Professional Documents
Culture Documents
Suggested Analytic Approach To Transmission Reliability Margin
Suggested Analytic Approach To Transmission Reliability Margin
Suggested Analytic Approach To Transmission Reliability Margin
Abstract if “all facility loadings are within normal ratings and all
voltages are within normal limits”, the system “remains
Transmission Reliability Margin (TRM) is the com-
stable following a disturbance that results in the loss
ponent of available transfer capability that accounts for
of any single element”, the post-contingency system ...
uncertainties and safety margins. We suggest an an-
has all facility loadings within emergency ratings and all
alytic framework for TRM calculation using transfer
voltages within emergency limits” [10]. In this report
capability sensitivity formulas and a probabilistic char-
we do not address some of the finer points of the transfer
acterization of the various uncertainties. Preliminary
capability definition.
results on a simple example show how we plan to test
the TRM calculation and validate it with a Monte Carlo The power system is partitioned into areas, each of
method. This draft report is produced in order to seek which is defined by a set of buses. The transfer between
comment from PSerc members on the practicality and two areas is the sum of the real powers flowing on all the
usefulness of this approach to TRM. lines which directly connect one area to the other area.
A list of contingencies is chosen and a nominal transfer
schedule is chosen. A secure base case is chosen. A
1 Introduction
base case transfer including existing transmission com-
Successful implementation of electric power deregu- mitments is determined. The transfer is then gradually
lation requires the determination of the available trans- increased starting at the base case transfer until the
fer capability of a power system. The available trans- first security violation is encountered. The real power
fer capability indicates the amount by which interarea transfer at the first security violation is the total trans-
power transfers can be increased without compromis- fer capability.
ing system security. The available transfer capability is The available transfer capability is then defined as
the total transfer capability minus the base case trans-
fer together with adjustments such as the Transmis- Available Transfer Capability (ATC) =
sion Reliability Margin (TRM) to allow some margin Total Transfer Capability (TTC)
of safety. The transmission reliability margin takes ac-
−Existing Transmission Commitments (ETC)
count uncertainties and provides safety margins. This
report suggests an analytic framework for computing −Transmission Reliability Margin (TRM)
the transmission reliability margin. −Capacity Benefit Margin (CBM)
The approach exploits formulas for the first order
sensitivity of transfer capability which have been devel- The following limits are accounted for in the transfer
oped by PSerc [7, 4]. These formulas can be quickly capability computation:
and easily computed when the transfer capability is
determined. The formulas essentially determine a lin- • power flow or current limits (normal and emer-
ear model for changes in transfer capability in terms of gency)
changes in any of the power system parameters. This
report assumes that the uncertainty of the parameters • voltage magnitude upper and lower limits (normal
can be estimated or measured. Using this information, and emergency)
the report shows how to estimate the corresponding un-
certainty in the transfer capability. A formula for TRM • voltage collapse limit
is then developed based on the uncertainty in the trans-
fer capability and the degree of safety required. Our framework accounts directly only for limits
which can be deduced from static model equations. Os-
cillation and transient stability limits are assumed to be
2 Summary of available transfer capability
studied offline and converted to surrogate power flow
For this report we use the main features of the NERC limits. However, treating dynamic limits with power
1995 and 1996 definitions [8, 9]: The power system is flow limit surrogates will not produce correct sensitiv-
judged to be secure for the purpose of interarea transfer ity information.
∂A
3 Purpose and definition of TRM ∂pi is the sensitivity of the transfer capability to the
According to NERC [9], “The determination of ATC parameter pi evaluated at the nominal transfer capabil-
must accommodate reasonable uncertainties in system ity.
conditions and provide operating flexibility to ensure When the available transfer capability is limited by
∂A
the secure operation of the interconnected network”. voltage collapse, ∂p i
can be computed using the for-
There are two margins defined to allow for this uncer- mulas of [5]. (Topology changes can also be accomo-
tainty: The transmission reliability margin is defined in dated with limited accuracy using the fast contingency
[9] as “that amount of transmission capability necessary ranking techniques in [6].) When the available transfer
to ensure that the interconnected transmission network capability is limited by voltage magnitude or thermal
∂A
is secure under a reasonable range of uncertainties in limits, ∂p i
can be computed using the formulas of [7, 4].
system conditions”. The capacity benefit margin en- In each case a static, nonlinear power system model is
sures access to generation from interconnected systems used to evaluate the sensitivities. The computation of
∂A
to meet generation requirements. The capacity benefit ∂pi is very fast and the additional computational effort
∂A
margin is calculated separately from the transmission to compute ∂p i
for many parameters pi is very small
reliability margin. [5, 7, 4].
Since the uncertainty increases as conditions are pre-
dicted further into the future, the transmission relia- 4.3 Formula for TRM
bility margin will generally increase when it applies to Since the parameters are assumed to be independent,
times further into the future. µ ¶
X m
∂A
2
σ (U ) = σ 2
(pi − µ(pi )) (5)
4 Quantifying TRM i=1
∂pi
4.1 Parameters and their uncertainty X m µ ¶2
∂A
= σ 2 (pi ) (6)
The transfer capability is a function A of many pa- i=1
∂pi
rameters p1 , p2 , ..., pm :
and the standard deviation of U is
transfer capability = A(p1 , p2 , ..., pm ) (1) v
um µ ¶
uX ∂A 2
The parameters pi are chosen to satisfy the following σ(U ) = t σ 2 (pi ) (7)
i=1
∂pi
conditions:
Under suitable conditions which are discussed in the
1. The uncertainty in the parameters pi causes the
appendix, the uncertainty U is approximately a normal
uncertainty in available transfer capability that is
random variable with mean zero and standard deviation
accounted for by the transmission reliability mar-
given by (7). This approximation gives a basis on which
gin.
to define the transmission reliability margin. The con-
2. The uncertainty in the parameters is accounted for ditions described in the appendix are mild and require
by regarding each parameter pi as a random vari- little knowledge of the distribution of the parameters.
able with known mean µ(pi ) and known standard We want to define the transmission reliability margin
deviation σ(pi ). large enough so that it accounts for the uncertainty in
U with rare exceptions. More precisely, we want
3. The parameters are statistically independent.
probability{−U ≤ TRM} = P (8)
4.2 Transfer capability sensitivity
where P is a given high probability. This can be
The uncertainty U in the available transfer capability achieved by choosing the transmission reliability mar-
due to the uncertainty in all the parameters is: gin to be a certain number K of standard deviations of
U:
U = A(p1 , p2 , ..., pm ) − A(µ(p1 ), µ(p2 ), ..., µ(pm )) (2) TRM = Kσ(U ) (9)
The mean value of the uncertainty is zero: K is chosen so that the probability that the normal
random variable of mean zero and standard
RK deviation 1
is less than K is P . (That is, √12π −∞ e−t /2 dt = P .)
2
µ(U ) = 0 (3)
It is straightforward to calculate K from P by consult-
Approximating the changes in available transfer capa- ing tables of the cumulative distribution function of a
bility linearly in (2) gives normal random variable [2]. For example, if it is de-
cided that the transmission reliability margin should
Xm
∂A
U= (pi − µ(pi )) (4) exceed the uncertainty −U with probability P =95%,
i=1
∂pi then K = 1.65. (Another way to state this result is that
a normal random variable is less than 1.65 standard de- parameter distribution
viations greater than the mean 95% of the time.) If it is line susceptance B25 binary, Prob{B25=5.0}=0.95,
decided that the transmission reliability margin should Prob{B25=0}=0.05
exceed the uncertainty −U with probability P =99%, line impedance X38 normal, mean=0.4, σ=0.02
then K = 2.33. line impedance X67 normal, mean=0.2, σ=0.01
Combining (7) and (9) yields a formula for transmis- system loading p4 normal, mean=0.0, σ=0.1
sion reliability margin: bus 5 generation p5 normal, mean=0.0, σ=0.01
v flow limit normal, mean=1.5, σ=0.0748
um µ ¶
uX ∂A 2
TRM = K t σ 2 (pi ) (10)
i=1
∂p i Table 1: Parameter distributions
In order to use formula (10) we need: While some of these uncertainties may be quite hard
to characterize a priori, it is important to note that
• A choice of uncertainty parameters p1 , p2 , ..., pm
it would be practical to collect empirical data on the
satisfying the three conditions above.
changes in base cases as time progresses. Then standard
• The standard deviation σ(pi ) of each parameter. deviations and means of the uncertain parameters cor-
responding to various time frames could be estimated.
• Calculation of the sensitivity of the transfer capa- It is also important to satisfy the statistical indepe-
∂A dence assumption when modeling the parameter uncer-
bility to each parameter ∂p i
.
tainty. For example, if the uncertainty of different loads
5 Uncertainty parameters has a common temperature component, then this tem-
perature component should be a single parameter and
The available transfer capability is computed from the load variations should be modeled as a function of
a base case constructed from system information avail- temperature.
able at a given time. There is some uncertainty or inac-
curacy in this computation. There is additional uncer-
6 Simulation test results
tainty for future available transfer capabilities because
the available transfer capability computed at the base
case does not reflect evolving system conditions or op-
erating actions. These two classes of uncertainty are
examined in the following two subsections.
X
m Z
1
lim X 2 dF = 0 (11)
m→∞ s2m |Xk |>²sm k
k=1
Pm
holds for all positive ² then s1m k=1 Xk converges in
distribution to a normal random variable of mean zero
and variance unity.
One useful class of random variables satisfying the
Lindeberg condition (11) is random variables which are
both uniformly bounded and whose variance uniformly
exceeds some positive constant. It is also straightfor-
ward to augment the random variables satisfying (11)
with some normal random variables.
REFERENCES
[1] P. Billingsley, Probability and measure, second edition,
Wiley 1986, theorem 27.2, page 369.