Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 22

Doc.

Painting No.:
KAR-TK-001

Procedure For Job No.: 001 Tank


Fire fighting
tank
Tanks Rev. 0 Date 16.Jun.2019

PAINTING PROCEDURE
FOR
FIELD ERECTED TANK

Rev Date Revision Description Prepared Checked Approved


0 16.Jun.2017 ISSUED FOR APPROVAL Parthiban

Revision
Project Number Document Number
Number
KAR-TK-P-003 0

Page 1 of 22
TABLE OF CONTENTS

1. PURPOSE.............................................................................................................................3
2. SCOPE......................................................................................................................................... 3
3. CODE AND STANDARD……………………………………………………………………………..3/4
4. ROLES AND RESPOSIBILITIES................................................................................................4
5. RESPONSIBILITIES OF SUBCONTRACTOR ............................................................... …….4/5
6. RESPONSIBILITIES OF THE APPLICATOR (SUBCONTRACTOR)................................... ...5/6
7. RESPONSIBILITIES OF PAINT MANUFACTURER.................................................................6
8. PAINT SYSTEM........................................................................................................................ 6
9. MATERIALS …………………………………………………………………………………………...6/8
10. EQUIPMENTS.......................................................................................................................8
11. AMBIENT CONDITION........................................................................................................8
12. EXECUTION PROCEDURES ................................................................................................. .8/9
13. TANK EXTERNAL BLASTING AND PAINTING PROCEDURE ..............................................9/12
14. TANK INTERNAL BLASTING AND PAINTING PROCEDURE................................... … …12/16
15. REPAIR PROCEDURE FOR EXTERNAL TANK SURFACE.....................................................16
16. REPAIR PROCEDURE FOR TANK INTERNAL LINING………………………………………..…......16/17
17. INSPECTION, TESTING AND REPORTING RECORDS………………………………............. . 17/19
18. INSPECTION TEST AND ACCEPTANCE CRITERIA FOR EXTERNAL PAINTING.................19
19. ATTACHMENT……………………………………………………………………………………. ...19/21

.
1. PURPOSE
The purpose of this method is to define the guidelines and procedures to carry out supply and
Application of painting works to protect plant equipment from corrosion and to provide an esthetically
pleasing environment for operating personnel.

2. SCOPE

This Method statement covers the painting requirements for exterior and interior surface of the
aboveground storage tanks made out of carbon steel in Khormala Plant Project.
The list of equipments in KAR Project are as below:

Size (Dia X
NO TANK NO DESCRIPTION QTY MATERIAL TYPE
Height( m)
1 Firewater tank 24.35 x Fire Water Tank 1 S355 JR DRT
11.91(without
roof)

3. CODE AND STANDARD

3.1 The society for Protective Coating(SSPC)


3.1. SSPC-PA1 Shop,Field & Maintenance painting
1
3.1. SSPC-PA2 Measurement of Dry paint Thickness with Magnetic Guages
2
3.1.3 SSPC-Vis 1 Visual Standard for Abrasive Blast Cleaned Steel
3.1.4 SSPC-SP1 Solvent Cleaning
3.1.5 SSPC-SP2 Hand Tool Cleaning
3.1.6 SSPC-SP3 Power Tool Cleaning
3.1.7 SSPC-SP5 White Blast Cleaning
3.1.8 SSPC-SP10 Near White Blast Cleaning

3.2 American Society of Testing and Materials(ASTM)


3.2.1 ASTM D4285 Standard Test Method for Indicating oil or water In Compressed Air.

3.3 ISO(International Organization for Standardization)


3.3.1 ISO 8501-1 Preparation of steel substrates before application of paints and
related products- Visual Assessment of surface cleanliness.
3.3.2 ISO 8502-2 Preparation of steel substrates before application of paints and
related products- Soluble Salt contamination method.
3.3.3 ISO 8502-3 Preparation of steel substrates before application of paints and
related products- Pressure Sensitive tape method.
3.3.4 ISO 8503-2 Preparation of steel substrates before application of paints and
related products- Surface roughness characteristics of blasted clean
substrates.
3.3.5 ISO 4624 Paints and varnishes-Pull-off test for adhesion .
3.3.6 ISO 2808 Paints and varnishes-Determination of Film Thickness.
3.3.7 ISO 29601:2011(EN) Paints and varnishes-Corrosion protection by protective
paintsystems- Assessment of porosity in a dry film.

3.4 Customer’s and Owner’s Technical Specification


3.4.1 Project Specification No:KAR1401-AMA-MA-568-ME-3901-5

3.5 Abbreviation
3.5.1 CS:Carbon Steel
3.5.2 DFT:Dry Film Thickness
3.5.3 WFT:Wet Film Thickness
3.5.4 M/S:Manufacture Standard.

4. ROLES AND RESPONSIBILITIES

COMPANY :KAR Group


CONTRACTOR :Silver Technik

5. RESPONSIBILITIES OF CONTRACTOR

The responsible for overall control of work according to this approved procedure in line
5.1 Site Manager

He will be responsible for overall control of work according to this approved method
statement in line with requirement of Health, Safety and Environment. Site manager will
coordinate with client for the scheduling and progress of work. He will assist his site
team for completing the scope as per project requirement.

5.2 QC Inspector

He will be responsible for maintaining the quality of work as per project specification.
He shall be following ITP and maintain all inspection records duly signed by all parties for
final hand over.

5.3 HSE Supervisor

He will responsible for safe implementation of this method statement for completing the
scope as per project health, safety and security & environment requirement. And he will
monitor the health and welfare of the site personnel.
5.4 Supervisor I Foreman1

He will be responsible for day to day activities as per planning and instruction of Site
Manager. Manpower and equipment planning, daily progress of work shall be his main
responsibilities and he will control painting materials and abrasives. He will control the
blast and painting team.

5.5 Crew Members

Work safely under the guidance of the supervision and in accordance with this
procedure. Set up barriers and exclusion zones around the tanks and ensure anyone
working in the area is aware of the hazards.

6.1 RESPONSIBILITIES OF THE APPLICATOR (CONTRACTOR)

The Contractor shall be responsible for:

1. Supply and application of all paint materials, labor, supervision, coating equipment, inspection
Tools and each every item of expense necessary for complete application of the paint system.

2. Cleaning and application of painting systems on welded and damaged surfaces.

3. Collection and disposal of all toxic waste materials from the work site as directed by the contractor.

4. Appropriate arrangements for technical services of the MANUFACTURER before and during
planning and application of the paint systems. A copy of purchase order for the materials showing
this provision shall be transmitted to the CONTRACTOR.

5. Preparation of appropriate work planning and taking all precautions to avoid any interfewith the
execution of work of other CONTRACTORS.

6. Obtaining the CONTRACTOR's releases that the equipment is certified safe and available and
that all appropriate tests are completed before starting any painting work.

7. The earthing of abrasive blast cleaning and painting equipment and paint containers.

8. Obtaining latest APPLICATION DATA and maintaining the same for use by all the parties.

9. Application of the paint systems to the extent stated in the procurement documents
in accordance with this specification and all other relevant documents such as site regulations,
safety rules, referenced standards and codes, etc.
10. Providing qualified painting inspectors and testing tools for carrying out specified inspection
and quality control Measures.

10. Maintenance of the paint work until completion of the contract. This shall not include the repair of
any damage caused by another contract.

7.0 RESPONSIBILITIES OF PAINT MANUFACTURER

Provide all timely technical services to ensure that the painting work is executed in
compliance with the specifications. Arranging technical representative to the work area
for random inspections and to provide all technical assistance. Submit a periodic report
to contractor confirming that painting is being carried out with their instruction and
quality of workmanship is acceptable to them. Ensure the timely delivery of all
materials for painting.

8.1 PAINT SYSTEM

8.2 All painting system shall be in accordance with Applied Painting Specification.

8.1.1 General Painting System for Tank

Application Work
Scope
Indoor/
No Equipment Material In/Outside
Outdoor
(Insulated)
No.of Paint Type DFT Total Final Color
coat DFT
(㎛)
(㎛)
High Build Epoxy
1st 80
Outside 300 RAL 9016
(Uninsulated) (Traffic White)
-.Raw water/Firefighting Tank 2nd High Build Epoxy 120
Site
1 Outdoor C.S
3rd Polyurethane 100

Outside
(Uninsulated)
- - - -
Bottom -

Inside - 300
Phenolic Epoxy 300

9.1 MATERIALS

All the material delivered at site shall be as per approved material submittal. The delivered
materials shall be checked by Inspector of s ub-contractor with its batch number manufacturing
and expiry date.Any damaged or expired material shall be quarantine from store.
9.2 Abrasive

 Surface Preparation will be carried out using the sand for blasting
Abrasive to produce the required surface profile as per paint
manufacturer recommendation.
• Under no circumstances shall be expandable grid be re-cycled.
• Grade of surface cleanliness
The surface cleanliness grades are summarized.

Grade of surface cleanliness ISO 8501-1 SSPC


White metal Sa 3 SP-5
Near-white metal Sa 2½ SP-10
Sweep blast cleaning SP-7
Solvent cleaning SP-1
Power tool cleaning St 3 SP-3
Power tool cleaning to bare metal SP-11
Water jetting (ISO 8501-4) Wa2½ SP-12
Wet abrasive blasting VIS 5

9.2. Paint Materials

» All material and related materials shall be as per Table.


» All paint containers shall be factory tinted, sealed, labelled and used on a first-in,
First out basis. Each container must have manufacturer's name, product identification,
batch - number, date of manufacture, shelf life, basic instructions and contact details for
technical services. Primer colours shall be manufacturer's standard colours and finish
colours as per Project Specification Further the intermediate coat colour shall be lighter
than finish coat. Mixing of different brands or generic types of painting materials is not
allowed.
» The paint material shall be stored in air conditioned container and as per
Manufacturer recommendation
» The VOC (Volatile Organic compound) in painting materials should be used as per Project
specification

9.2.1 Paint Material Selection


Paint Type International Paint

KANEPOX 19300
Phenolic epoxy

High Build Epoxy KANEOX 12200

Polyurethane KANPOLY 37850

10. EQUIPMENTS

Following equipment shall be used to carry out the blasting and painting works:
10.1 Air Compressor
10.2 After Cooler (Air Cooler)
10.3 Blasting Pots of 200 ltr capacity with remote control unit and minipot
10.4 Airless Pumps
10.5 Paint Mixer
10.6 Hand & Power Tools
10.7 Air receiver manifold
10.8 Inspection equipments (Shall have suitable calibration certificates)
10.9 Air Filter
10.10 Air hoods
10.11 Venturi type exhaust fans- air driven (Coppus 20 or equal)
10.12 Air quality meter- to check LEL levels of any potentially explosive mixture
10.13 Intrinsically safe lights
10.14 Low voltage tools
10.15 Lux meter
10.16 Industrial Vacuum Cleaner
10.17 Pneumatic fan.

11. AMBIENT CONDITION

The painting work shall be commenced with permissible ambient condition.


The Sub-contractor shall check daily ambient conditions during blasting, cleaning, and application
drying /curing at minimum 2 times in morning and 2 times in afternoon and
recorded in ambient report.

12. EXECUTION PROCEDURES

Blasting, Priming, Intermediate coat and final coat of tank will be done after water filling test.

General :
 Any defects found on the tanks like uncompleted weld seams, weld spatters,
edges not grinded properly etc. subcontractor will informed the contractor and the
Completion Certificate will not accept.

 All necessary precautions shall be taken to ensure the safety of personnel and
property.

 Painting yard and facilities shall be approved by Contractor and Company prior to
any painting operation.

 All Equipment welds shall not to be painted until all approved tests completed and
approved.

 All openings, including those that are flanged or threaded shall be sealed to
prevent entry of blast abrasive or paint material.

 The following items do not require any shop or field surface preparation and
coating unless otherwise specified and all surface that is not treated to be
protected by appropriate means:

13. TANK EXTERNAL BLASTING AND PAINTING PROCEDURES

A. Scaffolding for Tank External

Tank external scaffolding will be heavy duty. All required scaffolding will be erected by qualified
scaffolders in a safe manner. Each scaffolding will be certified by Scaffolding Supervisor prior to
commence activity using that scaffolding.

B. Surface Preparation of Blasting / Spot blasting on Painting Works

a. General

 The item to be blast clean and painted are tank shell, access platform, roof
top section, assemble handrails, stiffener

 Prior to start any blasting and painting works of tank handover notes must
be obtained from the contractor tank team to confirmed that there activity are
completed and the tank are ready for blasting and painting.

 Access for blasting and painting of the tank external by scaffolding or


man lift .
 All steel work shall be accessible for blasting and painting,ie staging boards
shall not prevent access for abrasive blasting,cleaning and subsequent paint
application. And all scaffolding must be certified by scaffolding inspector
before releasing and placing green tag.
 Prior to perform any blasting/painting works, the scaffolding will be covered with
green mesh. All blasting/painting equipments like - blasting pots, spray pumps
(manual attached) should be inspected & tagged by safety department prior to
start. All manholes, flange faces should be protected prior to start.

 For Blasting - blasted sand will be used for surface preparation and
after blasting all blasted sand will be collected on daily basis before
leaving the work site.

 Blasting abrasives shall be dry, clean and free from contaminants that will
be detrimental to the performance of the coating.

 Air compressor air shall be clean, dry, oil free and supplied at a
temperature of less than 65°C. Moisture and oil traps shall be used in
compressed air lines for blast cleaning, air to be check every morning
before start any blast cleaning.

 Air compressor must be checked in the morning to verify the air quality
prior to used if any oil in accordance ASTM D4285.

 Prior to blasting the surface must be high pressure washing to


remove any contamination like dust and any trace of oil, grease or
other contamination on the working surface must be removed.

 All surfaces to be treated shall be blast cleaned until degree of cleanliness


And surface profile as per approved procedure/specification.

 After completion blast the surface must be dry air blowing cleaning
Prior to inspection. Any trace of spot rusting area must be sweep
Blasting.

 The surface to be pre salt testing prior to start blasting to ensure no salt
contamination on the surface the max salt allowable must as per paint
manufacturer specification.

 The surface profile cleanliness must be as per paint manufacturer's


recommendation.

 The surface will be inspected to verify any dust contamination as per


paint manufacturer' recommendation
.
 The blast cleaned surface must be primed normally within 8 hours of
Completion of surface preparation and before occurrence of any trace
Of rust.

 Before any spray application to be done all edge, corner, weld area
must
Applied striped coated by using paint brush.
 All area or item not to be painted will be properly protection by means of
Splastic cover or making tape.

a) They shall start with tool box meetings, Superintendent foreman will discuss the days
plan which includes safety quality and routine work issues, all crew members will play an
active role by participating and developing the Safety Task Assessment meeting(STA).
b) Employees shall wear all necessary PPE (Personal Protective Equipments) as required for
the work they are doing, PPE such as coverall, safety boots, safety glasses, hand
gloves, earplugs, safety hard hats, respirators, dust mask, air hoods will always be available
at the job site.
c) Personnel working at heights above 1.8m.shall always wear full body harness and tied off
and must have the Contractor safety training in working at heights.
d) Safety body harness with 2 lanyards shall be worn by all personnel when working
from the gondolas and man lift. The body harness shall be hooked to
an independent safety line.
e) A surface profile by positector surface profile guage, Inc. may be used
f) All personnel involved or effectively by the blasting activity shall wear dust
mask provided.
g) Blasters will use air fed hoods with breathing air fed through a 38 inch hose and air-con
unit, during blasting. Compressor exit air will be circulated through an after cooler and air
filter prior to reaching the air fed hoods, trapping any oil or moisture and providing clean
odorless none contaminated breathing air.
h) Prior to start blast cleaning all bolts holes must be drilled and ground by mechanical
personnel and subcontractor will do solvent cleaning to remove any greased and oil in the
surface.
j) Contractor will informed the client if there is any sharp edges, fillets, corners, and weld
seams shall be rounded/radiuses or smoothened to a minimum of 2mm and any weld not
completely seal welded, porosity, pockets, and weld spatters, high spots to be repairs by
mechanical personnel.

C. Paint Application

a) Wet Film Thickness readings will be taken during each application to ensure the correct
film thickness is being applied and accordance with Paint manufacture
recommendation, Dry Film Thickness readings will be performed prior to application of
the proceeding coat of paint exceeding Dry Film Thickness will be performed on each
coating system accordance with SSPC PA2

Each coat of paint must be cleaned prior to applied next coat by sanding to remove any
contamination or paint defect like sagging, runs, tears, and if necessary washing to remove
dust and salt test must be checked again and offer for inspection before proceeding next
coat.
b) After completion of painting work,the finish color ,marking & Legened/Labeling shall
be as per project variation and can be visually checked with the standard of color
whether it meets the effected one

c) Color scheme of tanks shall be in accordance with project variation (Refer to below Table)
• Colors and color reference

Standard Color Code Color Name Color Chart


RAL RAL 9016 Traffic White

d) External paint work inspection will be as per the approved inspection and test plan

e) All TDS & MSDS will always be available at work site and paint storage site, and
workers will be aware of the nature and hazards posed by used of paint materials.

d) House Keeping around the work area shall be performed in daily basis, empty paint pail,
wood and paper waste materials to be disposed at the on-site designated waste disposal
facility.

D. Blasting and Painting Application Condition

All blasting and coating application shall not apply when:


 The ambient temperature is less than 10°C
 The relative humidity is more than 80%
 The surface temperature is less than 3°C above the dew point.
 The metal surface temperature is higher than 45°C or unless otherwise
acceptable to company upon recommended by the MANUFACTURER for
application.
 Surface preparation has not been completed or oil, grease, and dust are present
on the surface to be painted.
 Poor weather conditions for painting exist or are expected within two hours of
application such as blowing sand, fog, rain.
 Where there is a deposition of moisture in the form of rain, condensation, frost,etc.
on the surface.

14. TANK INTERNAL BLASTING AND PAINTING PROCEDURE

Tank internal scaffolding required will be used as per project requirement. All required
scaffolding will be erected by qualified scaffolders in a safe manner. Each scaffolding will be
certified with sticker by Scaffolding Supervisor prior to commence any activity using that
scaffolding.

14.1 Preparation for Blasting/Spot Blasting and Painting Works

a) Prior to start Internal blasting and painting works all workers involve must be prequalified
by the paint manufacturer

b) All inspection instruments must be calibrated and ready for use and reference panels must
be prepared.

c) All specified materials and equipment are available and inspected by the Contractor safety
personnel.

d) All tank tests must be completed with proper handover from the contractor tank team and
painting in charges.

e) All safety signed must be placed and all acc and emergency access must be visible.
And all the personnel must be trained in confined space by DHIC safety department.

f) Lighting must be placed and properly inspected by safety if ready to use. lighting for
Blasting will be u s e 220 volts, all wire will be placed in flexible PVC pipe to protect the
wire from damages.

g) Ventilation by means of using pneumatic fans, depending in tank manhole configuration.

h) Each Blast nozzle will be attached with independent halogen bulb lighting 12volts I
20watt.

i) All workers involve in internal working at heights must wear full safety hardness

j) Method of access inside the tank shall be through the shell manhole.

k) Manhole watch men must be in the work place in all times and. Watchman must understand
English language; how to speak, read and write and trained as manhole watchman in DHIC
safety department.
I) A hole watchman will be used and this hole watchman will have a phone and log in I
Log out book

j) Dust level must be 2 or better in accordance with ISO 8502-3. If the dust level is not accepted
then the surface must be re-cleaning by bristle brushing and same time air blowing and
reinspected.

14.2 Surface Preparation of Tank Bottom, Shell, Roof Bottom Plates and fixed roof

14.2.1 All activity must have approved work permits prior to start.
14.2.2 Air compressor must be checked in the morning to verify the air quality prior
to use if any oil or water content in accordance with ASTM D4285.

14.2.3 If the humidity inside the tank is more than 80%, dehumidification must be
used to maintain the tank internal temperature. Surface temperature must be
Maintained at least 3℃ above the dew point, dehumidifying equipment shall
be capable of achieving relative humidity levels below 60%.
14.2.4 Abrasive shall be composed of clean, hard particles free from foreign
substances such as dirt, oil, grease, toxic substances, organic matter,
mill scale, soil and water soluble salts

14.2.5 The conductivity of deionized water extract on abrasive materials shall be as


per Paint Manufacture recommendation

14.2.6 The abrasive must be capable of producing the degree of cleanliness


Surface Profile specified. The particle size of the abrasive shall be as per
Paint Manufacture Specification.

14.2.7 The Abrasive materials to be used are 30/60 mesh for upto 500 ㎛ (DFT)
cleanliness must be Sa 21/2 as per Internal lining specification.

14.2.8 After completion of blast cleaning, the surface must be clean by means of
brushing and vacuum (Heavy duty) to remove all sand and dust. All
personnel who will do the cleaning process must have clean coverall and
shoe cover to avoid any contamination into the blasted surface. Also to
reduce dust inside the tanks, pneumatic exhaust fan will fit to manhole
wherever the blasting is going on.

14.3 Paint Application of Tank Internal Lining

a) The paint material will be store in paint storage shop, Only the required paint are to be
shifted in the tank area and place in a appropriate paint stock shelter.
b) After completion of blasting, within 4 hours must be painted to avoid any rust spot in to the
blast clean surface.

c) Prior to spray paint, all weld joint and corners must be stripe coated to have adequate
protection.

d) The paint is to be mix by means of electric or air mixer.

e) Readings will be taken during each application the correct film thickness being applied and
accordance with Paint Manufacture Specification.DFT readings will be performed prior to
application of the proceeding coat of paint. Intermediate coat, sanding will be performed on
each coating system accordance with SSPC PA2.

f) WFT is required, and will be given in paint manufacturer's table.

g) Mixing of thinner as per manufacturer' paint data sheet to be followed.

h) Spray application must be 25 to 50% overlapping to give uniform thickness and without
runs, sags and dry spray.

i) The re-coating interval must be as per paint manufacturer' data sheet to be followed.

j) All area to be painted must be clean and dry without any oil or grease even dust
particles in the surface.

k) All workers involve in internal lining must use clear safety glass or goggles. And with
correct PPE's for confined space like respirator musk 3M half face piece respirator
6200(07025)

I) Ventilation must be maintained during the entire lining application and continue while the
solvent is released. The lighting to be used during paint application will be 24volts or below
explosion proof lamps.

m) When completed painting proper signed must be place in all manhole area (DO NOT
ENTER WET PAINT) and manhole to be placed barricading.

n) After completion of painting works Holiday test or pinhole test must be carried out to ensure
the there is no pinhole in the paint surface,

o) The selection of voltages to be used as per paint manufacturer' recommendation and as per
NACE RP0188 100% with zero defect, any defect found or holiday will be repaired as per
approve paint manufacturer' recommendation and re-tested those area.

15. REPAIR PROCEDURE FOR EXTERNAL TANK SURFACE

A. The coating surface not exposed the substrate to be over coated which become
contaminated or paint damaged shall be cleaned by solvent cleaning and or lightly brush,
sanding and after wipe out with clean rags to ensure that the surface is free of all contaminations
prior to applying the following coats. The coating around the damage area shall be chamfered
or feathering using sandpapers and applied paint with full system the overlapping must be
5O mm all side.

B. The surface coating damage are exposing the substrate surface shall be re-cleaned as
originally specified for that item and the full coating system reapplied in accordance with the
paint manufacturer' recommendation the re-cleaning shall be carry over onto tightly
Adhering surrounding coating for not less than 50mm all around and the edges shall be
chamfered or feathering by sandpaper. The remainder of existing coated surface shall properly
protected with shields to prevent any possible damages to the coating.

C. Repairing of High built epoxy primer damaged area surface shall be cleaned to remove all
loose materials and blast cleaned with a portable vacuum blast cleaning machine. Where
the maximum operating temp is below 120° ( the surface shall be coated with one coat of the
zinc rich.

D. Repairing of fully cured epoxy coating or full cured painting the coated has been suitably
abraded to provide an adequate tooth for the painting to be applied.

16. REPAIR PROCEDURE FOR INTERNAL TANK LINING

A. Surfaces adjacent to repair area shall be protected from damages. Suitable protective cover
shall be cardboard or similar materials. Areas required spot blasting required vacuum blasting
to avoid spillages of garnet in the area and dust.

B. Damaged surface lining shall be removed unless it is tightly bonded to the substrate metal.
the surface shall be wiped with clean rag to remove all dust and loose materials. If there is
any oil, grease or other foreign matter are present, it shall be washed with a water based
biodegradable cleaner followed by further rinsing with portable water to remove all traces
of cleaner. The surfaces must be dried.

C. Any painted surfaces with pinholes may be cleaned using pencil-head type grinding wheel.
pinholes shall be repaired as follows:

i. Grind back to the steel substrate at the pinholes and feather the edges of the existing
Lining with clean sandpaper back for radius of 3 to 5 cm, ensuring that the steel substrate
does not become polished.

ii. All dust shall be removed with industrial vacuum cleaner equipped with a brush.

iii. Brush full system (except primer) on to the prepared surface.

iv. Allow the material to cure to a tack-free state and recoated as necessary to bring
thickness to that specified in paint system table for internal lining.

V. Areas which is under thickness (Spot work)

1. Uniformly abrade all surfaces so at least 75% of the surface area is randomly
roughened and wipe with acetone to remove dust and contamination.
2. Apply one coat of topcoat, checking wet film thickness during application to achieve
necessary thickness. After cure, recheck dry film thickness of the repaired areas.

Over Thickness (Spot Work)

1. Abrade the area to an acceptable thickness using suitable equipment.


2. All other repair requirement be in accordance with Paint Manufacture
Recommendation.

17. INSPECTION, TESTING AND REPORTING RECORDS

A. The applied lining shall be free of runs, sags, voids, drips, overspray, pinholes, loss adhesion,
blistering, peeling, inadequate cure, spot rust, localized rusting and any other defects.

All defects on the paint surface shall be repaired and re-inspected. RFI will be raised as followed.
• Surface preparation prior to apply primer coat
• Primer inspection prior to next coating
• Mid coat inspection prior to apply final coat
• Final coat inspection
• Holiday test or Pinhole test
• Material Receiving inspection

* Notes: During inspection the attached IR (Inspection Report) in the RFI (Request for Inspection) will be
sign by Contractor Painting Inspector and Company Painting Inspector.

B. Inspection Surface preparation shall be in accordance with project specifications for painting.
Ambient temperature and relative humidity shall be checked and recorded before proceeding
to surface preparation and coating.

Measuring Thickness of Paint

1. Dry film thickness (DFT) of each coating shall be checked by an Positector dry film thickness
gage. Measurements of the D FT shall be taken in accordance with SSPC- PA2. Minimum Dry
film Thickness: Each spot’s average dry film thickness shall be equal to or more than 80 % of
specified dry film thickness. All spots’ average dry film thickness shall be more than specified
dry film thickness.

2. Max dry film thickness: Max dry film thickness shall be in compliance with paint
manufacturer’s instruction.

3. Coating Supervisor shall keep an accurate record of air temperature and humidity
condition at the time of commencement and cessation for all the phases during cleaning,
surface preparation and paint application.

Holiday Detection (ISO 29601:2011(EN))

When protective coatings are applied there is a possibility that flaws have occurred due to the
presence of trap air, or voids and pinholes and these defects only largest can be detected visually.
Holiday Detections inspection shall be conducted using either of this two instruments considering on
the paint film thickness.

a) Low Voltage Detector


The wet sponge method is most commonly used. This is suitable for coatings up to
approximately 300 micron. The method of operation is to draw the moistened sponge
over the surface. Where the defect has occurred a small current will flow and activate
and audible alarm. Excessive wetting of the sponge should be avoided.
For thicker film a higher voltage is required for flaw detection. Two types are used, either
with AC or DC voltages. The AC type is not totally satisfactory, as the coating is subject to
cyclic stresses which can cause fatigue and subsequent breakdown of some coatings.

The DC type produces a continuous current. Care must be taken with high voltage (spark) detectors to
ensure that the test voltage selected is not excessive for the coating thickness.
Voltage for Test
Voltage (V) Coating Thickness (microns)

9 Up to 300

90 Up to 500

* Note : When coating thickness exceeds 500 micron, high voltage holiday detectors are
recommended and nominally set SV/11m based on DFT or as agreed with paint
manufacturer,but not exceeding 25KV in total.

18. INSPECTION /TEST AND ACCEPTANCE CRITERIA FOR EXTERNAL PAINTING

Test Standard Frequency Acceptance Criteria

One per hundred(100) As per Paint manufacture


Surface cleanliness ISO 8501-1 data sheet (PMDS)
square metres

One per hundred(100) As per Paint manufacture


Surface profile ISO 8503-2
square metres data sheet (PMDS)

One per hundred(100) As per Paint manufacture


Dry Film Thickness ISO 2808 square metres data sheet (PMDS)

ISO 2808 As per Paint manufacture


Wet Film Thickness Spot Check
method-1A data sheet (PMDS)

All inspection and acceptance criteria will be based on Paint Manufacture Data Sheet.

18.1 Reporting and Recording


All painting activity will be recorded in the painting report form

19. ATTACHMENT

Attachment 1: Surface preparation/priming inspection Report


ID : TQ-TK-0023
Khormala power plant-Raw water / FIFI
storage tank (5000m3)Project
SURFACE PREPARATION /PRIMING
KAR INSPECTION REPORT
Tag Description: Tag No.:
System No.:
Subcontractor: Sub-System No.:
Work Package: P.O No.: Unit / Train:
Drawing Ref.: Report No.:
ITP Ref No / Rev. No RFI No.:
Surface
Ambient Condition during application preparation details
Date Specified Visual std.:
Time Abrasive / Power tool:
Attach Press 'O' Film
Dry Bulb ºc:
Wet Bulb ºc
Dew Point ºc
R.Humidity %
Ave. Max.
Mil/µ Mil/µ Min. Mil/µm
Substrate Temp. ºc Measurement m m

Specified Painting System: Inspection Result:


Applied primer Type:
Paint Manufacturer Name & Product Code:
Base & Curing Agent Batch nos.
Application Method:
Signature & Date:

Primer
Inspection
Substrate Details Date:
DFT
Heat
Min
S.No. Identification No. Size no./Spoo Quantity Max Avg.( Remarks
(µm)
l no. (µm) µm)

Description Subcontractor Contractor Company


Name
Signature
Date
Attachment 2: Intermediate / Top coat inspection report

ID: TQ-TK-0024
Khormala power plant- Raw water / FIFI storage
tank (5000m3)Project
INTERMEDIATE /TOP COAT PAINTING
KAR INSPECTION REPORT
Tag Description: Tag No.:
System No.:
Subcontractor: Sub-System No.:
Work Package: P.O No.: Unit / Train:
Drawing Ref.: Report No.:
ITP Ref No / Rev. No RFI No.:

Intermediate paint type: Final paint type: Specified System:

Ambient Condition during application


Date Paint Manufacturer's name:
Time Application Method:
Dry Bulb ºc: Final coat Color:
Wet Bulb ºc:
Dew Point ºc Base :
R.Humidity % C.A :
Substrate
Temp. ºc Thinner:
Intermediate Coat Insp.
Substrate Details Date: Top coat inspection Date:
Primer DFT DFT
Insp.
report Min Max Max
S.No. Identification No. Size no. (µm) (µm) Avg.(µm) Min(µm) (µm) Avg.(µm)

Adhesion
REMARKS Test:
Holiday Test:

Special tests recommended:

Description Subcontractor Contractor Company


Name
Signature
Date
Doc.
Painting No.:
KAR-TK-001

Procedure Job No.: 001 Tank


Fire fighting
tank
For Piles Rev. 0 Date 16.Jun.2019

Page 22 of 22

You might also like