Pile Cap Design Page 1 of 6

Print Calculation Sheet

PILE CAP DESIGN

US Code (ACI 318-11) - Metric

Pile Cap 130

PILE ARRANGEMENT
Footing Geometrical Data

Column Dimensions
Column Shape : Rectangular

Column Length - X (Pl) : 0.525 m

Column Width - Z (Pw) : 0.525 m

Pedestal

Include Pedestal : No
Pedestal Shape : N/A

Pile Cap Geometrical Data


Pile Cap Length PCL : 1.000 m
Pile Cap Width PCW : 2.200 m
Initial Pile Cap Thickness tI : 0.700 m

Pile Geometrical Data


Pile spacing Ps : 1.200 m
Pile Edge distance Pe : 0.500 m
Pile Diameter Pd : 0.400 m

Pile Capacities
Axial Capacity PP : 600.000 kN
Lateral Capacity PL : 100.000 kN
Uplift Capacity PU : 300.000 kN

Material Properties
Concrete f'c : 28000.005 kN/m^2
Reinforcement fy : 414000.070 kN/m^2

Concrete Cover
Bottom Clear Cover CCB : 0.075 m
Side Clear Cover CCS : 0.075 m
Pile in Pile Cap PCP : 0.050 m

Loading applied at top of cap

For the loads shown in this table, the sign convention is the same as that for JOINT LOADS in STAAD.Pro when global Y is the vertical
axis.

Service Level Combinations

Load Self
Load Case
Combination Load Combination Title Weight
Multiplier
Number Factor
54 GENERATED NSCP 2015 DRIFT CHECK COMBO 1 1.00 1.00
55 GENERATED NSCP 2015 DRIFT CHECK COMBO 2 1.00 1.00
56 GENERATED NSCP 2015 DRIFT CHECK COMBO 3 1.00 1.00
57 GENERATED NSCP 2015 DRIFT CHECK COMBO 4 1.00 1.00

file:///D:/CJNA/FINAL%20OUTPUTS/Construction%20of%20Barracks,%20NSJA/STA... 21/04/2021
Pile Cap Design Page 2 of 6

58 GENERATED NSCP 2015 DRIFT CHECK COMBO 5 1.00 1.00


59 GENERATED NSCP 2015 DRIFT CHECK COMBO 6 1.00 1.00
60 GENERATED NSCP 2015 DRIFT CHECK COMBO 7 1.00 1.00
61 GENERATED NSCP 2015 DRIFT CHECK COMBO 8 1.00 1.00
62 GENERATED NSCP 2015 DRIFT CHECK COMBO 9 1.00 1.00
63 GENERATED NSCP 2015 DRIFT CHECK COMBO 10 1.00 1.00
64 GENERATED NSCP 2015 DRIFT CHECK COMBO 11 1.00 1.00
65 GENERATED NSCP 2015 DRIFT CHECK COMBO 12 1.00 1.00
66 GENERATED NSCP 2015 DRIFT CHECK COMBO 13 1.00 1.00
67 GENERATED NSCP 2015 DRIFT CHECK COMBO 14 1.00 1.00
68 GENERATED NSCP 2015 DRIFT CHECK COMBO 15 1.00 1.00
69 GENERATED NSCP 2015 DRIFT CHECK COMBO 16 1.00 1.00
70 GENERATED NSCP 2015 DRIFT CHECK COMBO 17 1.00 1.00
71 GENERATED NSCP 2015 DRIFT CHECK COMBO 18 1.00 1.00
72 GENERATED NSCP 2015 DRIFT CHECK COMBO 19 1.00 1.00
73 GENERATED NSCP 2015 DRIFT CHECK COMBO 20 1.00 1.00
74 GENERATED NSCP 2015 DRIFT CHECK COMBO 21 1.00 1.00
75 GENERATED NSCP 2015 DRIFT CHECK COMBO 22 1.00 1.00
76 GENERATED NSCP 2015 DRIFT CHECK COMBO 23 1.00 1.00
77 GENERATED NSCP 2015 DRIFT CHECK COMBO 24 1.00 1.00
78 GENERATED NSCP 2015 DRIFT CHECK COMBO 25 1.00 1.00
79 GENERATED NSCP 2015 DRIFT CHECK COMBO 26 1.00 1.00
80 GENERATED NSCP 2015 DRIFT CHECK COMBO 27 1.00 1.00
81 GENERATED NSCP 2015 DRIFT CHECK COMBO 28 1.00 1.00

Strength Level Combinations

Load Self
Load Case
Combination Load Combination Title Weight
Multiplier
Number Factor
15 GENERATED NSCP 2015 USD/LRFD + EV 1 1.00 1.00
16 GENERATED NSCP 2015 USD/LRFD + EV 2 1.00 1.00
17 GENERATED NSCP 2015 USD/LRFD + EV 3 1.00 1.00
18 GENERATED NSCP 2015 USD/LRFD + EV 4 1.00 1.00
19 GENERATED NSCP 2015 USD/LRFD + EV 5 1.00 1.00
20 GENERATED NSCP 2015 USD/LRFD + EV 6 1.00 1.00
21 GENERATED NSCP 2015 USD/LRFD + EV 7 1.00 1.00
22 GENERATED NSCP 2015 USD/LRFD + EV 8 1.00 1.00
23 GENERATED NSCP 2015 USD/LRFD + EV 9 1.00 1.00
24 GENERATED NSCP 2015 USD/LRFD + EV 10 1.00 1.00
25 GENERATED NSCP 2015 USD/LRFD + EV 11 1.00 1.00
26 GENERATED NSCP 2015 USD/LRFD + EV 12 1.00 1.00
27 GENERATED NSCP 2015 USD/LRFD + EV 13 1.00 1.00
28 GENERATED NSCP 2015 USD/LRFD + EV 14 1.00 1.00
29 GENERATED NSCP 2015 USD/LRFD + EV 15 1.00 1.00
30 GENERATED NSCP 2015 USD/LRFD + EV 16 1.00 1.00
31 GENERATED NSCP 2015 USD/LRFD + EV 17 1.00 1.00
32 GENERATED NSCP 2015 USD/LRFD + EV 18 1.00 1.00
33 GENERATED NSCP 2015 USD/LRFD + EV 19 1.00 1.00
34 GENERATED NSCP 2015 USD/LRFD + EV 20 1.00 1.00
35 GENERATED NSCP 2015 USD/LRFD + EV 21 1.00 1.00
36 GENERATED NSCP 2015 USD/LRFD + EV 22 1.00 1.00
37 GENERATED NSCP 2015 USD/LRFD + EV 23 1.00 1.00
38 GENERATED NSCP 2015 USD/LRFD + EV 24 1.00 1.00
39 GENERATED NSCP 2015 USD/LRFD + EV 25 1.00 1.00
40 GENERATED NSCP 2015 USD/LRFD + EV 26 1.00 1.00
41 GENERATED NSCP 2015 USD/LRFD + EV 27 1.00 1.00
42 GENERATED NSCP 2015 USD/LRFD + EV 28 1.00 1.00
43 GENERATED NSCP 2015 USD/LRFD + EV 29 1.00 1.00
44 GENERATED NSCP 2015 USD/LRFD + EV 30 1.00 1.00
45 GENERATED NSCP 2015 USD/LRFD + EV 31 1.00 1.00
46 GENERATED NSCP 2015 USD/LRFD + EV 32 1.00 1.00
47 GENERATED NSCP 2015 USD/LRFD + EV 33 1.00 1.00
48 GENERATED NSCP 2015 USD/LRFD + EV 34 1.00 1.00
49 GENERATED NSCP 2015 USD/LRFD + EV 35 1.00 1.00
50 GENERATED NSCP 2015 USD/LRFD + EV 36 1.00 1.00
51 GENERATED NSCP 2015 USD/LRFD + EV 37 1.00 1.00

file:///D:/CJNA/FINAL%20OUTPUTS/Construction%20of%20Barracks,%20NSJA/STA... 21/04/2021
Pile Cap Design Page 3 of 6

52 GENERATED NSCP 2015 USD/LRFD + EV 38 1.00 1.00


53 GENERATED NSCP 2015 USD/LRFD + EV 39 1.00 1.00

Fy
(kN)
Load Fx Fz Mx Mz
Downwards is
Case (kN) (kN) (kNm) (kNm)
negative Upwards
is positive
15 -23.808 -431.426 -41.530 -12.553 1.176
16 -21.371 -407.444 -40.661 -18.132 8.383
17 -20.708 -381.559 -37.180 -13.064 3.313
18 -17.209 -363.968 -35.191 -9.635 -9.329
19 -23.251 -375.565 -36.013 -11.896 10.625
20 -20.412 -349.802 -17.266 38.657 1.045
21 -20.409 -389.118 -52.946 -58.260 1.002
22 -14.314 -369.908 -36.366 -10.814 -17.362
23 -26.397 -393.103 -38.011 -15.335 22.546
24 -20.719 -341.575 -0.516 85.770 3.386
25 -20.713 -420.208 -71.877 -108.063 3.300
26 -8.911 -265.694 -25.884 -5.820 -19.918
27 -20.994 -288.889 -27.530 -10.342 19.990
28 -15.316 -237.361 9.966 90.764 0.829
29 -15.310 -315.994 -61.395 -103.069 0.744
30 4.040 -444.711 -45.634 -0.345 -124.367
31 5.244 -448.888 -51.386 -17.774 -128.926
32 -63.495 -619.310 -52.341 -17.230 136.383
33 -62.291 -623.487 -58.094 -34.660 131.824
34 -31.177 -447.536 11.587 175.394 11.496
35 -27.192 -461.872 -7.568 117.290 -3.659
36 -31.059 -606.326 -96.159 -152.295 11.116
37 -27.074 -620.662 -115.314 -210.399 -4.040
38 9.443 -340.497 -35.152 4.649 -126.924
39 10.647 -344.674 -40.905 -12.781 -131.482
40 -58.092 -515.096 -41.860 -12.237 133.826
41 -56.888 -519.273 -47.612 -29.666 129.268
42 -25.774 -343.322 22.068 180.388 8.940
43 -21.789 -357.658 2.913 122.284 -6.216
44 -25.656 -502.112 -85.678 -147.301 8.560
45 -21.671 -516.448 -104.833 -205.405 -6.596
46 26.278 -35.417 -5.784 13.526 -127.756
47 27.482 -39.595 -11.537 -3.904 -132.314
48 -41.257 -210.016 -12.492 -3.360 132.995
49 -40.052 -214.193 -18.244 -20.789 128.436
50 -8.939 -38.243 51.436 189.265 8.108
51 -4.954 -52.578 32.281 131.161 -7.048
52 -8.820 -197.032 -56.310 -138.424 7.728
53 -4.835 -211.368 -75.465 -196.528 -7.428
54 -17.209 -363.968 -35.191 -9.635 -9.329
55 -23.251 -375.565 -36.013 -11.896 10.625
56 -20.412 -349.802 -17.266 38.657 1.045
57 -20.409 -389.118 -52.946 -58.260 1.002
58 -14.314 -369.908 -36.366 -10.814 -17.362
59 -26.397 -393.103 -38.011 -15.335 22.546
60 -20.719 -341.575 -0.516 85.770 3.386
61 -20.713 -420.208 -71.877 -108.063 3.300
62 12.457 -292.171 -30.950 4.094 -124.783
63 13.662 -296.349 -36.702 -13.336 -129.342
64 -55.077 -466.770 -37.657 -12.792 135.967
65 -53.873 -470.947 -43.410 -30.221 131.409
66 -22.760 -294.997 26.271 179.832 11.081
67 -18.775 -309.332 7.116 121.729 -4.075
68 -22.641 -453.786 -81.475 -147.856 10.700
69 -18.656 -468.122 -100.630 -205.960 -4.455
70 -8.911 -265.694 -25.884 -5.820 -19.918
71 -20.994 -288.889 -27.530 -10.342 19.990
72 -15.316 -237.361 9.966 90.764 0.829
73 -15.310 -315.994 -61.395 -103.069 0.744
74 17.860 -187.957 -20.468 9.088 -127.340
75 19.065 -192.134 -26.221 -8.342 -131.898
76 -49.674 -362.556 -27.176 -7.798 133.410
77 -48.470 -366.733 -32.928 -25.228 128.852
78 -17.357 -190.782 36.752 184.826 8.524
79 -13.372 -205.118 17.597 126.722 -6.632
80 -17.238 -349.572 -70.994 -142.862 8.144
81 -13.253 -363.908 -90.149 -200.966 -7.012

Two Pile Combination cannot resist transverse moment,hence for shear,punching,BM calculations transverse moment is ignored. So for
pile cap parallel to X, Mx=0,Fz=0. And for pile cap parallel to Z, Mz=0,Fx=0.

file:///D:/CJNA/FINAL%20OUTPUTS/Construction%20of%20Barracks,%20NSJA/STA... 21/04/2021
Pile Cap Design Page 4 of 6

PILE CAP DESIGN CALCULATION


Self Weight Calculation
Self Weight : 36.959 kN

Pedestal Weight : 0.000 kN

Soil Weight : 59.398 kN

Extra weight for Surcharge : 0.000 kN

Buoyancy Reduction : 0.000 kN

Maximum Pile Reactions for service load cases

X Coord. Z Coord. Reaction Allowable


Reaction Type Load case No. Pile No.
(m) (m) (kN) (kN)
Axial 69 1 0.000 -0.600 -512.577 600.000
Lateral 69 1 0.000 -0.600 51.172 100.000
Uplift 78 1 0.000 -0.600 31.894 300.000

Maximum Pile Reactions for Ultimate Load Cases

Governing Load Case : 33

This is the load case for which the pilecap depth required is the maximum. If there are
multiple load cases for which the same maximum depth is required, then the load case with
the highest axial load (absolute value) is considered as the critical load case.

Total number of piles N : 2

_ Arrangement Reaction
X Z Axial Lateral Uplift
Pile No.
(m) (m) (kN) (kN) (kN)
1 0.000 -0.600 -422.694 42.588 0.000
2 0.000 0.600 -297.150 42.588 0.000

Reinforcement Calculation for Pile Cap

Maximum bar size allowed : # 16


Bending Moment At Critical Section : -225.413 kNm (Along Length)
Pile Cap Thickness t : 0.700 m
Selected bar size : # 16
Selected bar spacing : 143.33 mm

Pile Cap Thickness Check

Critical Load Case : 33

Check for One-way Shear (Shear Line Parallel to Width)

Critical Load Case : 53

Shear Force
Pile No.
x1-x1(kN)

1 0.000

2 0.000

Design Shear for One-Way Action (Shear Line = SOL = 0.000 kN


Parallel to Width)

file:///D:/CJNA/FINAL%20OUTPUTS/Construction%20of%20Barracks,%20NSJA/STA... 21/04/2021
Pile Cap Design Page 5 of 6

VC = = = 1065.229 kN

SOL <= 0.75 VC. hence, safe

Calculation of Maximum Bar Size

Selected maximum bar size = # 16


Bar diameter corresponding to max bar size (db) = = 16.000 mm

Required development length for bars = = 0.596 m

Selection of Reinforcement

Along Length

Critical Load Case : 37

Governing moment (Mtl) = -225.413 kNm

dBeta =
= 0.650

Maximum Reinforcement Ratio (Rmax) = = 0.0166

Minimum Reinforcement Ratio (Rmin) = 0.0020


Calculated Reinforcement Ratio (R) = 0.0022
Rmin<= R <= Rmax, R is accepted.

Minimum spacing allowed (Smin) = 1.5 x db = 54 mm

Selected Bar Size = #16

Provided Number of Bars = 6

Provided spacing (S) = 143.33 mm

Smin<= S <= 18 inch and selected bar size < selected maximum bar size. The reinforcement is accepted.

Along Width

For two Pile arrangement, no moment acts in transverse direction. So, minimum reinforcement is
sufficient.

Maximum Reinforcement Ratio (Rmax) = = 0.0166

Minimum Reinforcement Ratio (Rmin) = 0.0020

Calculated Reinforcement Ratio (R) = 0.0022

Rmin<= R <= Rmax, R is accepted

Minimum spacing allowed (Smin) = 1.5 x db = 54 mm


Selected Bar Size = #16
Provided Number of Bars = 7
Provided spacing (S) = 139.00 mm
Smin<= S <= 18 inch and selected bar size < selected maximum bar size. The reinforcement is accepted.

file:///D:/CJNA/FINAL%20OUTPUTS/Construction%20of%20Barracks,%20NSJA/STA... 21/04/2021
Pile Cap Design Page 6 of 6

Selection of Top Reinforcement

Top reinforcement is provided same as bottom reinforcement

Material Take Off


Footing Reinforcement

Direction Size Number Total Length (m) Weight (kg)

Along X on Bottom 16 mm 6 5.10 8.05

Along Z on Bottom 16 mm 7 14.35 22.66

Along X on Top N/A N/A N/A N/A

Along Z on Top N/A N/A N/A N/A

Total Reinforcement Weight : 30.71 kg

Concrete

3
- Length (m) Width (m) Thickness (m) Volume (m )

Footing 1.00 2.20 0.70 1.54

Total Concrete Volume : 1.54 m3

Formwork

Footing : 4.48 m2

Pedestal : 0.00 m2

Total : 4.48 m2

Soil Excavation

Pit Depth : 2.20 m


Pit Slope (a : b) : 1 : 1 (Assumed)
Side Distance, s : 0 (Assumed)
Excavation Volume : 34.24 m3

Backfill Volume : 32.70 m3

file:///D:/CJNA/FINAL%20OUTPUTS/Construction%20of%20Barracks,%20NSJA/STA... 21/04/2021