Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

Doc No:

STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 1 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

PROJECT : PROVISION OF ENGINEERING, PROCUREMENT,


CONSTRUCTION AND COMMISSIONING OF
SANITARY TREATMENT SYSTEM (STS)
MODIFICATION AT GAS PROCESSING KERTIH
(GPK), PETRONAS GAS BERHAD

CLIENT : PETRONAS GAS BERHAD

PO. NO. : 3920133490

CONTRACT NO. : DTC-KTH/PGB-GPU/2020/0011

DOCUMENT TITLE : PROCESS AND OPERATING PHILOSOPHY

DOC. REVIEW : Z
CLASSIFICATION

SECURITY : OPEN
CLASSIFICATION

0 02.11.21 ISSUED AS FINAL NR ZIZ MAR


Prep’d Rev’d App’d Rev’d End’d App’d
Rev Date Description By By By By By By
MAWGSB PGB

© 2020 PETROLIAM NASIONAL BERHAD (PETRONAS). All rights reserved. No part of this document may be reproduced, stored
in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or
otherwise) without the permission of the copyright OWNER.
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 2 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

TABLE OF CONTENT

1.0  INTRODUCTION ....................................................................................................................3 
1.1  PROJECT OVERVIEW (BACKGROUND) .................................................................................................... 3 
1.2  OBJECTIVE........................................................................................................................................ 4 
1.3  DEFINITION ...................................................................................................................................... 4 
1.4  ABBREVIATION .................................................................................................................................. 4 
2.0  APPLICABLE CODES AND STANDARDS ...................................................................................5 
2.1  NATIONAL REGULATORY STANDARD ..................................................................................................... 5 
2.2  PETRONAS TECHNICAL STANDARD (PTS) ............................................................................................ 5 
2.3  ORDER OF PRECEDENCE ..................................................................................................................... 5 
3.0  PROJECT SCOPE ....................................................................................................................5 
4.0  PROCESS AND OPERATING PHILOSOPHY ...............................................................................7 
4.1   PROCESS AND OPERATING PHILOSOPHY FOR SANITARY PIT AND PUMP .................................... 7 

4.1.1  REFERENCE DRAWING/DOCUMENT: ..................................................................................................... 7 
4.1.2  FUNCTIONAL DESCRIPTION ................................................................................................................. 7 
4.1.3  CONTROLLER/SELECTOR/COMPUTING REQUIREMENT ........................................................................... 10 
4.2  PROCESS AND OPERATING PHILOSOPHY FOR SEWERAGE TREATMENT SYSTEM (STS) ............. 12 
4.2.1  REFERENCE DRAWING/DOCUMENT: ................................................................................................... 12 
4.2.2  FUNCTIONAL DESCRIPTION ............................................................................................................... 12 
4.2.3  CONTROLLER/SELECTOR/COMPUTING REQUIREMENT ........................................................................... 14 
5.0  CONTROL NARRATIVE ......................................................................................................... 16 
5.1  NPS (G2‐984, G2‐983, G3‐984, G‐756 & G4‐984) ........................................................................ 16 
5.1.1  AUTO MODE .................................................................................................................................. 12 
5.1.2  MANUAL MODE ............................................................................................................................. 17 
5.2  NPS (GH‐983) .............................................................................................................................. 17 
5.2.1  AUTO MODE .................................................................................................................................. 12 
5.2.2  MANUAL MODE ............................................................................................................................. 18 
5.3  SEWERAGE TREATMENT SYSTEM (STS) ....................................................................................... 19 
5.3.1  AUTO MODE .................................................................................................................................. 12 
5.3.2  MANUAL MODE ............................................................................................................................. 20 
5.3.3  EMERGENCY STOP ........................................................................................................................... 20 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 3 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

1.0       INTRODUCTION 
1.1. Project Overview (Background) 
The  objective  of  this  project  is  to  improve  and  to  upgrade  existing  sewerage  treatment 
system in GPK Plant and to meet Environment Quality Sewerage 2009 Regulation by 2020. 
 
The  existing  Sanitary  Treatment  System  consist  six  (6)  numbers  of  Sanitary  Pit  and  the 
Sanitary  Pit  consist  of  pumps,  electrical  power,  flow  meter,  level  transmitter  etc.  The  pit 
receives  and  process  raw  sewage  influent  from  maintenance  area,  non‐process  building, 
warehouse and laboratory, control building CCR123 and control building CCR4, then all the 
process raw sewage out to the treatment plant, which consist of Parshall Flume, settling tank 
and oxidation pond. 
 
All sewage was transfer from one pit to another pit and lastly to the oxidation pond through 
pump  and  underground  pipe.  The  oxidation  pond  is  where  biological  treatment  process 
takes place before treated effluent is discharge into the storm sewer. 
 
Sewerage Treatment System (STS) in GPK Plant can be schematically describes as below: 
 
Figure 1.1(a): Existing Sewage Treatment System (STS) at GPK 
 
 
 
  (NEAR CCR4)
  PIT : G4-984
PUMP : P4-982A/B
  (ADMIN BUILDING)
  OLD TREATMENT
  SYSTEM
(NEAR FLARE)
  PIT: G3-984
  PUMP : P3-981A/B
  (NEAR LAB M2-701)
  PIT : G2-983
PUMP : P2-981A/B
 
 
OXIDATION POND
 
 
 
 
  PIT : G-984 (NEAR WAREHOUSE)
  PUMP : P-989A/B PIT : G-756
PUMP : P-754A/B
 
 
(NEAR CCR 123)
  PIT : G2-984
  PUMP : P2-982A/B
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 4 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

 
However,  based  on  Situational  Assessment,  most  equipment’s  are  not  functioning  (i.e. 
pumps,  electrical  power,  flow  meter  and  level  transmitter  etc.).  Other  than  that,  existing 
underground pipelines also suspected leak at a few areas which are unable to transfer the 
sewage to the oxidation pond.  
 
1.2. Objective  
The  objective  of  this  report  is  to  present  the  process  and  operating  philosophy  and 
assumptions used in Basic Engineering Design for Sewerage Treatment System (STS) at Gas 
Processing Kertih (GPK). 
 
 
1.3. Definition 
COMPANY    PETRONAS GAS BERHAD 
CONTRACTOR    M.A.W GLOBAL SDN BHD 
VENDOR  The party that manufactures or supplies equipment and services to 
perform the duties specified by the CONTRACTOR. 
SUB‐VENDOR  The  party  or  parties  that  has  or  have  entered  a  contract  with  the 
VENDOR for the performance of any part of the SCOPE OF WORK. 
Third Party  A person or company independent of the manufacturer or VENDOR 
and shall be appointed by the VENDOR who is responsible to ensure 
the  item  is  designed,  fabricated,  inspected,  tested,  delivered  and 
installed in accordance with this Requisition/Purchase Order. 
WORK/SERVICES  This  shall  include  any  authorization  for  works,  services  or  changes 
which will be issued by VENDOR from time to time and shall become 
part  of  the  scope  of  WORK/SERVICES  whereby  all  terms  and 
conditions of this requisition shall govern. 
Project Data Sheets  Governing technical documents for the specific item(s) for purchase. 
Project Drawings  Reference drawings for the specific item(S) for purchase. 
Shall    Indicate a requirement 
Should    Indicate a recommendation 
 
 
1.4. Abbreviation 
ANSI      American National Standards Institute  
API    American Petroleum Institute 
ASME    American Society of Mechanical Engineer 
ASTM    American Society for Testing and Materials 
HAZOP    Hazard and Operability Study 
ISO    International Organisation for Standardisation 
MAWG    M.A.W Global Sdn Bhd 
NACE    National Association of Corrosion engineers 
P&ID    Piping and Instrumentation Diagram 
PTS    PETRONAS Technical Standard 
RAS    Return Activated Sludge  
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 5 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

SPAN  Suruhanjaya Perkhidmatan Air Negara 
MLSS  Mixed Liquor Suspended Solid 
pH  Potential of Hydrogen 
DCS  Distributed Control System 
LCP  Local Control Panel 
STS  Sanitary Treatment System 
NPS  Network Pumping Station 
LCD  Liquid Crystal Display 
 
2.0 APPLICABLE CODES AND STANDARDS 
This  section  identifies  the  latest  editions  of  applicable  codes  and  standards  to  be  used  for 
this  project.  As  a  minimum,  the  design  in  accordance  with  accepted  design  practices, 
applicable sections of the PETRONAS Technical Standard, the relevant sections of the latest 
national/international codes, standards and regulations as listed below: 
 
2.1. National Regulatory Standard 
Interim Report: (May 2019)  Technical Standard for Sewerage System less than 10,000PE 
by SPAN 
 
2.2. PETRONAS Technical Standard (PTS) 
PTS 12.30.01      Piping Classes – Basic of Design 
PTS 12.30.02      Piping General Requirement 
 
2.3. Order of Precedence 
In  the  event  that  there  are  conflicts  with  items  or  information  contained  within  the 
document,  the  following  order  of  precedence  shall  be  used  when  interpreting  the 
information of COMPANY provided documentation and references. Any deviations from the 
approved documents shall require COMPANY approval prior to implementation: 
 
1. National  or  local  regulatory  standards  where  the  WORK  is  being  performed  and/or 
where the facilities are to be installed. 
2. Contractual  requirements  and  project  specific  requirements  or  standards  (e.g. 
Specifications, Datasheets, Drawings etc.). 
3. Other  relevant  COMPANY  standards  and  procedures  such  as  Petronas  Gas  Berhad 
Standard Procedures, PETRONAS Gas HSE Management Standard etc. 
4. The latest PETRONAS Technical Standards (PTS) – June 2018 and its supplementary. 
5. International Codes and Practices (e.g. API, ASME, ASTM, ANSI, ISO, AWS, AISC, IEC, BS, 
IP & etc.). 

Where waiver or non‐compliance to codes and standards are required, the approval from 
relevant matrix custodians within COMPANY shall be adhered to. 

3.0 PROJECT SCOPE 
Existing  sewerage  system  in  Gas  Processing  Kertih  (GPK)  is  consist  of  four  (4)  sanitary  pit 
which collecting sewage flow from nearby buildings and two (2) sanitary pit as intermediate 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 6 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

sanitary pit. There is also one (1) existing small treatment plant that collecting the sewage 
from  non‐process  area  (administration  building,  surau  and  cafeteria).  Each  sanitary  is 
provide with sanitary pump to transfer collected sewage using underground piping network 
to  existing  Sewerage  Treatment  System  (STS)  which  consist  of  Settling  Tanks  and  Bio 
Oxidation  Ponds.  Treated  water  from  existing  Bio  Oxidation  Pond  is  flows  to  storm  sewer 
which leads to river/water body. 
 
Under this project, the following is upgraded: 
a) All existing sanitary pumps (inclusive instrumentation and control system) to be changed 
to new submersible pump as per SPAN guidelines. 
b) All  existing  UPVC  underground  pipe  for  sewage  transfer  in  between  sanitary  pits  and 
Sewerage  Treatment  System  (STS)  to  be  changed  to  Ductile  Iron  with  High  Alumina 
Internal Cement Lining as per SPAN guidelines. 
c) Existing  Sewerage  Treatment  System  (STS)  to  be  upgraded  to  Extended  Aeration  (EA) 
system to treat sewage fluid collected from sanitary pits before released to storm sewer. 
However,  based  on  the  site  assessment  and  value  re  ‐  engineering  exercise,  the  following 
had been decided: 
i) Pit G‐984 will be decommissioned and all the flow from the pit G‐756 will be transfer to 
G2‐984 prior to further transfer to EA STS by pumping system. 
ii) New Pit, GH‐981 will be construct near to non‐process treatment plant and the sewage 
from administration building will be transfer to G2‐983 by pumping system.  
The  new  designed  sewerage  treatment  system  at  GPK  can  be  schematically  described  as 
figure 3.1 (a) below. 
 
Figure 3.1(a): Proposed Sewage Treatment System (STS) at GPK 
 
 
(NEAR CCR4)  
PIT: G4-984  
PUMP: P4-982A/B   (ADMIN BUILDING)
  PIT: GH-983
  PUMP: PH-981A/B
  (NEAR FLARE)
PIT: G3-984
  PUMP: P3-981A/B
  (NEAR LAB M2-701)
  PIT: G2-983
PUMP: P2-981A/B
 
 
E.A 400 P.E STS
 
 
 
 
  (NEAR WAREHOUSE)
(NEAR CCR 123)
  PIT: G-756
PIT: G2-984
PUMP: P-754A/B
  PUMP: P2-982A/B
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 7 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

4.0    PROCESS AND OPERATING PHILOSOPHY 
 
4.1  Process and Operating Philosophy for Sanitary Pit and Pump 
 
4.1.1  Reference Drawing/Document: 
a)   Process Flow Diagram (PFD), Sanitary System ‐ Dwg No: STS‐EXE‐MAW‐981‐PRO‐PFD‐001 
b)   Utility Flow Diagram (UFD), Sanitary System ‐ Dwg No: STS‐EXE‐MAW‐981‐PRO‐UFD‐001 
c)   Utility Flow Diagram (UFD), Sanitary System ‐ Dwg No: STS‐EXE‐MAW‐981‐PRO‐UFD‐002 
  d)   Process Design Basis – Doc No: STS‐EXE‐MAW‐981‐PRO‐DES‐0001 
 
4.1.2  Functional Description 
  Sanitary Pump is designed to transfer sewerage fluid from Sanitary Pit into the Intermediate 
Sanitary Pit or into the Sewerage Treatment System (STS).  
 
a) Below is summary of process control philosophy for sanitary pump: 
 
Table 3.1.2 (a): Operating and Operating Philosophy for Equipment in Sanitary Pit 
Service  Screen  Pump Tag No  Operating Philosophy  Remark 
Tag. No  (Pump) 
GH‐983  GH‐981  PH‐981A / PH‐981B  One Duty & One Standby  Local 
Automation 
G2‐983  G2‐981  P2‐981A / P2‐981B  One Duty & One Standby  DCS 
G3‐984  G3‐982  P3‐981A / P3‐981B  One Duty & One Standby  DCS 
G2‐984  G2‐982  P2‐982A / P2‐982B  One Duty & One Standby  DCS 
G‐756  G‐763  P‐754A / P‐754B  One Duty & One Standby  DCS 
G4‐984  G4‐982  P4‐982A / P4‐982B  One Duty & One Standby  DCS 
 
b) Sanitary Pump PH‐981A/B shall control by Radar Level Transmitter which able to detect 
Low  Level  (L),  High  Level  (H)  and  High  High  Level  (HH)  according  to  the  level  set‐point 
settings at LCP. Duty Pump shall start automatically once High Level (H) is detected. Duty 
Pump shall stop automatically once achieve the Low Level (L) setting. Meanwhile, Duty 
and Standby Pumps shall run automatically once level increase to High High Level (HH) 
and both pumps shall stop once level reach back to Low Level (L) setting. Indication Light 
as  alarm  shall  light  on  automatically  once  level  increase  to  High  High  Level  (HH). 
Emergency  Stop  Button  should  be  located  at  LCP  to  shut  off  Sanitary  Pump  quickly  in 
case of any emergency. 
 
c) For others Sanitary Pump P2‐981A/B, P3‐981A/B, P2‐982A/B, P‐754A/B and P4‐982A/B, 
it shall control by Radar Level Transmitter which able to detect Low Level (L), High Level 
(H)  and  High  High  Level  (HH)  according  to  the  level  set‐point  settings  at  DCS.  LCP  shall 
receive  command  signal  from  DCS  to  start  and  stop  the  pumps.  Duty  Pump  shall  start 
automatically  once  High  Level  (H)  set‐point  is  detected.  Duty  Pump  shall  stop 
automatically once achieve the Low Level (L) setting.  
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 8 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

Meanwhile,  Duty  and  Standby  Pumps  shall  start  automatically  once  level  increase  to 
High High Level (HH) set‐point and both pumps shall stop once level reach back to Low 
Level (L) set‐point. Start and stop signals also available in DCS for monitoring and control. 
Emergency  Stop  Button  should  be  located  at  LCP  to  shut  off  Sanitary  Pump  quickly  in 
case of any emergency. 
 
Figure 3.1.2(b): Level Control by Radar Level Transmitter in Sanitary Pit 

Level Settings not as per


P&ID L, 600 mm, H
=1100, HH, 1250 mm

 
Note: Level Setting for all pit except Pit G3‐984 (L = 400, H = 500, HH = 150) 
 
d) In  new  Sanitary  Pit  GH‐983,  sewage  from  Admin  Building  shall  flow  through  Sanitary 
Screen GH‐981 before accumulates in Sanitary Pit. One of Sanitary Pump (P2‐981A/B), as 
Duty Pump shall start automatically once High Level (H) set‐point is detected to transfer 
sewage  into  the  Sanitary  Pit  G2‐983.  Duty  Pump  shall  stop  automatically  once  achieve 
the  Low  Level  (L)  set‐point.  Meanwhile,  Duty  and  Standby  Pumps  shall  start 
automatically once level increase to High High Level (HH) set‐point and both pumps shall 
stop once level reach back to Low Level (L) set‐point. 
 
e) In  Sanitary  Pit  G2‐983,  sewage  from  laboratory  M2‐701,  nearby  building  and  from  Pit 
GH‐983  shall  flow  through  Sanitary  Screen  G2‐981  before  accumulates  in  Sanitary  Pit. 
One  of  Sanitary  Pump  (P2‐981A/B),  as  Duty  Pump  shall  start  automatically  once  High 
Level  (H)  set‐point  is  detected  to  transfer  sewage  into  the  Sanitary  Pit  G3‐984.  Duty 
Pump shall stop automatically once achieve the Low Level (L) set‐point. Meanwhile, Duty 
and Standby Pumps shall start automatically once level increase to High High Level (HH) 
set‐point and both pumps shall stop once level reach back to Low Level (L) set‐point. 
 
 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 9 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

f) In intermediate Sanitary Pit G3‐984, sewage from Sanitary Pit G2‐983 shall flow through 
Sanitary  Screen  G‐982  before  accumulates  in  Sanitary  Pit.  One  of  Sanitary  Pump  (P3‐ 
981A/B), as Duty Pump shall start automatically once High Level (H) set‐point is detected 
to transfer sewage into the Sewerage Treatment System (STS) (refer 3.2 for Process and 
Operating Philosophy of STS). Duty Pump shall stop automatically once achieve the Low 
Level  (L)  set‐point.  Meanwhile,  Duty  and  Standby  Pumps  shall  start  automatically  once 
level  increase  to  High  High  Level  (HH)  set‐point  and  both  pumps  shall  stop  once  level 
reach back to Low Level (L) set‐point. 
 
g) In Sanitary Pit G‐984, sewage from Control Building H2‐702 and G‐756 shall flow through 
Sanitary  Screen  G2‐982  before  accumulates  in  Sanitary  Pit.  One  of  Sanitary  Pump  (P2‐ 
982A/B), as Duty Pump shall start automatically once High Level (H) set‐point is detected 
to transfer sewage into the Sewerage Treatment System (STS) (refer 3.2 for Process and 
Operating Philosophy of STS). Duty Pump shall stop automatically once achieve the Low 
Level  (L)  set‐point.  Meanwhile,  Duty  and  Standby  Pumps  shall  start  automatically  once 
level  increase  to  High  High  Level  (HH)  set‐point  and  both  pumps  shall  stop  once  level 
reach back to Low Level (L) set‐point. 
 
h) In  Sanitary  Pit  G‐756,  sewage  from  Control  Room  CCR  123  shall  flow  through  Sanitary 
Screen  G‐763  before  accumulates  in  Sanitary  Pit.  One  of  Sanitary  Pump  (P‐754A/B),  as 
Duty Pump shall start automatically once High Level (H) set‐point is detected to transfer 
sewage  into  the  Sanitary  Pit  G2‐984.  Duty  Pump  shall  stop  automatically  once  achieve 
the  Low  Level  (L)  set‐point.  Meanwhile,  Duty  and  Standby  Pumps  shall  start 
automatically once level increase to High High Level (HH) set‐point and both pumps shall 
stop once level reach back to Low Level (L) set‐point. 

i) In Sanitary Pit G4‐984, sewage from Control Room shall flow through Sanitary Screen G4‐ 
982  before  accumulates  in  Sanitary  Pit.  One  of  Sanitary  Pump  (P4‐982A/B),  as  Duty 
Pump  shall  start  automatically  once  High  Level  (H)  set‐point  is  detected  to  transfer 
sewage into the Sewerage Treatment System (STS) (refer 3.2 for Process and Operating 
Philosophy  of  STS).  Duty  Pump  shall  stop  automatically  once  achieve  the  Low  Level  (L) 
set‐point.  Meanwhile,  Duty  and  Standby  Pumps  shall  start  automatically  once  level 
increase  to  High  High  Level  (HH)  set‐point  and  both  pumps  shall  stop  once  level  reach 
back to Low Level (L) set‐point. 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 10 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

4.1.3  Controller/Selector/Computing Requirement 
a)  Sanitary Pump PH‐981A/B are local automation control by LCP. Two modes are available 
for selection: 
i)  AUTO Mode: Sanitary Pump either selected Sanitary Pump shall start and stop based 
on level set‐point setting in Sanitary Pit. 
ii)  MANUAL  Mode:  Pump  either  selected  Sanitary  Pump  shall  start  manually  via  local 
pushbutton. 
Duty  Pump  shall  stop  during  low  level  (L)  on  any  mode  to  protect  pump  from  running 
dry. 
 
b)  For others Sanitary Pump P2‐981A/B, P3‐981A/B, P2‐982A/B, P‐754A/B and P4‐982A/B, 
it shall be start and stop thru LCP automatically by receiving command signal from DCS. 
Start and stop signals are also available in DCS for monitoring and control. Two modes 
are available for selection at LCP: 
i)  AUTO  Mode:  Sanitary  Pump  either  selected  Sanitary  Pump  shall  start  and  stop 
based on level in Sanitary Pit via DCS. 
ii)  MANUAL Mode: Pump either selected Sanitary Pump shall start manually via local 
pushbutton. 
Duty Pump shall stop during low level (L) on any mode to protect pump from running 
dry. 
 
b)  Proposed level set‐point settings for Sanitary Pump are as follows: 

Table 3.1.3(a): Proposed Level set‐point settings for Sanitary Pit 
Sanitary  Sanitary  Settings  Proposed Level  Action  Remark 
Pit No.  Pump  Set‐point Settings 
(mm)NOTE1 
GH‐983  PH‐981A/B  High High (HH)  1250  Duty & Standby  Duty & Standby 
Pumps shall start  Pumps shall stop 
once level reach back 
to Low Level (L) 
High (H)  1100NOTE2  Duty Pump shall   
start 
NOTE2
Low (L)  600   Duty Pump shall   
stop 
G2‐983  P2‐981A/B  High High (HH)  1250  Duty & Standby  Duty & Standby 
Pumps shall start  Pumps shall stop 
once level reach back 
to Low Level (L) 
High (H)  1100NOTE2  Duty Pump shall   
start 
NOTE2
Low (L)  600   Duty Pump shall   
stop 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 11 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

Sanitary  Sanitary  Settings  Proposed Level  Action  Remark 


Pit No.  Pump  Set‐point Settings 
(mm)NOTE1 
G3‐984  P3‐981A/B  High High (HH)  1050  Duty & Standby  Duty & Standby 
Pumps shall start  Pumps shall stop once 
level reach back to 
Low Level (L) 
High (H)  900NOTE2  Duty Pump shall   
start 
Low (L)  400NOTE2  Duty Pump shall   
stop 
G2‐984  P‐982A/B  High High (HH)  1250  Duty & Standby  Duty & Standby 
Pumps shall start  Pumps shall stop once 
level reach back to 
Low Level (L) 
High (H)  1100NOTE2  Duty Pump shall   
start 
Low (L)  600NOTE2  Duty Pump shall   
stop 
G‐756  P‐754A/B  High High (HH)  1250  Duty & Standby  Duty & Standby 
Pumps shall start  Pumps shall stop once 
level reach back to 
Low Level (L) 
High (H)  1100NOTE2  Duty Pump shall   
start 
Low (L)  600NOTE2  Duty Pump shall   
stop 
G4‐984  P‐982A/B  High High (HH)  1250  Duty & Standby  Duty & Standby 
Pumps shall start  Pumps shall stop once 
level reach back to 
Low Level (L) 
High (H)  1100NOTE2  Duty Pump shall   
start 
Low (L)  600NOTE2  Duty Pump shall   
stop 
Note: 
(1) Level is from bottom of Sanitary Pit. 
(2) Difference  between  Duty  Pump  start  (Level  High)  and  Duty  Pump  stop  (Level  Low)  is  equal/more 
than 450mm as per requirement in Technical Standard for Sewerage System for less than 10000PE 
by SPAN. 
 
 
 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 12 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

4.2  Process and Operating Philosophy for Sewerage Treatment System (STS) 
 
4.2.1  Reference Drawing/Document: 
a) Process Flow Diagram (PFD), Sewerage Treatment System –  
Dwg No : STS‐EXE‐MAW‐981‐PRO‐PFD‐002 
b) Utility Flow Diagram (UFD), Sanitary System –  
Dwg No : STS‐EXE‐MAW‐981‐PRO‐UFD‐003 
c) Process Design Basis ‐ Doc No: STS‐EXE‐MAW‐981‐PRO‐DES‐0001 
 
4.2.2  Functional Description 
Sewerage Treatment System (STS) is designed using Extended Aeration (EA) system in order 
to  treat  all  sewage  collected  from  all  area  in  Gas  Processing  Kertih  (GPK)  Plant  prior  to 
discharge to storm sewer.  
 
STS are local automation control via LCP at Blower House‐Electrical Room and only certain 
signal status such as pump, mixer, blower, analyzer and flow transmitter are being transmit 
to DCS for monitoring. 
 
a)   Below is summary of process and operating philosophy for equipment within Sewerage 
Treatment System (STS): 
 
Table 3.2.29(a): Process and Operating Philosophy for Equipment in STS 
  Service  Operating Philosophy 
  Equalization Tank Pump  One Duty & One Standby (2x100%) 
 
Aeration Tank Pump  One Duty & One Standby (2x100%) 
 
Submersible Mixer  One Duty (1x100%)  
 
Aeration Blower  One Duty & One Standby (2x100%) 
 
b)   One of Equalization Tank Pump (P2‐983A/B), as Duty Pump shall start automatically once 
High  Level  (H)  set‐point  setting  is  detected  by  Radar  Level  Transmitter  setting  (as 
default)  to  transfer  sewage  through  flow  control  box  into  the  Anoxic  Tank.  Duty  Pump 
shall stop automatically once achieve the Low Level (L) set‐point. Meanwhile, Duty and 
Standby Pumps shall start automatically once level increase to High High Level (HH) set‐
point  and  both  pumps  shall  stop  once  level  reach  back  to  Low  Level  (L)  set‐point. 
Equalization Tank Pump shall start and stop from LCP located in Blower House‐Electrical 
Room and monitoring signal status shall be transmit to DCS. As safeguarding protection 
to avoid dry condition in Equalization Tank, the Float Switch via vendor package is install 
at Level Switch Cutt Off Level (LSLL). Proposed level setting for Equalization Tank as table 
below:  
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 13 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

Table 3.1.3(a): Proposed Level Settings for Equalization Tank
Sanitary  Sanitary  Settings  Proposed Level  Action  Remark 
Pit No.  Pump  Set‐point Settings 
(mm)NOTE1 
G2‐990  PH‐983A/B  High High (HH)  2950  Duty & Standby  Duty & Standby 
Pumps shall  Pumps shall stop 
start  once level reach 
back to Low Level (L) 
High (H)  1950  Duty Pump shall   
start 
Low (L)  1450  Duty Pump shall   
stop 
Level Switch  1350 NOTE2  Duty Pump shall   
Cut Off (LSLL)  stop 
Note: 
(1) Level is from bottom of Sanitary Pit. 
(2) Set‐point setting for Float Switch. 
    
c) Anoxic  Tank  Mixer  (R2‐982)  to  operate  intermittently  base  on  timer  setting  for  de‐
nitrification process and transfer to Aeration Tank. Anoxic Mixer (R2‐982) shall start and 
stop via LCP located in Blower House‐Electrical Room and signal status shall transmit to 
DCS  for  monitoring.   If  fine  tuning  of  the  treatment  system  is  required,  timer  settings 
can be applied at the LCP for the Anoxic Mixer (R2‐982).  
 
d) In the Equalization Tank (G2‐990), the Dissolved Oxygen Analyzer (AT‐03A) shall install 
to measure the total oxygen content. Dissolved Oxygen Analyzer (AT‐03A) readings can 
be monitor on the LCD at site and DCS. The amount of Dissolve Oxygen shall 2.0mg/l. 
 
e) One of Aeration Tank Pump (P2‐984A/B), to operate intermittently to transfer MLSS to 
Anoxic  Tank  (G2‐992),  while  the  other  Aeration  Tank  Pump  is  meant  as  standby. 
Aeration Tank Pump (P2‐984A/B) shall start and stop from LCP located in Blower House‐
Electrical Room and signal status shall be transmit to DCS for monitoring. 
 
f) In  the  Aeration  Tank  (G2‐993),  the  Dissolved  Oxygen  Analyzer  (AT‐03B)  shall  install  to 
measure the total oxygen content. Dissolved Oxygen Analyzer (AT‐03B) readings can be 
monitor on the LCD at site and DCS. The amount of Dissolve Oxygen shall 2.0mg/l. 
 
g) In  the  Aeration  Tank  (G2‐993),  the  Mixer  Liquor  Suspended  Solid  (MLSS)  Analyzer  (AT 
004) shall install to measure the total  MLSS  content. MLSS Analyzer (AT‐004) readings 
can be monitor on the LCD at site and DCS. 
 
 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 14 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

h) One  of  Air  Blower  (R2‐981A/B)  to  run  alternately  (as  default)  to  supply  air  to 
Equalization  Tank  (G2‐990),  Aeration  Tank  (G2‐993),  Secondary  Clarifier  Tank  and 
Sludge  Holding  Tank  (G2‐991),  while  the  other  Air  Blower  (R2‐981A/B)  is  meant  as 
standby  (2x100%).  Air  Blower  (R2‐981A/B)  shall  start  and  stop  from  LCP  located  in 
Blower House‐Electrical Room and signal status shall be transmit to DCS for monitoring.
If fine tuning of the treatment system is required, Timer settings can be applied at the 
LCP for the Air Blower (R2‐981A/B). 
 
i) Effluents from Disinfection Chamber (G2‐995) need to pass through Parshall Flume (G2‐
996) before flowing to Final Sampling Point (G2‐997). Inside the Parshall Flume, there is 
a pH Analyzer (AT‐002) and Ultrasonic Flow Transmitter (FT‐001) to measure hydrogen‐
ion  activity  (acidity  or  alkalinity)  in  solution  and  to  measure  the  treated  effluent 
quantity  before  discharge  to  storm  sewer.  PH  Analyzer  (AT‐002)  and  Ultrasonic  Flow 
Transmitter (FT‐001) readings can be read on the LCD at site and DCS. 

4.2.3  Controller/Selector/Computing Requirement 
a) Equalization  Tank  Pump  (P2‐983A/B)  and  Anoxic  Tank  Mixer  (R2‐982)  shall  start  and 
stop via LCP located in Blower House‐Electrical Room and signal status shall be transmit 
to DCS for monitoring.  There are two (2) modes are available for selection at LCP: 
 
i) AUTO Mode: Either selected Equalization Pump shall start and stop via Radar Level 
Transmitter  which  able  to  detect  Low  Level  (L),  High  Level  (H)  and  High  High  Level 
(HH)  according  to  the  level  set‐point  settings  at  LCP.  Float  Switch  to  detect  Level 
Switch Cut Off Level (LSLL) as safeguarding to protect pump from running dry. Mixer 
and Blower to start and stop based on timer settings at LCP. 
 
ii) MANUAL  Mode:  Either  selected  Equalization  Tank  Pump,  Aeration  Tank  Pump, 
Anoxic  Tank  Mixer  and  Aeration  Blower  to  start  manually  via  local  pushbutton. 
Under manual mode of operation, all the above equipment can be set to start and 
stop without any restricted control by turning on the key‐switch at LCP. 
 
b)  Aeration Tank Pump (P2‐984A/B), Anoxic Tank Mixer (R2‐982) and Aeration Blower (R2‐
981A/B)  to  start  and  stop  based  on  timer  settings.  Following  is  the  summary  of  timer 
settings for those equipment: 
 
Table 3.2.3.(a): Mixer and Aeration Blower Timer Settings 
  Equipment  Timer Settings  Remarks 
   
 
Aeration Tank Pump  1 hours x 4 times/day  Pump  to  operate  intermittently  base  on 
 
timer  setting  with  cumulative  of  4  running 
 
hours  per  day.  Running  hours  can  be 
 
divided  evenly  within  8  hours  with  1  hour 
 
rest interval. 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 15 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

 
  Equipment  Timer Settings  Remarks 
   
  Anoxic Tank Mixer  5 hours x 4 times/day  Mixer  to  operate  intermittently  base  on 
  timer setting with cumulative of 20 running 
  hours  per  day.  Running  hours  can  be 
  divided evenly within 24 hours with 1 hour 
  rest interval.  
  Aeration Blower  12 hours/day  Air  Blower  to  operate  intermittently  base 
  on  timer  setting  with  cumulative  of  24 
  Not tally with timer running  hours  per  day.  The  relief  valve 
  setings, 24 (continuous) (fix/come  together  with  Air  Blower)
  or 12 hours / day running controls the pressure of the blowing out. 
(Intermittent)
 
c)  PH  reading  (AT‐002)  at  Parshall  Flume  is  provided  with  alarm  at  DCS  for  high  and  low 
reading. The following is proposed set point for pH alarm at effluent. Once low reading 
is  detected,  Field  Technician  shall  dose  the  Sodium  Hydroxide  (NaOH)  in  Disinfection 
Chamber to reach back neutral pH (7.0). Once high reading is detected, Field Technician 
dose the Sulfuric Acid (H2SO4) in Disinfection Chamber to reach back neutral pH (7.0). 
 
  Effluent pH Alarm Low (H)  5.5 
  Effluent pH Alarm High (L)  9.0 
 
d)  Dissolve  Oxygen  reading  (AT‐003A/B)  at  Equalization  Tank  and  Aeration  Tank  is 
provided  with  alarm  at  DCS  for  Low  (L)  reading  monitoring.  Once  low  reading  is 
detected, Field Technician shall increase speed of blower thru LCP via local automation 
until  Dissolve  Oxygen  reading  back  to  normal.  Once  high  reading  is  detected,  Field 
Technician shall decrease speed of blower thru LCP via local automation until Dissolve 
Oxygen  reading  back  to  normal.  The  following  are  proposed  set‐point  for  Dissolved 
Oxygen alarm at Equalization Tank and Aeration Tank. 
 
Dissolved Oxygen Alarm Low (L), mg/l  1.8 
Dissolved Oxygen Alarm High (H), mg/l  2.2 
 
d)         Mixed  Liquor  Suspended  Solid  (MLSS)  reading  (AT‐004)  at  Aeration  Tank  is  provided 
with  alarm  status  at  DCS  for  high  and  low  reading    monitoring.  Once  high  reading  is 
detected, Field Technician shall increase the retention time of aeration tank within stop 
the Equalization Tank Pump. Once low reading is detected, Field Technician shall fill the 
certain  amount  of  MLSS  from  others  Aeration  Tank.  The  following  are  proposed  set 
point for MLSS alarm at Aeration Tank. 
 
  Aeration Tank MLSS Alarm Low (L), mg/l  2500 
  Aeration Tank MLSS Alarm High (H), mg/l  5000 
 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 16 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

5.0 CONTROL NARRATIVE


The following control narrative will further explain for Sanitary Pit (GH‐983, G2‐984, G2‐983, 
G3‐984, G‐756 & G4‐984) operational mode. 
 
Sewerage level inside every individual Sanitary Pit will detected three (3) level setting L, H & 
HH by Radar Level Transmitter installed at every individual pits. Each Sanitary Pit has two (2) 
pumps A and B in operation based on selector switch selection depending on which one shall 
be in Duty and Standby mode at LCP. 
 
Reference Drawing/Documents: 
a) Instrument Cable Block Diagram – Dwg No: STS‐EXE‐MAW‐981‐INC‐CBB‐0001 
b) Instrument Cause and Effect Matrix – Dwg No: STS‐EXE‐MAW‐981‐INC‐CEM‐0001 
 
5.1  Sanitary Pit (G2‐984, G2‐983, G3‐984, G‐756 & G4‐984) 
 
5.1.1  Auto Mode  
In normal operation, Field Technician shall ensure selection of selector switch located at LCP 
for each Sanitary Pit shall be at auto mode. The Level Transmitter signals from each Sanitary 
Pit  will  be  route  to  DCS  thru  Junction  Box  IJB‐XXX1  to  the  designated  control  building  to 
monitor the sewerage level setting as Analog Input (AI). DCS graphic shall show level setting 
and pump start/stop status for each sanitary pit connected to DCS. 
 
Start/stop pump will shall be control by DCS system based on the level set‐point setting from 
each Sanitary Pit. Duty Pump shall start when the level reach High Level (H) and stop when 
the  level  reach  at  Low  Level  (L).  Standby  Pump  shall  start  when  the  level  reach  High  High 
Level (HH) and stop when the level reach back at Low Level (L).  
 
Below is the Level Transmitter Analog Input (AI) setting for DCS programming: 
j) High High Level (HH) 
In the event of Level Transmitter detect High High Level (HH), it shall indicate High High 
Level (HH) signal status at DCS. At this state, the DCS will give command signal to start 
Standby Pump. Start for Standby Pump and High High Level (HH) indication status shall 
be  indicated  at  DCS  graphic.  Start  and  stop  Indication  light  for  Standby  Pump  shall  be 
provided at LCP. Duty & Standby Pump shall start at the same  time during  this event. 
Standby Pump shall stop when the Sanitary Pit reach Low Level (L) and stop indication 
status shall be indicated at DCS graphic and LCP via indication light.  
 
ii) High Level (H) 
In the  event  of Level Transmitter detect High Level  (H), it shall  indicate High Level (H) 
signal status at DCS. At this state, the DCS will give command signal to start Duty Pump. 
Start  for  Duty  Pump  and  High  Level  (H)  indication  status  shall  be  indicated  at  DCS 
graphic.  Start  and  stop  Indication  light  for  Duty  Pump  shall  be  provided  at  LCP.  Duty 
Pump will be always running even at High High Level (HH). Duty Pump shall stop when 
the Sanitary Pit reach Low Level (L) and stop indication status shall be indicated at DCS 
graphic and LCP via indication light. 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 17 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

iii) Low Level (L) 
In the event of Level Transmitter detect Low Level (L), it shall indicated the Low Level (L) 
signal status at DCS. At this state, the DCS shall give command signal to stop Duty Pump. 
Stop for Duty Pump and Low Level (L) indication status shall be indicated at DCS graphic. 
Stop Indication light for Duty Pump shall be provided at LCP. This action is to protect the 
pump from running dry. 
 
5.1.2  Manual Mode  
In abnormalities, Field Technician shall ensure selection of selector switch located at LCP for 
each Sanitary Pit shall be at manual mode. The purpose of this operation is to test run both 
Duty  &  Standby  Pump  for  maintenance.  Field  Technician  shall  communicate  with  Panel 
Operator during this occasion.

i) Start/Stop 
In  Manual  Mode  operation,  Field  technician  shall  select  the  Start/Stop  for  both  Duty 
and  Standby  Pump  manually  depends  on  pump  availability.  Level  Transmitter  still  can 
detect level setting as in during auto mode. 
 
In  the  event  of  Sanitary  Pit  in  High  Level  (H)  or  High  High  Level  (HH),  Field  Technician 
shall push start button for Duty or Standby pump at LCP. At this state, the LCP shall give 
signal to start Duty & Standby Pump. Indication light for start shall be light up at LCP. 
Panel Operator shall be able to receive start signal indication status at DCS. 
 
In the event of Sanitary Pit in Low Level (L) or High Level (H), when level reach Low Level 
(L)  Field  Technician  shall  push  stop  button  for  Duty  Pump  and  Standby  Pump.  At  this 
state, the LCP will give signal command to start Duty & Standby Pump. Indication light 
for  stop  shall  be  light  up  at  LCP.  Panel  Operator  shall  be  able  to  receive  stop  signal 
indication status at DCS. 

5.2  NPS (GH‐983) Admin Building‐Non Process Area
 
5.2.1  Auto Mode  
In normal operation, Field Technician shall ensure selection of selector switch located at LCP 
shall be at auto mode. The Level Transmitter from each pit shall be route to LCP to monitor 
the sewerage level setting.  
 
Start/stop pump shall be control by local automation at LCP based on the level setting. Duty 
pump shall start when the level reach High Level (H) and stop when the level reach Low Level 
(L). Standby pump shall start when the level reach High High Level (HH) and stop when the 
level reach Low Level (L).  
 
 
 
 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 18 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

Below is the Level Transmitter setting for local automation: 
i) High High Level (HH) 
In the event of Level Transmitter detect High High Level (HH), it shall indicate the High 
High level (HH) indication at LCP. At this state, the LCP will give command signal to start 
Standby  Pump.  Start  for  Standby  Pump  and  High  High  Level  (HH)  indication  shall  be 
indicated  at  LCP  via  indication  light.  Duty  &  Standby  Pump  shall  be  start  at  the  same 
time during this event. Standby pump shall be stop when the Sanitary Pump reach the 
Low Level (L) and stop indication shall be indicated at LCP via indication light.  
 
ii) High Level (H) 
In the event of Level Transmitter detect High High Level (HH), it shall indicated the High 
Level (H) indication at LCP. At this state, the LCP shall give command signal to start Duty 
Pump.  Start  for  Duty  Pump  and  High  Level  (H)  indication  shall  be  indicated  at  LCP  via 
indication  light.  Duty  Pump  shall  always  running  even  at  High  High  Level  (HH).  Duty 
pump shall stop when the Sanitary Pit reach Low Level (L) and stop indication shall be 
indicate at LCP via indication light. 
 
iii) Low Level (L) 
In  the  event  of  Level  Transmitter  detect  Low  Level  (L),  it  shall  indicate  Low  Level  (L) 
indication  status  at  LCP.  At  this  state,  the  LCP  shall give  command  signal  to  stop  Duty 
Pump.  Stop  for  Duty  Pump  and  Low  Level  (L)  indication  shall  be  indicate  at  LCP  via 
indication light. This action is to protect the pump from running dry. 
 
5.2.2  Manual Mode  
In abnormalities, Field Technician shall ensure selection of selector switch located at LCP for 
each Sanitary Pit shall be at manual mode. The purpose of this operation is to test run both 
Duty  &  Standby  Pump  for  maintenance.  Field  Technician  shall  communicate  with  Panel 
Operator during this occasion. 
 
i) Start/Stop 
In Manual Mode operation, Field technician shall select the Start/Stop either Duty and 
Standby  Pump  manually  depends  on  the  current  situation.  Level  Transmitter  still  can 
detect level setting as in during auto mode. 
 
In  the  event  of  Sanitary  Pit  in  High  Level  (H)  or  High  High  Level  (HH).  Field  Technician 
shall  push  start  button  for  either  Duty  or  Standby  Pump  at  LCP.  At  this  state,  the  LCP 
shall give signal to start Duty or Standby Pump. Indication light for start and High Level 
(H) & High High Level (HH) shall be indicated at LCP.  
 
In the event of Sanitary Pit in Low Level (L) or High Level (H), when level reach Low Level 
(L)  Field  Technician  shall  push  stop  button  for  Duty  Pump  and  Standby  Pump.  At  this 
state,  the  LCP  shall  give  signal  to  stop  Duty  &  Standby  Pump.  Indication  light  for  stop 
and Low Level (L) shall be indicated at LCP.  
 

Typ. Comment
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 19 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

5.3  Sewerage Treatment System (Sts)
 
5.3.1  Auto Mode  
In  normal  operation,  Field  Technician/Chargeman  shall  ensure  selection  of  selector  switch 
located at LCP in Blower House‐Electrical Room shall be at auto mode. The Level Transmitter 
from STS will be route to LCP to monitor the sewerage level setting.  
 
Start/stop pump shall be control by local automation at LCP in Blower House‐Electrical Room 
based  on  the  level  setting.  Duty  pump  shall  start  when  the  level  reach  High  Level  (H)  and 
stop when the level reach Low Level (L) & Low Low Level (LL). Standby pump shall start when 
the level reach High High Level (HH) and stop when the level reach Low Level (L).  
 
Below is the Level Transmitter setting for local automation: 
i) High High Level (HH) 
In the event of Level Transmitter detect High High Level (HH), it shall indicate High High 
Level  (HH)  indication  at  LCP  via  indication  light.  At  this  state,  the  LCP  shall  give 
command signal to start Standby Pump. Start for Standby Pump indication status shall 
be  indicated  at  DCS  graphic.  Run  and  stop  Indication  light  for  Standby  Pump  shall  be 
provided at LCP. Duty & Standby Pump shall running at the same time during this event. 
Standby pump shall stop when the STS reach the Low Level (L) and stop indication signal 
shall indicated at DCS graphic and LCP via indication light.  
 
ii) High Level (H) 
In the event of Level Transmitter detect High Level (H), it shall indicated the High Level 
(H) indication at LCP via indication light. At this state, the LCP shall give command signal 
to  start  Duty  Pump.  Start  for  Duty  Pump  indication  status  shall  be  indicated  at  DCS 
graphic.  Start  and  stop  Indication  light  for  Duty  Pump  shall  be  provided  at  LCP.  Duty 
Pump shall always running even at High High Level (HH). Duty pump shall stop when the 
STS reach the Low Level (L) and stop indication shall be indicated at DCS graphic and LCP 
via indication light. 
 
iii) Low Level (L) 
In the event of Level Transmitter detect Low Level (L), it shall indicate the Low Level (L) 
indication  status  at  LCP.  At  this  state,  the  LCP  shall give  command  signal  to  stop  Duty 
Pump  and  Standby  Pump.  Stop  for  both  pump  indication  shall  be  indicated  at  DCS 
graphic and LCP via indication light. This action is to protect the pump from running dry. 
 
iv) Low Low Level (LL) 
In the event of float switch detect Low Low Level (LL), it shall indicate the Low Low Level 
(LL)  indication  status  at  LCP  via  indication  light.  At  this  state,  the  LCP  shall  give 
command  signal  to  stop  Duty  Pump.  Stop  for  Duty  Pump  and  Low  Low  Level  (LL) 
indication shall be indicate at LCP via indication light. This action act as safeguarding for 
Duty Pump when it is still running below Low Level (L). 
 
Doc No:
STS-EXE-MAW-PRO-RPT-
0001

Revision: 0

PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND


COMMISSIONING OF SANITARY TREATMENT SYSTEM (STS) MODIFICATION Page: 20 of 20
PROJECT AT GAS PROCESSING KERTIH, PETRONAS GAS BERHAD

5.3.2  Manual Mode  
In  abnormalities,  Field  Technician/Chargeman  shall  ensure  selection  of  selector  switch 
located at LCP for STS shall be at manual mode. The purpose of this operation is to test run 
both  Duty  &  Standby  Pump  for  maintenance.  Field  Technician/Chargeman  shall 
communicate with Panel Operator during this occasion. 
 
i) Start/Stop 
In Manual Mode operation, Field technician/Chargeman shall select the start or stop for 
both Duty and Standby Pump manually depends on pump availability. Level Transmitter 
still can detect level setting as in during auto mode. 
 
In  the  event  of  STS  in  High  Level  (H)  or  High  High  Level  (HH).  Field  Technician/ 
Chargemen shall push start button for Duty and Standby Pump at LCP. At this state, the 
LCP  shall  give  signal  to  start  Duty  &  Standby  Pump.  Indication  light  for  start  and  High 
Level (H) & High High Level (HH) shall be indicated at LCP.  
 
In the event of STS in Low Level (L) or High Level (H) when level reach Low Level (L) Field 
Technician/Chargeman  shall  push  stop  button  for  Duty  Pump  and  push  stop  button 
when level reach High Level (H) for Standby Pump. At this state, the LCP will give signal 
to  start  Duty  &  Standby  Pump.  Indication  light  for  stop  and  Low  Level  (L)  shall  be 
indicated at LCP.  
 
In the event of STS in Low Low Level (LL), the LCP shall give signal to stop Duty Pump 
automatically  as  in  auto  mode  operation.  Indication  light  for  stop  and  Low  Low  Level 
(LL) shall be indicated at LCP. 
 
5.3.3  Emergency Stop  
 
If  there  is  any  emergency  situation  at  site,  Field  Technician  shall  push  the  emergency  stop 
button  and  it  shall  triggered  the  signal  inside  the  LCP.  It  shall  give  signal  to  stop  Duty  & 
Standby  Pump.  Stop  indication  shall  be  indicated  at  LCP  via  indication  light  and  Panel 
Operator shall be able to receive stop signal indication status at DCS. 
 

You might also like