Pre-Commissioning Test Report

Client AVAADA GREEN H.N PROJECT PVT.LTD 


Project 50 MW MITHI SURERA(SIRSA) SOLAR POWER PROJECT AT HARYANA 
Contractor TECHNO 
Testing
Team  EUREKA ENTERPRISES

Date: 01-10-2021

TEST REPORT FOR FEEDER PROTECTION RELAY


Location : 50MW AVAADA SIRSA
Switchgear Name : 33 KV SS
Feeder Name : INCOMER- 02
Designation : Feeder Protection Relay

1.Relay Details:
Make ABB Type REF615
Model HBFFAEAGNBA1BNA11 Sr 1VYV91362897
G
CTR 300/1 A PTR 33000/110 V

2. GENERAL INSPECTION & TESTING:-


SL.NO General Inspection & Testing REMARKS
1 Installation & Wiring Correct To Relevant Drawings OK
2 Relay Case Connected To Local Earth Bar OK
3 Relay Output Checked OK
4 Visual Inspection Of Unit OK

3. Measured Value Test:-


Inject current in the relay as per the table below. Observe the reading on the relay display,
in primary values.

Ct ratio – 300/1 A, Pt ratio – 33000/110 V


Primary Current Displayed on Relay (A)
Phase Current Injected (A)
IL1 IL2 IL3 IN
R-N 1 300 0A 0A 300
Y-N 1 0A 300 0A 300
B-N 1 0A 0A 300 300
RYB 1 300 300 300 0A

Primary Voltage Displayed on Relay (kV)


Phase Voltage Injected (V)
L1-L2 L2-L3 L3-L1
R-Y 110 32.99 0 0
Y-B 110 0 32.99 0
B-R 110 0 0 32.99

Details Tested By: Witnessed By: Witnessed By:


NAME Hariharan J M.Manik  Pankaj Mandal 
SIGNATURE      
DATE 01-10-2021    
(Testing) AVAADA (Testing) AVAADA (Quality)
Pre-Commissioning Test Report
Client AVAADA GREEN H.N PROJECT PVT.LTD 
Project 50 MW MITHI SURERA(SIRSA) SOLAR POWER PROJECT AT HARYANA 
Contractor TECHNO 
Testing
Team  EUREKA ENTERPRISES

Date: 01-10-2021

4. Overcurrent Protection 51/50 :-

DPHLPDOC1:1
Ip> 0.78 A, IEC Normal Inverse, TMS – 0.07

Operating Time in (sec)


Pick up in (Amps)
2 times 5 times 10 times
Phase
Expected Actual Expected Actual Expected Actual Expected Actual
(A) (A) (sec) (sec) (sec) (sec) (sec) (sec)

R 0.78 0.79 0.712 0.303 0.220


Y 0.78 0.79 0.715 0.304 0.223
0.702 0.300 0.208
B 0.78 0.79 0.716 0.306 0.224
RYB 0.78 0.79 0.712 0.302 0.224

PHIPTOC1:1
I> 2.5 A, Time Delay – 0.150 Sec.
Phase I Pickup (A) Expected Trip Time (sec) Actual Trip Time (sec)
R 2.51 0.150 0.158
Y 2.51 0.150 0.153
B 2.51 0.150 0.163
RYB 2.51 0.150 0.154

5. Earthfault Protection 51N/50N :-

DEFLPDEF1:1
Ie>- 0.2 In, IEC Normal Inverse, TMS – 0.10
Operating Time in (sec)
Pick up in (Amps)
2 times 5 times 10 times
Reference
Expected Actual Expected Actual Expected Actual Expected Actual
(A) (A) (sec) (sec) (sec) (sec) (sec) (sec)

N 0.2 0.22 1.003 1.015 0.428 0.438 0.297 0.312

EFHPTOC1:1
Details Tested By: Witnessed By: Witnessed By:
NAME Hariharan J M.Manik  Pankaj Mandal 
SIGNATURE      
DATE 01-10-2021    
(Testing) AVAADA (Testing) AVAADA (Quality)
Pre-Commissioning Test Report
Client AVAADA GREEN H.N PROJECT PVT.LTD 
Project 50 MW MITHI SURERA(SIRSA) SOLAR POWER PROJECT AT HARYANA 
Contractor TECHNO 
Testing
Team  EUREKA ENTERPRISES

Date: 01-10-2021

Ie>> 0.4 A, Time Delay – 0.160 Sec.


Reference I Pickup (A) Expected Trip Time (sec) Actual Trip Time (sec)
Neutral 0.41 0.160 0.183

6. Undervoltage Protection (27) :-

U<27.5 V, Time Delay – 4.00 Sec.


Phase U Pickup (V) Expected Trip Time (sec) Actual Trip Time (sec)
RY 27.4 4.000 4.022
YB 27.4 4.000 4.024
BR 27.4 4.000 4.021
RYB 27.4 4.000 4.023

7. Remarks : Above test results were found normal.

Note: Reference standard for field testing of Electrical Relays & Current transformer : IS9124 -1979.

Details Tested By: Witnessed By: Witnessed By:


NAME Hariharan J M.Manik  Pankaj Mandal 
SIGNATURE      
DATE 01-10-2021    
(Testing) AVAADA (Testing) AVAADA (Quality)