- (150-mm-) square samples of each acoustical panel type, pattern, and color.
1.03 QUALITY ASSURANCE
A Single-Source Responsibility for Ceiling Units: Obtain each type of acoustical ceiling panel from a single source
with resources to provide products of consistent quality in appearance and physical properties without delaying
the Work.
B Single-Source Responsibility for Suspension System: Obtain each type of suspension system from a single source
with resources to provide products of consistent quality in appearance and physical properties without delaying
the Work.
1.04 COORDINATION
A Coordinate layout and installation of acoustical panels and suspension system components with other construction
that penetrates ceilings or is supported by them, including light fixtures, HVAC equipment, fire-suppression
system components (if any), and partition assemblies (if any).
1.05 EXTRA MATERIALS
A Furnish extra materials described below that match products installed, are pack aged with protective covering for
storage, and are identified with labels clearly describing contents.
1 Acoustical Ceiling Units: Furnish quantity of full-size units equal to 2.0 percent of amount installed.
2 Exposed Suspension System Components: Furnish quantity of each exposed component equal to 2.0 percent
of amount installed.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine substrates and structural framing to which acoustical panel ceilings attach or abut, with Installer present,
for compliance with requirements specified in this and other Sections that affect ceiling installation and
anchorage. Do not proceed with installation until unsatisfactory conditions have been corrected.
1 Verify all mechanical, electrical, fire-sprinkler line work is complete, set at the correct height and won’t
interfere with the acoustical panel ceiling system.
3.02 PREPARATION
A Coordination: Furnish layouts for cast-in-place anchors, clips, and other ceiling anchors whose installation is
specified in other Sections.
B Measure each ceiling area and establish the layout of acoustical panels to balance border widths at opposite edges
of each ceiling. Avoid using less-than-half-width panels at borders, and conform to the layout shown on reflected
ceiling plans.
3.03 INSTALLATION
Wilson Associates Architects and Planners Section 09 51 13 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
A General: Install acoustical panel ceilings to comply with publications referenced below per manufacturer’s
instructions and CISCA "Ceiling Systems Handbook."
1 Standard for Ceiling Suspension System Installations: Comply with ASTM C 636.
2 Standard for Ceiling Suspension Systems Requiring Seismic Restraint: Comply with ASTM E 580.
3 CISCA Guidelines for Systems Requiring Seismic Restraint: Comply with CISCA "Guidelines for Seismic
Restraint of Direct-Hung Suspended Ceiling Assemblies."
4 IBC Seismic requirements
B Suspend ceiling hangers from building's structural members and as follows:
1 Install hangers plumb and fire from contact with insulation or other objects within ceiling plenum that are
not part of the supporting structure or of the ceiling suspension system.
2 Splay hangers only where required to miss obstructions; offset resulting horizontal forces by bracing,
countersplaying, or other equally effective means.
3 Where width of ducts and other construction within ceiling plenum produces hanger spacings that interfere
with the location of hangers at spacings required to support standard suspension system members, install
supplemental suspension members and hangers in the form of trapezes or equivalent devices. Size
supplemental suspension members and hangers to support ceiling loads within performance limits
established by referenced standards and publications.
4 Secure wire hangers to ceiling suspension members and to supports above with a minimum of 3 tight turns.
Connect hangers either directly to structures or to inserts, eye screws, or other devices that are secure, that
are appropriate for substrate, and that will not deteriorate or otherwise fail due to age, corrosion, or elevated
temperatures.
5 Space hangers not more than 48 inches (1200 mm) o.c. along each member supported directly from hangers,
unless otherwise shown; and provide hangers not more than 8 inches (200 mm) from ends of each member.
C Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and where necessary to
conceal edges of acoustical panels.
1 Screw attach moldings to substrate at intervals not over 16 inches (400 mm) o.c. and not more than 3 inches
(75 mm) from ends, leveling with ceiling suspension system to a tolerance of 1/8 inch in 12 feet (3.1 8 mm
in 3.66 m). Miter comers accurately and connect securely.
2 DO NOT USE EXPOSED FASTENERS, INCLUDING POP RIVETS, ON MOLDINGS AND TRIM.
D Install suspension system runners so they are square and securely interlocked with one another. Remove and
replace dented, bent, or kinked members.
E Install acoustical panels with undamaged edges and fitted accurately into suspension system runners and edge
moldings. Scribe and cut panels at borders and penetrations to provide neat, precise fit.
1 Install hold-down clips in areas indicated and in areas required by governing regulations, or for fire-
resistance ratings; space as recommended by panel manufacturer, unless otherwise indicated or required.
2 Protect lighting fixtures and air ducts to comply with requirements indicated for fire-resistance-rated
assembly.
3.04 CLEANING
A Clean exposed surfaces of acoustical panel ceilings, including trim, edge moldings, and suspension system
members. Comply with manufacturer's instructions for cleaning and touchup of minor finish damage. Remove
and replace ceiling components that cannot be successfully cleaned and repaired to permanently eliminate
evidence of damage.
END OF SECTION
1.01 SUMMARY
A Section Includes: High pressure laminate flooring, underlayment and vapor barrier and all related trims and
moldings.
1.02 SUBMITTALS
A Product Data –
1 Product information sheets and detailed specification of construction.
2 Manufacturer’s installation instructions.
3 Manufacturer’s recommendations for product handling, acclimation, protection and maintenance.
B Shop Drawings: Submit installation details showing layout and location of each product type and accessory
component including design and finish textures.
C Samples: Submit selection and verification samples for design and finish texture.
1.03 CLOSEOUT SUBMITTALS
A Provide one box of plank laminate in the original packaging with the manufacturer, product number and color
clearly visible.
1.04 WARRANTY
A Manufacturer’s Warranty: Provide a 10-year commercial warranty for joint integrity, wear resistance, stain
resistance, and fade resistance.
B Installers Warranty: Provide a 1-year warranty coving repair and/or replacement for all installation defects.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Site verification of Conditions: Examine substrate conditions, application areas, and jobsite conditions are
acceptable for product installation.
B Verify concrete slab is dry according to ASTM F 1869 with maximum moisture emission of 5 lbs per 1,000 s.f.
per 24 hours.
C Verify wood floor system is structurally sound.
3.02 PREPARATION
A Surface preparation: Follow manufacturer’s recommendations for surface preparation.
B Fill all cracks and voids.
C Provide leveling compound to ensure level, in-place substrate.
D Clean substrate thoroughly. Remove all grease, paint, adhesive, dirt, dust and other contaminants that may
impact adhesion.
E Acclimation: Condition flooring materials in unopened cartons in the room where the installation is to take place
or room with exact similar conditions for at least 48 hours prior to installation.
3.03 INSTALLATION
A Install polyethylene sheet vapor barrier on concrete subfloors and wood subfloors that have open crawlspaces
underneath them.
B Install laminate flooring per manufacturer’s recommendations.
C Connect the planks via the manufacturer’s locking mechanism and stagger the plank end joints a minimum of
12”.
D Install transition pieces:
END OF SECTION
1.01 SUMMARY
A Section Includes: Sheet vinyl flooring and related adhesives and accessories.
1.02 REFERENCES
A Reference Standards – [Make sure you are familiar with the content of the standard before specifying it.]
1 American Society for Testing of Materials (ASTM)
a ASTM F710 – Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring
b ASTM F1516 – Sealing Seams of Resilient Flooring Products by the Heat Weld Method.
c ASTM F1869 – Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete
Subfloor Using Anhydrous Calcium Chloride.
d ASTM F2170 – Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs
Using in situ Probes.
e ASTM F1303 – Standard Specification for Sheet Vinyl Floor Covering with Backing.
f ASTM F141 – Standard Terminology Relating to Resilient Floor Coverings.
g ASTM F925 – Standard Test Method for Resistance to Chemicals of Resilient Flooring.
h ASTM F970 – Standard Test Method for Static Load Limit
i ASTM F1515 – Standard Test Method for Measuring Light Stability of Resilient Vinyl Flooring by
Color Change
j ASTM F1516 – Practice for Sealing Seams of Resilient Flooring Products by the Heat Weld Method
(when Recommended)
k ASTM F1914 – Standard Test Method for Short-Term Indentation and Residual Indentation of
Resilient Floor Covering.
l ASTM F386 – Standard Test Method for Thickness of Resilient Flooring Materials Having Flat
Surfaces.
m ASTM F410 – Standard Test Method for Wear Layer Thickness of Resilient Floor Coverings by
Optical Measurement.
2 National Fire Protection Association (NFPA)
a NFPA 253 – Standard Method of Test for Critical Radiant Flux for Floor Covering Systems Using a
Radiant Energy Source.
b NFPA 258 – Research Test Method for Determining Smoke Generation of Solid Materials.
3 Resilient Floor Covering Institute
a Recommended Work Practices for Removal of Resilient Floor Coverings.
1.03 SUBMITTALS
A Product Data: Submit manufacturer’s printed descriptions of materials, components and systems, performance
criteria, use limitations, recommendations, installation information, and the following
1 Typical section details indicating each specified system on proposed substrates and transitions to other
flooring systems.
2 Sections indicating flooring system abutting walls.
3 Typical plan views of various layout patterns.
B Shop Drawings: Submit keyed location plans, plans indicating resilient flooring type, layout, pattern direction,
edge transitions, columns, doorways, enclosing partitions, built-in furniture, cabinets, cutouts, expansion and
control joints, and attachment requirements.
C Samples:
1 Initial: Submit printed color charts, sample chains or Architectural binder indicating manufacturer’s
complete range to determine color, texture, shape, and/or composition for each type of material finish.
2 Final: Submit two 24-inch square samples of each different type, color and pattern selected.
1.04 CLOSEOUT SUBMITTALS
A Maintenance Contracts
B Operation and Maintenance Data
C Warranty Documentation
D Record Documentation
E Sustainable Design Documentation
F Software
1.05 WARRANTY
Wilson Associates Architects and Planners Section 09 65 16 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
A Manufacturer’s Warranty: Provide manufacturer’s warranty to be free from defects in material and workmanship,
under normal use and service, to repair or replace all defective sheet flooring for 10-years from the date of
Substantial Completion.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Verification of Conditions: Job site measurements shall be field verified.
B Substrate Testing:
1 Relative Humidity Test: 75% maximum using ASTM F2170 or as allowed by manufacturer.
2 Anhydrous Calcium Chloride Test: 5 lbs of water / 1,000 s.f. in 24-hours using ASTM F 1869
3 Alkilinity: Between 7.0 and 9.0 per ASTM F710 or as allowed by manufacturer.
4 Bond Testing: Compatibility test using ASTM F710
C Verify that substrate meets ASTM F710 requirements and is flat to within 3/16-inch in 10-feet or the equivalent
of 1/32-inch in 12-inches.
3.02 PREPARATION
A Acclimate product to installation location:
1 Deliver materials to jobsite room in which it will be installed 48-hours before installation.
2 Maintain temperature between 65-degreees F and 80-degrees F for 48-hours prior to and during installation.
3 Maintain humidity between 20— and 65- percent for 48 hours prior to and during installation.
B HVAC system shall be in full operation a minimum of 2-weeks prior to installation.
C Existing Concrete Floors: Mechanically scrape down residue to a flat bare minimum.
D Fill all cracks, voids, holes and depressions in substrates with trowlable leveling and patching compound and
remove bumps, ridges and other irregularities to produce a uniform and smooth substrate.
E Remove existing base moldings and undercut each doorjamb. Cover jambs with appropriate molding.
3.03 INSTALLATION
A Concrete Substrates:
1 Prime and cover surface cracks, grooves, depressions, control joints or other non-moving joints, and other
irregularities with a Portland-cement based underlayment patching compound with a 3,000 psi minimum
compressive strength.
B General:
1 Establish layout to use as few seams as possible.
2 Make short seams rather than long seams as appropriate.
3 Place seams in low-traffic areas when possible.
4 Avoid cross seams and utilize only length seams as they blend better with sheet and floor material.
5 Trim all factory edges at least ¼-inch to remove shipping damage or deformities.
6 Cut all seams neat. Do not leave gaps and do not cut seams tight so that material peaks.
7 Avoid trapping air or allowing wrinkles when rolling out the flooring.
8 Heat weld all seams.
Wilson Associates Architects and Planners Section 09 65 16 - 2
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
END OF SECTION
PART 2 - PRODUCTS
2.01 PRODUCTS
A General: Provide commercial grade carpeting with no padding.
B See Interior Design Drawings
2.02 ACCESSORIES:
A Tackless Carpet Stripping: Water-resistant plywood in strips, 3/8-inch or 9/32-inch thick, as required to match
cushion thickness; 2 rows or 3 rows, as indicated in Part 3 below, of angular pins protruding from top, designed to
grip and hold stretched carpet at backing.
B Carpet Edge Guard: extruded or molded heavy-duty vinyl or rubber of size and profile indicated; minimum 2-
inch-wide anchorage flange; manufacturer's standard colors.
C Seaming Cement: Hot-melt adhesive tape or similar product recommended by carpet manufacturer for taping
seams and butting cut edges at backing to form secure seams and to prevent pile loss at seams.
D Carpet Adhesive: Water resistant and nonstaining as recommended by carpet manufacturer to comply with
flammability requirements for installed carpet.
E Latex caulk.
F Patching/leveling compound. Verify required moisture level and pH requirements from the carpet manufacturer.
If allowed by the carpet manufacturer, gypsum-based patching and/or levelling compounds which contain high
Portland or high alumina cement and meet or exceed the compressive strength of 3,000 psi are acceptable.
G Transitions.
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine the subfloor to verify it is structurally sound.
B Determine floor porosity and ensure it is within the manufacturer’s recommended limitations.
3.02 PREPARATION
A General:
1 Substrate must be free of dust, dirt, oil, grease, paint, curing agents, concrete sealers, loosely bonded
toppings, loose particles and other substances or conditions that may prevent or reduce adhesion.
2 Fill depressions or cracks with cementitious patching/leveling compound. For large cracks (generally over
Wilson Associates Architects and Planners Section 09 68 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
1-inch) follow the manufacturer’s guidance on preparation.
B Use a floating compound as necessary to create a level, in-plane substrate.
3.03 GENERAL
A Comply will standard regulations for indoor air quality protection, including but not limited to:
1 Open windows and doors, if possible, for an adequate supply of fresh air. Use window fans, exhaust fans,
room air-pumps or other means for fresh-air ventilation during the installation of new flooring.
2 Continue operating ventilation equipment for 48 to 72 hours after installation.
3 Verify with the building occupants that anyone who considers themselves to be unusually sensitive is
properly notified so that they can avoid areas where installations are occurring.
4 Safely and legally dispose of excess materials as soon as the work is done. Do not leave flooring materials
lying around after installation.
B Store all flooring materials on site so that they are protected prior to installation.
C Lay out the carpeting to minimize seams and center patterns within the bounding room area.
END OF SECTION
1.01 SUMMARY
A Section Includes: Prefinished polyester glass reinforced plastic sheets and adhered to unfinished gypsum
wallboard, for use in kitchen areas.
1.02 REFERENCES
A Reference Standards :
1 American Society for Testing and Materials (ASTM)
a ASTM D 256 – Izod Impact Strengths
b ASTM D 570 – Water Absorption
c ASTM D 638 – Tensile Strengths and Tensile Modulus
d ASTM D 790 – Flexural Strengths & Flexural Modulus
e ASTM D 2583 – Barcol Hardness
f ASTM D 5319 – Standard Specification for Glass-Fiber Reinforced Polyester Wall and Ceiling Panels
g ASTM E 84 – Standard Test Method for Surface Burning Characteristics of Building Materials.
1.03 SUBMITTALS
A Product Data : Submit manufacturer’s data to indicate compliance with the following:
1 Preparation instructions and recommendations
2 Storage and handling requirements and recommendations
3 Installation Methods
B Shop Drawings: Submit elevations of each wall showing location of paneling and trim members.
C Selection Samples: Submit manufacturer’s standard color pattern selection samples representing manufacturer’s
full range of available colors and patterns.
D Samples for Verification: Submit 6-inch x 6-inch section of panel for each finish selected indicating color,
texture, and pattern required.
1 Submit complete with specified applied finish.
2 For selected patterns show complete pattern repeat.
3 Exposed molding and trim: Provide samples of each type, finish and color.
E Manufacturer’s Material Safety Data Sheets (MSDS) for adhesives and sealants prior to their delivery to the site.
1.04 QUALITY ASSURANCE
A Conform to the building code requirements for interior finish for smoke and flame spread requirements as tested
in accordance with:
1 ASTM E 84
2 Wall Required Rating – Class [A] [C]
B Sanitary Standards: System components and finishes to comply with:
1 United States Department of Agriculture (USDA) requirements for food preparation facilities, incidental
contact.
2 Food and Drug Administration (FDA) Food Code 6-101.11
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Prior to installation, the installer shall examine pertinent job-site conditions in insure proper arrangement and fit
of the work. Start of work implies acceptance of job-site conditions.
3.02 ERECTION
A Install work as indicated on drawings, as specified herein and in accordance with approved shop drawings and
manufacturer’s recommendations.
B Provide all support framing/reinforcing/support brackets required for work of this section and to ensure solid and
secure installation.
C Provide temporary supports to maintain position as units are being installed.
D FRP units shall be installed true and plumb, shimmed where necessary.
E Caulk or fill all joints as required following Manufacturing recommendations. Control joints shall be provided
where required as specified by Architect.
3.03 REPAIR/RESTORATION:
A Repair any defects found after the work of all trades has been completed, regardless of how, or by whom, the
damage was caused. Patching shall match the original work. Use Manufacturer’s recommended materials when
available.
B Patch all countersunk fasteners and damages to match unit texture, finish flush with face of unit. Use
manufacturer’s recommended materials when available.
END OF SECTION
1.01 SUMMARY
A Section Includes: All labor, materials, tools and other equipment, services and supervision required to complete
all exterior and interior painting and decorating work, including preparing the substrates, priming, pre-treatments,
painting and other related work.
B Related Sections:
1 See interior design drawings for additional information on paint colors and gloss levels.
1.02 REFERENCES
A Reference Standards :
1 Master Painters Institute (MPI)
a Architectural Painting Specification Manual
2 American Society for Testing of Materials (ASTM)
a ASTM D523-89: “Standard Test Method for Specular Gloss”
3 Environmental Protection Agency (EPA)
a Test Method for Measuring Total Volatile Organic Compound Content of Consumer Products, Method
24 (for Surface Coatings)
1.03 SUBMITTALS
A Materials List: Submit a list of the materials proposed for use. Each list to state the name of the material, the
manufacturer, and the name with stock number of each item. Include recommended tools for application of the
paint finish and any other special provisions.
B Product Data – Provide product data from the paint manufacturer, including MSDS sheets with VOC content.
C Time Schedule: Provide a time schedule showing the anticipated dates for painting work in each area. Include
each coat of paint and wait times between coats in the schedule.
D Samples – Provide 3 sets of color samples comprised of every substrate requiring painting work with all paint
products required for that material. Provide samples on a representative sample of the material substrate the paint
will be applied to. The sample shall be large enough to be easily evaluated as a representative sample of the
actual finished product.
1.04 MAINTENANCE MATERIAL SUBMITTALS [coordinate with 01 78 00 – Closeout Submittals]
A Extra Materials: Provide [1 gallon] of extra paint material to the owner.
1.05 QUALITY ASSURANCE
A Qualifications:The Contractor shall have a minimum of 5 years proven satisfactory experience and shall show
proof before commencement of work that he will maintain a qualified crew of painters throughout the duration of
the work. When requested, Contractor shall provide a list of the last three comparable projects including name
and location, specifying authority/project manager, start and completion dates and value of the painting work.
B Only qualified journeypersons shall be engaged in painting and decorating work. Apprentices may be employed
provided they work under the direct supervision of a qualified journeyperson in accordance with trade
regulations.
C All materials, preparation and workmanship shall conform to requirements of the latest edition of the
Architectural Painting Specification Manual by the Master Painters Institute (MPI).
D All paint manufacturers and products used shall be as listed under the Approved Product List of the MPI Painting
Manual.
1.06 FIELD CONDITIONS
A Perform no exterior painting work unless environmental conditions are within MPI and paint manufacturer’s
requirements or until adequate weather protection is provided. Where required, suitable weatherproof covering
and sufficient heating facilities shall be in place to maintain minimum ambient air and substrate temperatures for
24 hours before, during and after paint application.
B Perform no interior painting or decorating work unless adequate continuous ventilation and sufficient heating
facilities are in place to maintain ambient air and substrate temperatures above minimum requirements for 24
hours before, during and after paint application. Provide supplemental ventilating and heating equipment if
ventilation and heating from existing system is inadequate to meet minimum requirements.
C Perform no painting or decorating work when the maximum moisture content of the substrate exceeds:
1 12% for concrete and masonry
2 15% for wood
3 12% for plaster and gypsum board
Wilson Associates Architects and Planners Section 09 90 00 - 1
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
D Conduct all moisture tests using a properly calibrated electronic Moisture Meter, except test concrete floors for
moisture using a simple cover patch test.
E Test concrete, masonry and plaster surfaces for alkalinity as required.
1.07 WARRANTY
A Provide a 2 year warranty on products and application covering the cost of all materials and labor for a complete
repair of any defective product or installation.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Carefully examine the surfaces scheduled to receive paint for conditions which might adversely affect the
execution, performance, or quality of the finish and which cannot be made acceptable through standard
preparatory work for painting. Apply paint only to dry, clean, properly cured and adequately prepared surfaces in
areas where dust is no longer generated by construction activities such that airborne particles will not affect the
quality of finished surfaces.
B Verify that a minimum of 30 footcandles of lighting are available on surfaces to be painted.
C Pre-Application Testing – Verify moisture content of surfaces and any other testing required by the manufacturer
as part of the warranty requirements.
3.02 PREPARATION
A Prepare all surfaces in accordance with MPI requirements. Refer to the MPI Painting Manual in regard to
specific requirements.
B Mask, remove, and otherwise protect all adjacent surfaces, hardware, accessories, fixtures and similar items not
scheduled to receive paint.
Wilson Associates Architects and Planners Section 09 90 00 - 2
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
C Fill all nail-holes with putty.
D Sand, clean, dry, etch and neutralize all surfaces under adequate illumination, ventilation and temperature
requirements.
E Remove and securely store all miscellaneous hardware and surface fittings/fastening (electrical plates, louvers,
door and window hardware, etc.) Doors shall be removed before painting to paint bottom and top edges and then
re-hung.
F Preparation of new wood surfaces:
1 Clean all wood surfaces until they are free from dirt, oil and foreign matter.
2 Wood shall have a moisture content of 12% or less prior to beginning application of paint.
G Preparation of new metal surfaces
1 Galvanized steel: Use self-etching primer to touch up damage on the shop coat areas.
2 Non-galvanized steel: Remove grease, dust, scale and other foreign matter. Touch up damaged shop coat
areas with matching primer.
3.03 APPLICATION
A General:
1 Conform to the latest edition of the Industrial Health and Safety Regulations of the local jurisdiction in
regard to site safety (ladders, scaffolding, ventilation, etc.)
2 Conform to local authorities having jurisdiction in regard to the storage, mixing, application and disposal of
all paint and related waste materials.
B Spread material evenly without runs or sags.
C Cut sharp lines at terminations.
D Follow manufacturer’s recommendations for drying time between coats. Do not apply succeeding coats until the
previous coat has thoroughly dried.
E Paint visible surfaces behind grilles.
F Apply coating without reduction, except as specifically allowed by the label instructions.
G Do not adulterate the materials by substituting in part or whole the material provided by the manufacturer, unless
specifically allowed by the manufacturer.
H Paint applied to operable or moving components shall not limit the operation.
I Sand surfaces between coats to provide an anchor for the next coat and to remove defects.
3.04 COATING SYSTEMS
A Exterior Systems:
1 Lap Siding (optional):
a EXT 3.3J 2-coats Latex paint, Gloss Level G2 (Velvet) over alkali resistant water based primer
2 Aluminum (gutters, downspouts, flashing):
a EXT 5.4A 2-coats Alkyd paint, Gloss Level G4 (Satin), finish over vinyl wash primer and quick
dry primer.
3 Galvanized Metal (exterior stair, fence posts, flashing, exposed vents, bollards, bike racks):
a EXT 5.3B 2-coats alkyd enamel, Gloss Level G4 (Satin)
4 Dimension Lumber (wood posts at building):
a EXT 6.2A 2-coats latex paint, Gloss Level G2 (Velvet) over alkyd/oil primer
5 Dimension Lumber (memory care fence, garbage enclosure):
a EXT 6.2L Semi-Transparent Stain Finish
6 Brick (optional)
a EXT 4.1F Water repellent (non-paintable) finish.
B Interior Systems
1 Gypsum Board (ceilings):
a INT 9.2A 2-coats latex paint, Gloss Level G1 (Flat) over 1-coat latex sealer.
2 Gypsum Board (walls):
a INT 9.2A 2-coats latex paint, Gloss Level G4 (Satin) over 1-coat latex sealer.
3 Ferrous Metals (doors, frames, railings, etc)
a INT 5.3A 1-coat latex paint, Gloss Level G4 (Satin) over shop primed metals.
4 Dressed Lumber (Doors, window casings, molding):
a INT 6.3H Lacquer, clear, Gloss Level G3 (Eggshell).
5 Clay Masonry Units
a INT 4.1A Latex paint, Gloss Level G4 (Satin).
6 Metal (door frames, railings, panel box covers, misc exposed steel)
a INT 5.3A Latex paint, Gloss Level G5-Semi Gloss
C Mechanical/Electrical Equipment and Related Surfaces:
Wilson Associates Architects and Planners Section 09 90 00 - 3
MT HOOD SENIOR LIVING – REMODEL AND ALTERATIONS
1 Unless otherwise specified or noted, paint all unfinished conduits, piping, hangers, ductwork and other
mechanical and electrical equipment with color and texture to match adjacent surfaces in the following
areas:
a Where exposed to view
b In all interior high humidity areas
c In all boiler rooms, mechanical rooms, sprinkler riser rooms and electrical rooms
2 Paint the inside of all ductwork where visible behind louvers, grilles and diffusers for a minimum of 18-
inches or beyond the sight line, with one coat of primer and one coat of matte black paint.
3 Paint the inside of light valences gloss white.
4 Paint disconnect switches for fire alarm systems and exit light systems in red enamel.
5 Paint fire protection piping red and natural gas piping yellow, or in accordance with specific specification
section.
6 Backprime and paint face and edges of plywood service panels for telephone and electrical equipment
before installation grey, semi-gloss. Leave equipment in original finish except for touch-up as required, and
paint conduits, mounting accessories and other unfinished items.
7 Paint exterior steel electrical light standards. Do not paint outdoor transformers and substation equipment.
3.05 TOUCHUP:
A After completion of the required coats, go through the entire project to touch-up areas where paint has been
applied thinly, the color is inconsistent, there are visible splotches or the finish is otherwise visibly incomplete or
damaged.
3.06 QUALITY CONTROL
A Field Inspections: Verify installed colors match the samples. Application which does not match samples will be
considered non-conforming and required to be corrected.
3.07 CLEANING
A Paint, stain and wood preservative finishes and related materials are regarded as hazardous products and are
subject to regulation for disposal. Obtain information on these controls from applicable government departments
having jurisdiction.
B Dispose of paint in a legal fashion. Recycling of unused paint is encouraged. Place materials defined as
hazardous in containers or areas designated for the storage of hazardous waste.
C Clean materials daily. Paint spatter should be immediately cleaned t avoid staining.
D To avoid the amount of contaminants entering waterways, sanitary/storm drain systems or into the ground, the
following procedures shall be strictly enforced:
1 Retain cleaning water for water-based materials to allow sediments to be filtered out. In no case shall
equipment be cleaned using free draining water.
2 Retain cleaners, thinners, solvents and excess paint and place in designated containers and ensure proper
disposal.
3 Return solvent and oil soaked rags used during painting operations for contaminant recovery, proper
disposal, or appropriate cleaning and laundering.
4 Dispose of contaminants in an approved legal manner in accordance with hazardous waste regulations.
5 Empty paint cans are to be dry prior to disposal or recycling.
6 Close and seal tightly partly used cans of materials including sealant and adhesive containers and store
protected in well ventilated fire-safe area at moderate temperature.
3.08 CLOSEOUT ACTIVITIES
A Provide surplus and new finish materials to the Owner in the following quantities:
1 One gallon of each color used on the project. Clearly mark containers with color and locations used on the
building.
END OF SECTION
1.01 SUMMARY
A Section Includes: Identifying devices, including architectural signage, in the building interior.
1.02 REFERENCES
A Reference Standards
1 American Society for Testing and Materials (ASTM)
a B209 – Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate
b B221 – Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire,
Profiles, and Tubes
c B241/B341M – Standard Specification for Aluminum and Aluminum-Alloy Seamless Pipe and
Seamless Extruded Tube.
2 American National Standards Institute:
a A117.1 – Accessible and Usable Buildings and Facilities
1.03 SUBMITTALS
A Product Data: Submit products data, including manufacturer’s product sheets, color and style charts, materials
lists and photos of installed product if available.
B Provide a sign schedule. Schedule should be organized as follows: Room/Location/Sign Designation/Mounting
Type/Typestyle/Color/Material/Graphic/Notes
C Shop Drawings: Submit shop drawings showing quantities, layout, profiles and product components, including
anchorage, accessories, and location in the building where each product is installed. Show sign mounting types,
heights, anchorage methods and attachment devices.
D Samples: Submit selection and verification samples for finishes, colors and textures.
1.04 QUALITY ASSURANCE
A Certifications: Provide UL listings on all products that require them.
B Mock-Ups: Mock-up one door sign installation and make available for Owner and Architect to review and
approve.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Site verification of Conditions: Verify that conditions of substrates previously installed under other sections are
acceptable for product installation in accordance with manufacturer’s instructions.
1 Verify that areas are ready to receive signage.
2 Verify location of cast-in anchors installed under other sections.
3.02 PREPARATION
A Adjacent Surfaces Protection: Protect adjacent work areas and finish surfaces from damage during product
installation.
B Coordination:
1 Coordinate installation with adjacent finish materials in a manner not to destroy adjacent surfaces.
2 Coordinate with other sections for cast-in or built-in anchors and mounting hardware required in work
accomplished in other sections.
3.03 INSTALLATION
A Install signs in accordance with manufacturer’s instructions. Ensure the installation is proper so as to avoid
warps, buckles, distortions, opening up of joints, or overstressing of welds and fasteners.
B Locate and install signs in locations indicated on drawings in accordance with approved shop drawings and in
accordance with ANSI and ADAAG requirements.
C Install plumb and square.
D For direct burial installations, bore required holes to a diameter at least 4 times as large as the largest post cross-
section and to a minimum depth of at least 36-inches below grade. Cover post section that will be below-grade
with a bituminous coating to prevent oxidation. Place gravel, sand or crushed stone in the bored hole to allow for
proper drainage. Place concrete around post and ensure unit is square, level and plumb.
E For base mounted installations, set unit on prepared base and secure with anchor bolts. Secure joint between
module and base. Ensure that the unit is square, level and plumb.
END OF SECTION
1.01 SUMMARY
A Section Includes:
1 Microwave Ovens
1.02 REFERENCES
A National Fire Protection Association (NFPA)
1 70 “National Electric Code”
B US Environmental Protection Agency (EPA)/US Department of Energy Programs
1 ENERGY STAR Performance Rating System
1.03 SUBMITTALS
A Product Data: For each appliance type required, indicate compliance with requirements, include complete
operating and maintenance instructions for each appliance.
B Submit a schedule of appliances, using the same room designations on the Drawings.
1.04 QUALITY ASSURANCE
A Electrical Appliances: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency approved by
the local jurisdiction.
B UL and NEMA Compliance: Provide electrical components required as part of residential appliances that are
listed and labeled by UL and that comply with applicable NEMA standards.
1.05 WARRANTY
A Parts Warranty: 1-year entire appliance
5-year internal system
B Labor Warranty: 1-year entire appliance
5-year internal repairs
PART 2 - PRODUCTS
2.01 PRODUCTS:
A General: All appliances shall meet the following guidelines
1 Energy Star
2 ADA Compliant
B Microwave Oven:
1 Location: Countertop.
2 Color: White
3 Capacity: 1.6 or 1.8 cu. Ft
C Washer/Dryer
1 Location: 2nd Floor Laundry Room
2 Manufacturer: Samsung or approved
3 ADA Compliant controls
4 Style:
a Washing Machine: Top Load
b Dryer: Front Load
5 Capacity:
a Washer: 5.0 cu ft
b Dryer: 7.4 cu ft
6 Color: By Owner, Architect and Interior Designer
PART 3 - EXECUTION
3.01 EXAMINATION
A Examine rough-in for plumbing, mechanical, and electrical services, with installer present, to verify actual
locations of services before residential appliance installation.
B Verify existing utilities and connectors are appropriate for the installed appliances.
3.02 INSTALLATION
END OF SECTION
1.01 SUMMARY
A Section includes window treatments to be used at windows where no existing window treatments are salvaged, or
where existing window treatments are damaged and can no longer be used.
1.02 SUBMITTALS
A Product Data showing manufacturer, model, installation instructions, coordination requirements and materials
used.
B Shop Drawings showing all locations proposed for installation of window treatments.
C Samples – Provide a sample showing the proposed blind for installation. Sample should be the same material,
color and size as the proposed installation.
1.03 MAINTENANCE MATERIAL SUBMITTALS
A Spare Parts: Provide spare replacement blinds and blind accessories
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Verification of Conditions: Visually inspect all areas that will receive work prior to starting. Do not start work
until all deficiencies have been corrected.
B Evaluation and Assessment: Evaluate existing substrates to receive work to assess their suitability for proper
installation/application of products. Proceeding with the work will be understood as acceptance of the preexisting
conditions.
3.02 INSTALLATION
A Tolerances: Installation to be level, plumb and completely cover the window opening when in the closed position.
3.03 REPAIR/RESTORATION:
A Replace any slats that are damaged as part of the installation, or are damaged due to construction activity prior to
Substantial Completion
B Reinstall blinds that come loose at their attachment location, fall out of plumb or are otherwise damaged prior to
Substantial Completion.
END OF SECTION
1.01 SUMMARY
A Section Includes: Linen Chutes.
1.02 REFERENCES
A National Fire Protection Association (NFPA)
1 NFPA – Code 82 – Standard on Incinerators and Waste and Linen Handling Systems and Equipment.
1.03 SUBMITTALS
A Catalogue Cuts: Submit product catalogue cut sheets showing all details of installation and assembly. Include
door hardware and standard finish options.
B Product Data: Provide manufacturer’s product data including listed ratings and certifications.
C Shop Drawings: Provide shop drawings showing the installation proposed in the particular framing system
provided in the field. Include plans, elevations and detail drawings.
1.04 CLOSEOUT SUBMITTALS
A Operation manual.
B Warranty.
1.05 QUALITY ASSURANCE
A All primary products specified in this section shall be from a single manufacturer.
1.06 WARRANTY
A Manufacturer’s Warranty: One year from the date of Substantial Completion
PART 2 - PRODUCTS
2.01 PRODUCTS
A Chutes: 24-inch diameter chute constructed of #16 gauge aluminized steel.
B Doors:
1 Intake Doors:
a Size: 18-inch wide by 18-inch high
b Operation: Hand operated, lever style
c Self-Closing.
d Self-Latching
e Rating: 60-minutes minimum
f Finish: Brushed stainless
2 Discharge Door:
a Size: 24-inch wide by 30-inch high
b Operation: Top Hinge with UL listed hold open device, 165-degrees with fusible link.
c Rating: 60-minutes minimum
d Hopper complete with adjustable pedestal for support.
e Provide drain flange.
3 Vent: Full diameter vent of same gauge steel extending 3-feet above roof with metal safety cap, in
accordance with NFPA Code 82.
4 Floor Frames: 1-1/2-inch by 1-1/2-inch by 3/16-inch steel angles with 3/16-inch flat stock cross members
coated with anti-corrosive alkyd enamel paint.
5 Flushing Head and Sprinkler: ½-inch NPT sprinkler and ¾-inch NPT flushing head above top intake. In
addition a ½-inch sprinkler shall be installed within the chute at alternative floor levels in the building,
starting at the top level with a mandatory sprinkler located at the lowest intake level, as required by NFPA
Code 82.
2.02 ACCESSORIES
A Factory sprayed on acoustic sound dampening.
B Electric interlock: Doors are normally in the locked position. Interlock system prevents other doors from being
opened when one intake is in use.
C Floor Retaining Flanges: UL listed fire-stop for floor ceiling penetrations.
D Sanitizing Unit to clean the chute interior.
2.03 SOURCE QUALITY CONTROL
PART 3 - EXECUTION
3.01 EXAMINATION
A Verify area in which the system is to be located. Verify correct size and location, and that the area is prepared for
installation of chute and components.
3.02 PREPARATION
A Clean surfaces prior to installation.
B Prepare surfaces using methods recommended by the manufacturer for achieving the best result for the substrate
under the project conditions.
3.03 INSTALLATION
A Install in accordance with manufacturer’s instructions. Test for proper operation.
END OF SECTION
1.01 SUMMARY
A Section Includes: One piece fiberglass shower inserts for use in residential applications.
1.02 REFERENCES
A Reference Standards:
1 ANSI A117.1 – Accessible and Usable Buildings and Facilities
2 ANSI Z124.2 – American National Standard for Plastic Shower Units.
3 ASTM E 84 – Standard Test Method for Surface Burning Characteristics of Building Materials.
4 ASTM F 446 – Standard Consumer Safety Specification for Grab Bars and Accessories Installed in the
Bathing Area
1.03 SUBMITTALS
A Product Data: Manufacturer’s data sheets on each product used, including:
1 Preparation instructions and recommendations.
2 Storage and handling requirements and recommendations.
3 Installation methods
B Selection samples: For each finish product specified, two complete sets of color chips representing
manufacturer’s full range of available colors and patterns.
1.04 WARRANTY
A Manufacturer’s Warranty: 30-year warranty against manufacturing defects.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.01 EXAMINATION
A Verification of Conditions: Visually inspect all areas that will receive work prior to starting. Do not start work
until all deficiencies have been corrected.
B Verify that framing is complete and that the opening dimensions are correct.
C Verify that rough plumbing has been installed and is ready to accept shower installation.
D Verify that fire rated construction adjacent to shower installation is complete and that all inspections related to
fire rated wall assemblies have been finalized.
E Verify that the floor is level and the walls are plumb.
3.02 PREPARTION
A Install drain core through the subfloor.
3.03 INSTALLATION
A Place the fixture in the framed alcove.
B Seal the fixture around the entire base.
C Use construction adhesive per the manufacturer’s written instructions.
END OF SECTION