METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

METHOD STATEMENT FOR ……….

Originator
Company:
Contract no.:

APPROVAL STATUS
STATUS* A B C
NAME
POSITION
DATE
SIGNATURE

* Please circle the proper letter:


A: Approved B: Approved as noted C: Not approved, commented

ISSUED FOR
02
APPROVAL
ISSUED FOR
01
APPROVAL
00 ISSUED FOR REVIEW
REV
DESCRIPTION Prepared Checked Approved Date
.

Comments:

Page 1 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

SUMMARY OF DOCUMENT REVISIONS

Date Section
Rev. No. Revision Description
Revised Revised

Page 2 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

CONTENTS

1. PURPOSE................................................................................................................ 5
2. SCOPE..................................................................................................................... 5
3. RESPONSIBILITIES................................................................................................5
4. PLANNING AND PREPARATION...........................................................................5
5. METHOD OF WORK...............................................................................................5
6. HSE AND RISK ASSESMENT.................................................................................5
7. INSPECTION AND RECORDS................................................................................5
8. ATTACHMENTS......................................................................................................5

Page 3 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

1. PURPOSE
Tesisin inşa edileceği saha kotunu elde etmek için yapılan kazıdır.
2. SCOPE
Kazı projelerinde gösterilen eğimler, enkesitler ve kotlara uygun olarak yapılacaktır.
3. RESPONSIBILITIES
Contractor shall be responsible to supply all required equipment, labour and materials according
to the scope of this work, and complete the construction activities with ensuring all HSE aspects
described in this context.
4. PLANNING AND PREPARATION
Yüklenici bu işi gerçekleştirebilmesi için ihtiyaç olunan personeli ve ekipmanı sahada
hazır edilecektir.
İhtiyaç olunan personel ;
İnşaat mühendisi
Topoğraf
Kamyon Şoförü
Ekskavatör Oparatörü
Loader Oparatörü
Vasıfısz işçi
İhtiyaç olunan ekipman ;
Ekskavatör
Kamyon
Loader
Total Station

Page 4 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

5. METHOD OF WORK
Kazıya başlamadan önce topoğraf tarafından kazı yapılacak alan onaylı projesine göre
işaretlenir.Bu alan içerisinde varsa telefon,elektirik,doğalgaz,su kanalı,ağaç vb.yapılar
varsa bu yapılar kaldırılır veya deplase edilir.Daha sonra onaylı projesinden hesaplanan
enkesit ve boykesitlere göre şev kazıkları sahaya aplike edilir.

RESİM 1 – Kazı planına göre işaretleme yapılması

Page 5 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

Bu kazıklara göre ekskavatörler şev açılarını onaylı projesine göre kazarak kamyona
yüklemeye başlar.

Resim 2 – Kazı çalışması yapılması

Page 6 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

Zaman zaman topoğraf şev açılarını control ederek onaylı projesine uygun olmasını
sağlar.

Resim 3 – Şev açılarının control edilmesi

Kazılan malzeme, labaratuvar tarafından analizi yapılarak dolguya uygunluğu verilirse


dolgu amacıyla kullanılması için depo sahasında depo edilecektir.Dolguya uygun
olmadığı tespit edilirse çıkan malzeme işverenin gösterdiği atık alanına kamyonlarla
taşınıp dökülecektir.Kazı alanında onaylı projesine uygun, istenilen kotlarda düzgün bir
yüzey elde edilince kazı işi sona erecektir ve saha temel kazılarına hazır hale getirilmiş
olacaktır.

Page 7 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

Resim 4 – Temel Kazılarına Hazır Hale Getirme


6. HSE and RISK ASSESMENT
Timuçin Bey’den istenilecektir.

7. INSPECTION AND RECORDS


KALİTE KONTROL
PLANI
ANA 7.KAZI İŞLERİ
AKTİVİTE
AKTİVİTE 7.1 YA:RMA KAZIS I ARIYET OCAĞI HAZIRLANMAS I VE KONTROLÜ
Kullanılan Deney Deneyin
Alt Aktivite Uygulayıcı Deney Sıklığı Toleranslar
Ekipman Standardı yapılacağı yer
7.1.1
Şev açılarının Total Station Kalite Kontrol Şev kazısının ve Onaylı Proje ve Jeoteknik Azergold CIL
ve Kazı Ekibi Tesis kazısının Jeoteknik Report Raporda Tesis Alanı
Kotlarnın farklı Belirtilen Değer
ölçülmesi formasyonlarında

Page 8 of 9
METHOD STATEMENT FOR >>>>>

Project: Date: Rev:


MST No: Engineering, Procurement and Construction works related to the
underground (sulfide) stage of the Chovdar deposit -Document Number

8. ATTACHMENTS
Proje eklenecektir.