Professional Documents
Culture Documents
Feasibility Study+Preliminary Design Peshwar Torkham
Feasibility Study+Preliminary Design Peshwar Torkham
for
Peshawar Torkham Motorway
CONSULTANCY SERVICES
PERTAINING TO FEASIBILITY STUDY
AND PRELIMINARY DESIGN OF
PESHAWAR - KABUL MOTORWAY
Submitted to:
National Highway Authority
July2017
Submitted by:
Associated Consultancy Centre (Pvt.) Ltd. (ACC) in association
with
SAMBO Engineering Co. Ltd. (South Korea),
ACE-TES Lahore & Assign International
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
TABLE OF CONTENTS
Summary................................................................................................................... v
CHAPTER-1 ................................................................................................................ 1
BACKGROUND .......................................................................................................... 1
1.1 Peshawer Tortham- Section I ...........................................................................2
CHAPTER-2 ............................................................................................................... 3
OBJECTIVE AND SCOPE OF STUDY ............................................................................ 3
CHAPTER-3............................................................................................................... 4
DESCRIPTION OF STUDY AREA ................................................................................ 4
CHAPTER-4 ............................................................................................................... 7
HYDROLOGICAL INVESTIGATION ............................................................................. 7
4.1 General ........................................................................................................... 7
4.2 Climatic Characteristic Analysis ...................................................................... 7
4.3 Rainfall Frequency Analysis .......................................................................... 10
4.4 Rainfall-Runoff Method ................................................................................ 14
CHAPTER-5.............................................................................................................. 15
HYDRAULIC INVESTIGATION .................................................................................. 15
5.1 Hydraulic Analysis for Major Streams and Nullahs ....................................... 15
5.2 Hydraulic Analysis for Cross-Drainage Structures/ Culverts ......................... 20
5.3 Hydraulic Design Analysis for Side Channels .................................................29
CHAPTER-6 ............................................................................................................. 32
FINDINGS & RECOMMENDATIONS .......................................................................... 32
References ................................................................................................................ 33
ANNEXURES............................................................................................................. 34
Annexure A: Historical Climatic Data for Peshawar ................................................ 35
Annexure-B: Catchments Delineation of Major Streams/ Nullahs ............................ 39
Annexure-C: Hydrologic and Hydraulic Parameters relating Bridges over Major
Streams/ Nullahs ..................................................................................................... 50
Annexure-D: Hydraulic Outputs of Major Streams/ Nullahs .................................... 53
Annexure-E: Scour Depth Estimation by Lacey Regime Theory .............................. 64
ii
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
LIST OF FIGURES
iii
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
LIST OF TABLES
iv
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Summary
The trade via Afghanistan towards Central Asian countries and from Arabian sea
has been centuries old activity through road connectivity. With the passage of time,
the traffic has increased tremendously, exerting pressure on existing road
infrastructure, arising need for an improved road infrastructure from Peshwar to
Torkham to meet the expanding communication needs, especially after CPEC
(China-Pakistan Economic Corridor) initiative. The current hydrological investigation
is carried out to study the hydrological regime and allied impacts for safe
development and operation of Peshawar-Torkham Expressway (approx 47 km) in
the northern part of the Khyber Pakhtunkhwa province of Pakistan.
The Peshawar-Torkham proposed alignment falls in the areas mainly in terrains with
barren and rugged mountains where several small streams and nullahs cross the
alignment. The area falls in the climate mostly under semiarid Mediterranean
influence and less monsoon effects with annual total around 400 mm. The average
temperature in summer varies from 18 to 40 oC whereas the winter average
temperatures range from 2 to 25 oC. However, the extreme temperatures could be
below 0 oC in winters and more than 40 oC in summers. The long term temperature
analysis (1974 to 2015) does not present any major deviation in the temperatures
both in summer and winters. Whereas long term rainfall pattern shows an increasing
trend in annual totals due to the fact that monsoon rains are moving upward towards
northern parts of the country. However, the study alignment moves further upward,
where such impact would not be that significant as Mediterranean disturbances
having more influence in upper parts of the alignment.
Based on the rainfall and runoff analysis in connection with the topography of the
area, there have been proposed 22 bridges to safely pass the runoff generated from
the upstream and adjoining areas. The design parameters for the bridges have been
provided based on hydraulic analysis under the study in order to pass the standard
floods safely (100-year). For bridges over major streams and nullahs, scour depth
analysis have also been provided. Similarly, for overland flow and minor natural
channels, 132 culverts have been proposed (including modification of 11 existing
ones) for which design parameters are also provided to safely pass standard flood
of 50-year recurrence interval.
The road is located in the range where topography varies from mild to steep. The
road may come mostly under the effect of direct flow from the hills in the form of
torrents as flash flood; also carrying mud/boulders on its way. To avoid this,
drainage channels along the road on hill sides connected to the nearest x-culverts
may be provided to protect the road, for which design has also been proposed. The
overland flow from the road itself may be passed through road-side drop structure
and connected to corresponding culvert or existing conveyance system
(watercourse or drain). In the design of culverts, there has been kept cushion for
such overland flow from the road itself, giving 20% (0.2 to 0.3 m) freeboard for all
culverts.
v
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CHAPTER-1
BACKGROUND
The subject road is connecting Peshawar with Kabul through Torkham and Jalalabad.
Peshawar is the capital of Khyber Pakhtunkhwa and the administrative centre and
economic hub for the Federally Administered Tribal Areas of Pakistan. Peshawar is
situated in a large valley near the eastern end of the Khyber Pass, close to the Pak
Afghan border. Known as “City on the Frontier”, Peshawar’s strategic location on the
cross roads of Central Asia and South Asia has made it one of the most culturally vibrant
and lively cities in the greater region. Peshawar is connected to Motorway system of
Pakistan through Motorway M-1.
Peshawar Northern Bypass having a definition of 4-lane dived Expressway provides link
between Motorway M-1 and Start Point of Peshawar – Kabul Motorway. Total Length of
the existing road from Peshawar (Hayatabad) to Kabul (Abdul Haq Square) is
approximately 281 KM (Project alignment between Peshawar and Kabul is shown in
Figure 1). The project is divided into following three sections:
Table 1: Project Sections
From Peshawar to Torkham, the terrain is very difficult in some reaches where the
alignment mostly follows valleys and hill slopes. Although the design is completed by
1
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
NHA for the section between Peshawar and Torkham but it is envisaged that the
consultant shall provide further value addition and improvement.
From Torkham to Jalalabad the existing 2-lane is being upgraded to 4-lane by FWO. The
work is held up due to various reasons, it shall now be redesigned/upgraded to
Motorway Standard. The distance from Torkham to Jalalabad is 76 Km.
From Jalalabad to Kabul using Kabul – Nangarhar Highway the existing road measures
139 km. The terrain is mountainous with hard rock and steep vertical slopes. Especially
about 50 km section after Sarobi. It is envisaged that total Motorway length shall be
around 265 Km1. Tunnels exist in Afghanistan section of the Highway.
In the first phase, the Consultant has been advised to carry out feasibility study and
preliminary design of Peshawar-Torkham Section. The Consultant have studied various
alignment alternates in order to achieve stipulated motorway standards. Options of
provision of tunnels in mountainous reach was also investigated. Final proposed
Motorway alignment from Peshawar-Torkham is shown in Figure 2.
1
As per TOR the length is 281 km.
2
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CHAPTER-2
OBJECTIVE AND SCOPE OF STUDY
The main objective of the study is to carry out hydrological investigations with
reference to the proposed alignment from Peshawar to Torkham in Khyber
Pakhtunkhwa province of Pakistan, expanding over a length of about 47 km. The
specific scope of the study however is:
1. To carry out hydrological investigation with the analysis of rainfall and
flood records supplemented by detailed field investigations for
development of new road alignment and providing required
2. Analyze and propose required cross-drainage structures for the safe
development and operation of the proposed alignment such as bridges,
culverts, support structures etc. against standard flood conditions (100
years for bridges and 50 years for culverts)
3. Submit recommendations based upon concise analysis supported by field
data for embankment, crossing/ drainage bridges, culverts etc. along the
proposed alignment.
The flyovers and other road crossing bridges are not discussed being not scope
of study. The geo-referenced location of the subject road is shown in Figure 2.
3
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CHAPTER-3
DESCRIPTION OF STUDY AREA
Proposed
Alignment
4
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
The climate of the area in which the new alignment falls is semiarid subtropical
continental highland type. The mean annual rainfall is approximately 450 mm, of
which 200 mm falls in March and April, with warm summers and cool winters. The
area falls out of the monsoon belt where the major portion of rainfalls occurs due
to western disturbances. The average daily maximum temperature of the hottest
month is 36°C and the average daily minimum of the coldest is -0.5°C.
The study alignment mainly falls in the Khyber Agency – Federally Administered
Tribal Areas. This the geological region of Pre-aravallis, metamorphic in general
including Precambrian and younger intrusions. The massive grey limestone with
sand and clay beds that makes up the Carboniferous Khyber Formation and the
slate, phyllites and schists with minor limestone and quartzite beds of the
Ordovician-Silurian Landi Kotal Formation in the eastern part of the Khyber
Agency. Mesozoic sediments occur in the western part of the Khyber Agency
(Kruseman and Naqvi, 1988). Near Warsak on the boundary with the Peshawar
Vale is a granite intrusion (Shah et al., 1980). In the western part Jurassic
limestone has been found (Meissner at al.,1975).
The Khyber Agency is mountainous without any well developed alluvial plain.
According to the available information, approximately 20 test-and tube wells have
been drilled in different valleys. The lithological data on two boreholes in the
Jamrud – Landi Kotal area indicate an ill-sorted mixture of clay and gravels,
probably with low transmissivity values. The depth to water level is quite large
(more than 30 m). If these boreholes are representative of the whole area, then
the groundwater development is not viable (Kruseman and Naqvi, 1988).
The land use is generally mild hilly terrain with barren and rugged mountains,
without a well-developed alluvial plain. However, the green valleys are also seen.
But it also has some beautiful valleys with plain cultivable lands. The elevation
varies from about 396 to 1050 along the alignment however, the hills are higher
than these. The soils are derived mainly from the local weathering of bedrock,
deposited by streams and rivers, though loess also occurs to some extent.
Landforms in the area are varied and include piedmont, plains, valleys, gravel
fans, rough broken land and gullied land. Level areas are loamy, while lowlands
are slightly to strongly calcareous. The content of organic matter and available
phosphorus is very low.
5
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
The population is scattered in the area with minimal road and other civil facilities.
Due to recent insurgencies in the FATA areas, it is also badly affected due to
refugees affecting the natural land use/ land cover of the area. The development
of new highway will play a major role in the development of this under-privileged
area as well as help further developing the trade.
6
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CHAPTER-4
HYDROLOGICAL INVESTIGATION
4.1 General
The hydrological investigation under the current study has been carried out to
analyze the climate cum flow regime in connection with the development of
Peshawar to Torkham highway extending over a stretch of 46 about. For such
development it is necessary to take all necessary deign and protection measures
for safe operation of the road after its development for its service life. The design
considerations and measures could be: appropriate embankment/ alignment,
cross drainage structures including bridges, culverts and drops structures to
safeguard against possible rainfall/ flooding or surface runoff, and inundation
impacts. For such type of structures, the recurrence interval is generally adopted
as 100 year for large bridges and 50 year for small structures and culverts
(Mutreja, 1990).
The land use layout of proposed alignment is such that it mainly passes through
mountainous terrains where the runoff flux due to rainfalls could be either from
the hills along the road or the natural steams or nullahs crossing the alignment.
This section therefore focuses to estimate the runoff flux to the road alignment so
that the protective measures and cross-drainage structures could be proposed to
safeguard the alignment. For this purpose, there could be two different
approaches or sometimes the combination of both to estimate the runoff
magnitude of standard return periods viz. i) Discharge frequency analysis using
observed data, and ii) well practiced and acceptable rainfall-runoff methods
making use of observed rainfall which is mostly available along with physical
characteristics of the catchment areas from where the runoff is generated. Such
hydrological analyses have been presented hereafter.
7
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
The rainfall is due to more Mediterranean influence and less monsoon effects
with annual total around 400 mm (Figure 5).
The temperature extremes were analyzed for study area as it plays significant
role in the material selection. For this purpose, long term annual maximum and
minimum temperatures were analyzed from the observed temperature data and
the results are shown in Figure 6. The general trend shows that during summer
the maximum temperature is higher than 45 oC with extremes of 48 oC. However,
8
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Whereas long term rainfall pattern shows an increasing trend in annual totals
(Figure 8). This is due to the fact that monsoon rains are moving upward towards
9
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
northern parts of the country – the unprecedented flood of 2010 and thereafter.
However, the study alignment moves further upward, where such impact would
not be that significant as Mediterranean disturbances having more influence in
upper parts of the alignment.
10
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Alternatively, long term rainfall extreme events play significant role to estimate
the standard rainfalls (100, 50, or 25 years). These standard rainfalls would be
then used to convert into runoff using standard rainfall-runoff methods, such as
SCS Synthetic Unit Hydrograph method. Therefore, under the current study, such
approach was followed. For the estimation of rainfall of standard recurrence
intervals, Generalized Extreme Value Distribution (GEV) is mostly used. In this
case, it is Type-I i.e. Gumbel Distribution for extreme events (a two parametric
distribution) which is well suited for most Pakistani catchments especially relating
frequency analysis. The frequency analysis of observed annual maximum
rainfalls (1974 to 2015) was carried out using widely accepted HEC-SSP
software developed by US Army Corps of Engineers (Figure 10). This ensures
more rigorous analysis for better decision making. The estimated rainfall
frequency curves are shown in Figure 11 (Gumbel) and Figure 12 (GEV).
11
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
100.0
10.0
0.9999 0.999 0.99 0.9 0.5 0.2 0.1 0.02 0.005 0.001 0.0001
Probability
Computed Curve Expected Probability Curve
5 Percent Confidence Limit 95 Percent Confidence Limit
Observed Events (Weibull plotting positions) Hig h Outlier
12
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
100.0
10.0
0.9999 0.999 0.99 0.9 0.5 0.2 0.1 0.02 0.005 0.001 0.0001
Probability
Computed Curve Expected Probability Curve
5 Percent Confidence Limit 95 Percent Confidence Limit
Observed Events (Weibull plotting positions) Hig h Outlier
The rainfall estimates for standard return periods of 50-year and 100-year are
drawn in Table 1, which indicate difference in standard rainfall estimates as 14%
to 21% between Gumbel and GEV distributions. However, for rainfall frequency
analysis relating major events, a recent global survey on the distribution of annual
maxima of daily rainfall by Apalexiou and Koutsoyiannis (2012) have provided
that GEV (Log Pearson Type III) distribution is most suitable for large return
periods. Therefore, the maximum estimates were adopted under the current
study and also in the light of increasing rainfall trends in Figure 4.
13
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
All such discharge estimates from each identified crossing stream and small
catchments overland flow to the alignment, were studied through hydraulic
analysis presented in the coming sections. This was done in order to see the
impact to the alignment and suggest accordingly the protective measures and
design parameters for necessary drainage structures.
14
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CHAPTER-5
HYDRAULIC INVESTIGATION
15
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
The model was run simultaneously in calibration/ validation process and the final
outcomes of the modeling results were drawn in Table 2, wherein the finish levels
of the road have been proposed in contrast to the highest flood levels through the
proposed bridges, keeping in view the safety of the proposed highway. The
hydraulic parameters for the bridges over these streams and nullahs are also
given in Annexure-C, whereas the hydraulic model outputs are given in
Annexure-D for further elaboration.
All the bridges have been so proposed to have sufficient capacity as the floods in
these areas also bring lot more mud and boulders along due to bare mountains
and steep slopes. For this purpose, the scour depth calculations have also been
made using Lacey Regime Theory (Lacey, 1946). The conditions of Lacey’s
regime are very rarely achieved and are very difficult to maintain in practice.
However, in rivers and streams only in bank full stage or high flood conditions, it
may be considered to achieve temporary or quasi-regime. The recognition of this
fact can be utilized to deal with the issues concerning scour and floods. The total
scour depth for each proposed bridge is therefore given in Table 2, whereas the
estimations are also provided in Annexure-E. As per general rule, the piling depth
for bridges is taken as double the scour depth.
16
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
RD/
Location on Total
Bridge Catchment 100-year discharge/ Deck Level Highest
Pesh- Scour
Structure Location/ Name of Size Area design capacity (top of road) Flood Level
S.#. Torkhum Depth
Road Type stream
Cell x 2
km km cumecs cusecs m m m
Span (m)
Chaura Khwar near 481.00
1 7+060 Bridge 7 x 40 425.31 2356 83119 497.225 8.02
Jamrud (481.00)
532.780
2 8+650 Bridge Nullah 1 x 30 0.53 12.72 449 542.500 1.26
(532.790)
537.060
3 8+890 Bridge Nullah 1 x 40 0.73 17.50 617 542.500 1.33
(537.060)
538.110
4 9+580 Bridge Nullah 1 x 40 1.41 34 1197 543.86 1.96
(538.110)
17
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
RD/
Location on Total
Bridge Catchment 100-year discharge/ Deck Level Highest
Pesh- Scour
Structure Location/ Name of Size Area design capacity (top of road) Flood Level
S.#. Torkhum Depth
Road Type stream
Cell x 2
km km cumecs cusecs m m m
Span (m)
824.50
9 24+700 Bridge Nullah 2 x 35 7.70 92.3 3257 828.000 1.85
(824.50)
867.030
11 25+810 Bridge Chingai Khwar 2 x 20 3.29 79 2780 870.000 2.59
(867.000)
958.630
13 30+460 Bridge Dand Khwar 1 x 25 9.00 154 5449 962.000 2.98
(958.630)
1003.660
14 33+000 Bridge Bori Khwar 1 x 20 6.80 117 4117 1006.000 2.87
(103.660)
1013.66
15 33+587 Bridge Sawal Khwar 1 x 20 9.00 154 5449 1017.000 3.05
(1013.660)
18
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
RD/
Location on Total
Bridge Catchment 100-year discharge/ Deck Level Highest
Pesh- Scour
Structure Location/ Name of Size Area design capacity (top of road) Flood Level
S.#. Torkhum Depth
Road Type stream
Cell x 2
km km cumecs cusecs m m m
Span (m)
1019.750
16 35+002 Bridge Nullah 1 x 25 1.36 32.8 1158 1024.000 1.93
(1019.760)
1024.870
17 36+410 Bridge Nullah 1 x 40 5.60 96 3390 1041.675 2.60
(1024.870)
949.130
18 39+680 Bridge Nullah 3 x 30 0.80 19.2 677 958.000 1.62
(949.110)
898.550
19 40+545 Bridge Wuch Tangi 1 x 40 9.75 117 4124 922.9 2.71
(898.560)
804.16
20 43+230 Bridge Nullah 1 x 30 3.20 55 1939 808.000 2.29
(804.160)
738.540
21 45+215 Bridge Nullah 1 x 40 15.00 181 6373 749.726 2.73
(738.570)
22 46+300 Bridge Giani at Torkham 4 x 25 29.20 350 12349 711.000 708.290 4.25
19
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
For this purpose, GIS applications were also made for estimating the catchments
characteristics (watershed area, main stream length, average slope, land use
etc.). This was done first estimating the standard runoff from standard rainfalls
(50 years) using HEC-HMS Computer Mode. The standard flow at respective
point of interest was estimated for using as input in the HY-8 Culvert Analysis
Computer Model to estimate viable culvert parameters (shape, number of cells,
width, height, freeboard).
20
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
On the basis of analysis, total 132 box culverts have been proposed including
improvement of 11 existing ones (Table 3). The design parameters are given in
Table 4 providing sufficient design capacity to safely pass the runoff generated
especially from the steep slopes along the road which also bring sediment/
boulders along with due to generally bare mountains. For such purposes, the
sufficient viable capacity of the culverts has been proposed.
Total 132
21
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
(Manning’s n=0.020 for concrete culverts; Curve Number for SCS Runoff Estimation CN=75 )
22
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
23
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
24
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
25
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
26
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
27
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
123 42+820 Provide new box culvert 1 2 1.5 0.075 1.27 1.39
124 43+690 Provide new box culvert 5 4 4 0.250 4.22 63.66
125 43+840 Provide new box culvert 1 2 4 0.092 1.55 4.62
126 44+380 Provide new box culvert 1 2 4 0.200 3.38 4.62
127 44+760 Provide new box culvert 1 2 4 0.102 1.72 4.62
128 44+890 Provide new box culvert 1 2 4 0.066 1.11 4.62
129 45+4360 Provide new box culvert 1 2 4 0.060 1.01 4.62
130 45+440 Provide new box culvert 1 2 3 0.060 1.01 3.30
131 45+650 Provide new box culvert 1 2 4 0.100 1.68 4.62
132 45+938 Provide new box culvert 1 4 1.5 0.161 2.72 3.43
28
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Rainfall
NSL
Road
For example an area of 500 m upto 50 m height of hill with 43 mm critical rainfall
(in 15 minutes) may bring about 0.24 cumecs (8.5 cusecs) to the road using
following Rational formula:
Q=CiA (1)
Where
Q = Discharge in cusecs
29
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
A = Area in acres
To avoid this, drainage channels along the road on hill sides connected to the
x-culverts may be provided to protect the road. Further, reinforced retaining walls
would also be required especially at steep slopes. The scheme along with design
of side channel is shown in Figure 15.
Rainfall
NSL
Adequate cut-off must be provided such that the maximum length of flow path in
the road drainage channel does not exceed up to a reasonable length, preferably
200 m. The cut-off must discharge to a natural watercourse. In the instant case, it
is proposed that drainage may be provided from the sides connecting through
drop structures with proper riprap arrangements (Figure 16) to avoid any rill
development of the embankment. Under the propose alignment, there is at least
one cross-drainage structure at about 300 m apart so the road overland flow may
be diverted to the nearest one through drop structures. And the given proposed
culverts have suffici9ent capacity with 20% freeboard to accommodate such
overland flows.
30
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
31
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CHAPTER-6
FINDINGS & RECOMMENDATIONS
32
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
References
33
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
ANNEXURES
34
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
35
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
36
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
37
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
2009
2010
2011 46.00 0.00
2012 45.00 -15.00
2013 44.00 0.00
2014 44.00 1.00
2015 43.00 2.00
38
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 8+650
39
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 8+890
Nullah at RD 9+580
40
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
41
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
42
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 24+700
43
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
44
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
45
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 35+002
46
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 36+410
Nullah at RD 39+680
47
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 43+230
48
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Nullah at RD 45+215
49
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Annexure-C: Hydrologic and Hydraulic Parameters relating Bridges over Major Streams/ Nullahs
Catchment
100-Year Channel
Channel Flow Flow
Discharge Velocity
Velocity at Area at Area at
Main at HFL HFL
Catchment Average Bridge Bridge bridge bridge
stream (Curve Bridge (before (with
Area Slope Size Location location location
Name of Stream/ Length Number Location bridge) bridge)
S.No. Location (before (before (with
Nullah CN for (with
bridge) bridge) bridge)
SCS bridge)
Runoff=75)
2 Cell x 2 2
km Km m/m cumecs m/sec m/sec m m m m
Span
Chaura Khwar
1 7+060 425.31 38.70 0.0388 2356 7 x 40 2.81 2.86 837.20 824.65 479.22 479.30
near Jamrud
2 8+650 Nullah 0.53 0.93 0.0690 12.72 1 x 30 0.49 0.55 26.12 23.05 532.79 532.78
3 8+890 Nullah 0.73 0.96 0.2190 17.5 1 x 40 0.63 0.64 27.60 27.14 537.06 537.06
4 9+580 Nullah 1.41 1.40 0.2764 34 1 x 40 0.92 1.10 36.91 30.90 538.11 538.11
Khyber Khwar at
5 21+920 70.00 20.00 0.0070 341 2 x 40 1.76 1.89 193.68 179.97 753.67 753.65
Ali Masjid
Khyber Khwar
6 22+560 69.80 19.80 0.0071 340 2 x 30 1.77 2.15 192.48 158.17 771.94 771.91
(RD22+560)
Khyber Khwar
7 22+765 69.60 19.60 0.0071 339 2 x 25 2.20 2.47 154.18 137.13 779.14 779.10
(RD22+765)
Khyber Khwar
8 23+950 63.00 18.00 0.0361 307 4 x 30 1.48 1.55 207.35 197.46 803.90 803.91
(RD23+950)
50
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Catchment
100-Year Channel
Channel Flow Flow
Discharge Velocity
Velocity at Area at Area at
Main at HFL HFL
Catchment Average Bridge Bridge bridge bridge
stream (Curve Bridge (before (with
Area Slope Size Location location location
Name of Stream/ Length Number Location bridge) bridge)
S.No. Location (before (before (with
Nullah CN for (with
bridge) bridge) bridge)
SCS bridge)
Runoff=75)
2 Cell x 2 2
km Km m/m cumecs m/sec m/sec m m m m
Span
9 24+700 Nullah 7.70 4.53 0.0838 92.3 2 x 35 0.94 1.43 97.89 64.43 823.24 823.28
Khyber Khwar
10 25+615 56.00 16.00 0.0406 273 1 x 40 1.74 2.50 156.70 109.40 836.24 836.17
(RD25+615)
11 25+810 Chingai Khwar 3.29 2.33 0.3425 79 2 x 20 0.90 1.53 87.73 51.71 867.00 867.03
Kagga Khwar at
12 28+700 8.45 3.49 0.2146 145 2 x 30 1.55 1.58 93.32 91.82 953.09 953.10
Wali Khel
13 30+460 Dand Khwar 9.00 4.50 0.1756 154 1 x 25 1.75 2.02 87.91 76.33 958.68 958.63
14 33+000 Bori Khwar 6.80 4.00 0.1595 117 1 x 20 0.81 2.74 144.33 42.71 1003.48 1003.84
15 33+587 Sawal Khwar 9.00 4.50 0.1818 154 1 x 20 1.08 2.94 142.30 52.35 1013.74 1015.13
16 35+002 Nullah 1.36 1.60 0.1119 32.8 1 x 25 0.63 0.99 52.46 33.04 1019.76 1019.75
17 36+410 Nullah 5.60 3.20 0.1678 96 1 x 40 2.44 2.44 39.32 39.32 1024.87 1024.87
18 39+680 Nullah 0.80 1.76 0.1403 19.2 3 x 30 1.07 1.12 18.02 17.14 949.10 949.13
19 40+545 Wuch Tangi 9.75 6.50 0.1418 117 1 x 40 1.65 1.73 70.99 67.81 898.56 898.55
51
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
Catchment
100-Year Channel
Channel Flow Flow
Discharge Velocity
Velocity at Area at Area at
Main at HFL HFL
Catchment Average Bridge Bridge bridge bridge
stream (Curve Bridge (before (with
Area Slope Size Location location location
Name of Stream/ Length Number Location bridge) bridge)
S.No. Location (before (before (with
Nullah CN for (with
bridge) bridge) bridge)
SCS bridge)
Runoff=75)
2 Cell x 2 2
km Km m/m cumecs m/sec m/sec m m m m
Span
20 43+230 Nullah 3.20 5.10 0.2049 55 1 x 30 1.45 1.45 37.89 37.89 802.82 802.82
21 45+215 Nullah 15.00 8.00 0.1373 181 1 x 40 1.61 1.79 112.21 100.99 738.57 738.54
22 46+300 Giani at Torkham 29.20 8.00 0.1415 350 4 x 25 1.88 1.98 186.30 177.07 708.28 708.30
52
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
500
Crit PF 1
Ground
Bank Sta
495
Elevation (m)
490
485
480
475
470
0 50 100 150 200 250 300 350
Station (m)
EG PF 1
548
WS PF 1
Crit PF 1
546 Ground
Bank Sta
544
542
Elevation (m)
540
538
536
534
532
530
0 50 100 150 200 250
Station (m)
53
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
546 Crit PF 1
Ground
Bank Sta
544
Elevation (m)
542
540
538
536
0 20 40 60 80 100 120 140
Station (m)
EG PF 1
WS PF 1
560 Crit PF 1
Ground
Bank Sta
555
Elevation (m)
550
545
540
535
0 50 100 150 200 250
Station (m)
54
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
762
Crit PF 1
Ground
Bank Sta
760
Elevation (m)
758
756
754
752
750
0 20 40 60 80 100 120 140 160
Station (m)
EG PF 1
WS PF 1
Crit PF 1
785 Ground
Bank Sta
780
Elevation (m)
775
770
765
0 20 40 60 80 100 120 140 160
Station (m)
55
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
Crit PF 1
790 Ground
Bank Sta
785
Elevation (m)
780
775
770
0 20 40 60 80 100
Station (m)
EG PF 1
816 WS PF 1
Crit PF 1
814 Ground
Bank Sta
812
Elevation (m)
810
808
806
804
802
800
0 100 200 300 400 500
Station (m)
56
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
830 Crit PF 1
Ground
Bank Sta
828
Elevation (m)
826
824
822
820
0 20 40 60 80 100 120 140 160
Station (m)
EG PF 1
WS PF 1
Crit PF 1
840 Ground
Bank Sta
838
Elevation (m)
836
834
832
0 50 100 150 200 250 300
Station (m)
57
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
880 WS PF 1
Crit PF 1
878 Ground
Bank Sta
876
Elevation (m)
874
872
870
868
866
864
0 20 40 60 80 100 120 140 160
Station (m)
EG PF 1
WS PF 1
Crit PF 1
958 Ground
Bank Sta
956
Elevation (m)
954
952
950
0 50 100 150 200
Station (m)
58
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
Crit PF 1
970 Ground
Bank Sta
965
Elevation (m)
960
955
950
0 50 100 150 200
Station (m)
EG PF 1
WS PF 1
Crit PF 1
1005 Ground
Bank Sta
1004
Elevation (m)
1003
1002
1001
0 50 100 150 200 250
Station (m)
59
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
Crit PF 1
1030 Ground
Bank Sta
1025
Elevation (m)
1020
1015
1010
0 50 100 150 200 250 300 350
Station (m)
EG PF 1
WS PF 1
1040 Crit PF 1
Ground
Bank Sta
1035
Elevation (m)
1030
1025
1020
1015
0 50 100 150 200 250
Station (m)
60
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
Crit PF 1
1060 Ground
Bank Sta
1050
Elevation (m)
1040
1030
1020
0 20 40 60 80 100 120 140
Station (m)
EG PF 1
WS PF 1
970 Crit PF 1
Ground
Bank Sta
965
Elevation (m)
960
955
950
945
0 50 100 150 200 250 300
Station (m)
61
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
950
Crit PF 1
Ground
Bank Sta
940
Elevation (m)
930
920
910
900
890
0 50 100 150 200 250 300 350 400
Station (m)
EG PF 1
WS PF 1
825 Crit PF 1
Ground
Bank Sta
820
Elevation (m)
815
810
805
800
0 10 20 30 40 50 60 70
Station (m)
62
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
EG PF 1
WS PF 1
Crit PF 1
755 Ground
Bank Sta
750
Elevation (m)
745
740
735
0 50 100 150 200 250 300 350
Station (m)
EG PF 1
718 WS PF 1
Crit PF 1
Ground
716 Bank Sta
714
Elevation (m)
712
710
708
706
704
0 50 100 150 200 250
Station (m)
63
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
64
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
D50 P=4.75*sqrt(Q)
Design
L
100-Year Lacey silt factor Sy
(Soil Type river width relation (actual channel
Discharge [1.76 SQRT(D50)] (scour depth)
S.# Location AASHTO to select Lacey width)
Q
A-1-b) Equation
mm cumecs f m m m
65
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
D50 P=4.75*sqrt(Q)
Design
L
100-Year Lacey silt factor Sy
(Soil Type river width relation (actual channel
Discharge [1.76 SQRT(D50)] (scour depth)
S.# Location AASHTO to select Lacey width)
Q
A-1-b) Equation
mm cumecs f m m m
66