Infrastructure Monitoring Sheet As of March 2021

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

UPDATE ON THE INFRASTRUCTURE PROJECTS

As of March 2021

NAME OF THE DESCRIPTION UPDATE IMPLEMENTING


PROJECT AGENCY
The Subic-Clark Railway - China Harbour and BCDA/ DOTr
Project is a component of Engineering
the PNR Luzon System signed the
Development Framework contract on
providing initial freight January 16 2021
SUBIC-CLARK service between the and was awarded
RAILWAY Subic Bay Freeport Zone on January 28,
PROJECT and the Clark Freeport 2021.
and Special Economic
Zone, linking Subic Port
with Clark International
Airport and other major
economic hubs in Central
Luzon, especially New
Clark City, and forming
an integrated logistics
hub for the development
of Central Luzon as a new
growth center to
decongest Metro Manila.
This is a 30 km –four lane The 18-kilometer DPWH
Central Luzon Link expressway from Tarlac section from the
Expressway City to Cabanatuan City, connection of SCTEX
Nueva Ecija. It will and TPLEX in
reduce travel time Balingcanaway, Tarlac
between Tarlac City and City, up to Aliaga
Cabanatuan City from 70 Interchange of the
minutes to 20 minutes. Central Luzon Link
Moreover, it is expected Expressway (CLLEX)
to decongest traffic by Project Phase 1 will be
about 48% passing thru substantially
Daang Maharlika. completed on May 15,
2021.

A 38-kilometer mass Ongoing construction - DOTR


PNR North 1 transportation railway overall progress rate of
(North South that will connect Malolos, 45 percent and a
Commuter Rail) Bulacan with NCR. It will construction phase
reduce travel time rate of 11.78 percent
between these two areas as of March, 2021. 
from over one hour thirty
minutes today to thirty
five minutes once the
railway is fully
operational. The PNR
North 1 is expected to
serve over 300,000
passengers daily in its
opening year in 2021. It
will be seamlessly
integrated with PNR
North 2 and PNR South
Commuter, forming one
integrated commuter rail
system serving
commuters travelling to,
from, and within NCR,
Region III, and Region IV-
A. Using the legacy PNR
right-of-way, the project
will also restore
historical station
buildings.

PNR North 2 A 53 kilometer mass All (5) five civil works DOTr
(North South transportation railway contract packages
Commuter Rail) that will extend PNR signed and awarded.
North 1, connecting NCR
with Clark International Overall progress rate
Airport and New Clark standing at 27.79
City. The project will percent as of Jan. 31. In
enable a one-way travel this segment, there are
time of 56 minutes ongoing pre-
between Manila and construction works
Clark International and site visits. PNR
Airport (CIA), supporting Clark Phase 2 will have
the development of CIA its ground-breaking in
as a major air transport 2021.
hub. PNR North 2 will be
seamlessly integrated
with PNR North 1 and
PNR South Commuter.

5.33 kilometres long (6)


Construction of lanes with 900 meter 97% complete as of BCDA
Airport – New bridge amounting to March 2021
Clark City Access 3,696,544,342.75
Road Phase 1
8.80 kilometres long (6)
Construction of lanes with pedestrian 39% complete as of BCDA
Airport – New and bike lanes March 2021
Clark City Access amounting to
Road Phase 2 2,719,957632.55 (GAA)

5.70 kilometers long (6)


Construction of lanes with pedestrian 20% complete as of BCDA
Airport – New and bike lanes March 2021
Clark City Access amounting to
Road Phase 3 1,865,659,101.91
4.45 kilometers long (4)
Construction of lanes amounting to 95% complete as of
NCC Spur Road 610,022,649.40 March 2021
(Clark-Bamban-
Capas road)
12 Kilometers long (8)
Construction of lanes with (2) 95% complete as of BCDA
New Clark City to interchanges and toll March 2021
SCTEX Access plaza with a total budget
Road of 3,124,504,943.24
pesos
The project aims to
Clark construct a new 100% complete as of BCDA
International passenger terminal October 2020
Airport Expansion building to accommodate
Phase 1 - 8 million passengers per
Engineering, annum, as well as the
Procurement, and construction and
Construction installation of all
required associated
facilities - both landside
and airside, to support
the operations of the
Clark International
Airport.
5.81KM long (8/6) lanes
Construction of with bike and pedestrian Ongoing as of March BCDA
NCC Connecting lane amounting to 2021
Roads Package 1 965,807,314.26

7 Kilometres bike lane


Clark Freeport inside CFZ amounting to Ongoing as of March BCDA
Zone Non- 34,348,869.46 2021
motorized
Transport System Midori to Expo Filipino to
Prince Balagtas – TI –
Mabalacat Gate

4.28 Kilometres long (4-


Connector Road lane with river Ongoing as of March BCDA
from McArthur protection structure) 2021
amounting to
422,399,454.06
Rehabilitation /
CIA airfield Replacement of CIA AGLS 9% complete as of BCDA
ground lighting amounting to March 2021
system 491,888,888.77

Construction of 18-
CIA New Air Traffic Stroey Air Traffic Control Ongoing as of March BCDA
Control Tower Tower amounting to 2021
290,360,830.70
DAED of PAF Operational
DAED of PAF Facilities in a 146.88 ha. Ongoing as of March BCDA
Operational Area in Omni Aviation 2021
Facilities Complex amounting to
117,843,499.20
The New Clark City
New Clark City- National Government Completed 2020 BCDA
National Administrative Center is
Government envisioned to house
Administrative Satellite Offices of
Center various government
agencies. The future
development also
includes an Integrated
Operations Center and
Disaster Risk and
Recovery Center which
shall serve as a back-up
(redundancy) facility to
provide continuous
business and service by
the National
Government. It will also
house sports facilities
with athlete's housing
that will serve as the
national training center
for Philippine athletes.
The New Clark City Food
New Clark City- Processing Terminal and Project development BCDA
Food Processing International Food stage
Terminal and Market is envisioned to
International Food be a “stock exchange” of
Market fresh produce and
processed products. The
Project aims to attract
investors from the
private sector, local
government units and
other associations and
cooperatives to invest on
managing storage and
other infrastructures and
facilities for processing,
handling, distribution of
agricultural products
utilizing integrated
research development
and technology to be set-
up in New Clark City’s
agro-industrial zone. The
Project will consolidate
food supply chain and
post-harvest production
system (e.g., fruits,
vegetables, poultry and
livestock) for Northern
and Central Luzon, Metro
Manila and even
neighboring countries,
for niche market (organic
produce, halal-certified
goods).
A sustainable mixed-use
New Clark City - development featuring Project BCDA
Mixed Use green industries that Implementation stage
Industrial Real leverage on the local
Estate trade and Progress 17.5%
Developments environmentally-
sensitive approaches.
This is a 288–hectare
parcel of the New Clark
City that will be
developed through a
joint venture between
BCDA and Filinvest Land,
Inc.

INFRASTRUCTURE PROJECTS FOR 2021 (Status – Ongoing Procurement)

- Connecting Roads to Industrial Park


- CIA Primary and Secondary Terminal Radar
- Site Development of PAF Housing Facilities
- DAED of CIA Second Runway
- CMS of the Site Development of PAF
- Housing Facilities
- Construction of PAF Housing Facilities
- CMS of the Construction of PAF Housing Facilities

Submitted by:

JERICO D. NAMORO
Director for Infrastructure and Utilities