Computation of Liquidated Damages as of March 16, 2021

Name of Project :Rehabilitation and Improvement of Balete Pass National


Shrine
Location :Sta. Fe Nueva Vizcaya
Original ABC (P) : 3,360,154.63
Revised ABC (P) :

1) Original Contract Time (calendar days) 120 CALENDAR DAYS

2) Date of Effectivity of Contract JUNE 03, 2020

3) Original Expiry Date SEPTEMBER 30, 2020

4) Time Extension Allowed (calendar days) 43 CALENDAR DAYS

5) Revised Expiry Date after Allowed NOVEMBER 12, 2020


Extension
6) Revised Contract Time (calendar days) 163 CALENDAR DAYS

7) Total Calendar Days Elapsed to-date 287 CALENDAR DAYS

8) Total Calendar Days of Delay 124 CALENDAR DAYS

9) Percent Accomplishment As of November 62.45%


12, 2020
11) Percent Remaining after Contract Expiration 37.55%

12) Liquidated Damages (1/10 of 1% of the 1,261.74 x 124 days = 156,455.52


percent remaining after contract termination per
day of delay)
13) Total Liquidated Damages Php 156,455.52

Prepared by: Certified by:

Engr. Aldrin L. Malabad Engr. Valerico C. Lim, MNSA


BFMS, Project Engineer Chief, GSSMD