Professional Documents
Culture Documents
I00-211-EM620-30014 Rev.A - Preservation Procedure
I00-211-EM620-30014 Rev.A - Preservation Procedure
1. General
1-1 Purpose
1-2 Scope
1-3 Packing condition prior to delivery
1-4 Material control
2. Receipt of cargoes
3. Inspection on receipt
3-1 Inspection without unpacking
3-2 Inspection with unpacking
3-3 Records of inspection on receipt
4. Handling at site
6. Warehouse management
7. Other works
7-1 Handling of spare parts and special tools
7-2 Long term storage
Appendix
A. Handling procedure
B. Unpacking procedure
C. Storage procedure
C-1 General
C-2 Pile of Cargoes
C-3 Details of storage procedure
D. Repair and repack procedure
1
1. General
1-1 Purpose
This specification describes generally recommended method, procedure, and/or guidance for
inspection on receipt, handling at site and storage of the shipped package to protect all
equipments and materials to be used at the construction site from any damage and impairment
caused during storage.
1-2 Scope
This specification applies to the all equipments and materials supplied by Fuji Electric Co., Ltd.
for INDONESIA ISM POWER PLANT.
2. Receipt of cargoes
Material controller should confirm the arrival date, contents of cargoes and quantity of all
equipments and materials based on the Delivery Notice and Packing List for preparation.
Material controller should instruct necessary information to all workers with regard to the contents
of cargo, unloading place, piling method and preparation of temporary materials (dunnage sheet
wire, etc.), as required.
If necessary, heavy machinery for handling should be arranged (refer to Appendix A).
3. Inspection on receipt
3-1 Inspection without unpacking
Received packages should be checked against Delivery Notice and Packing List for the
quantity of packages (or equipments and materials) and visually checked for any damage
wounded in transit.
Packages should be stored at proper place on site.
2
3-2 Inspection with unpacking
Inspection for the quantity of equipments and materials and visual inspection for any damage
should be conducted with unpacking the packages. This inspection with unpacking should be
conducted immediately after reception of cargoes in the following case. In other case, it should
be conducted before the installation works so as not to affect installation sequence.
(1) Any damage was found by the visual inspection (refer to Item No. 3-1 Inspection without
unpacking)
(2) For equipments and materials necessary to be stored in specific condition, such as air
conditioned indoor storage, etc. (refer to Item No.5 Storage and protection)
(3) For equipments and materials should be managed in specific procedure, such as checking
sealing gas pressure, periodical rotation and energization, etc. during storage.
4. Handling at site
Material controller should handle equipments and materials complying with the caution mark on
the package (refer to Table A in Appendix A) and prescription from Fuji and supplier.
Care should be taken for the intensity of equipments and materials, necessary space for handling
and surrounding situation. Curing of necessary portion should be conducted to prevent all
equipments and materials from any damage.
If any damage or missing of equipments and materials is caused by handling, material controller
should report them to Fuji head office. (Reporting procedure should be referred to Item No. 3-3.
Records of inspection on receipt.)
Erection contractor has responsible for any damage caused by their work when handling.
If necessary, heavy machinery for handling should be arranged (refer to Appendix A).
3
5. Storage and protection
Material controller should store and protect equipments and materials complying with the caution
mark on the package and prescription from Fuji and supplier.
Care should be taken for the intensity of equipments and materials, necessary space for storage
and surrounding situation. Curing of necessary portion should be conducted to prevent all
equipments and materials from any damage.
Erection contractor has responsible for any damage or missing caused by their work during
storage period.
Especially, electrical products, metering equipments and precisely machined mechanical products
should be stored by strictly keeping away from humidity and dusts.
4
(4) Specific place storage:
If any damage was found by the inspection in both cases, material controller should have
pictures and records of the damage and report them immediately to Fuji head office.
Erection contractor has responsible for any damage caused by their work during installation.
6. Warehouse management
Material controller should make “Warehouse Inventory” based on the Delivery Notice and Packing
List to manage the equipments and materials in the warehouse.
Material controller should record every entering and dispatching from warehouse using this
“Warehouse Inventory”.
7. Other works
7-1 Handling of spare parts and special tools
Cargoes of spare parts and special tools should not be unpacked without instruction by Fuji’s
Turbine TFA or Generator TFA. After the instruction, material controller and Fuji’s TFA should
5
unpack and check quantity.
Prior to handover to the customer, contractor should store spare parts and special tools.
Erection contractor has responsible for any damage or missing caused by their work during
storage period.
After the storage period, material controller should hand over them to the customer complying
with “Spare parts list” and “Special tool list”.
If necessary, material controller should borrow them from customer with clearance of purpose
and preserve the record on the “Warehouse Inventory”. After usage, borrowed items should be
returned immediately to the customer.
Management of “Warehouse Inventory” should be referred to 6.Warehouse management.
6
Appendix
A. Handling procedure
Procedure of heavy machinery for handling
(1) Use of overhead traveling crane (truck crane)
a) Arrange a truck crane in a suitable plan and fix the outrigger.
b) Check for the presence of obstacles in the operating area of the crane.
c) The crane should not be operated by the judgment of the operator alone.
The operator must follow the signs from supervisor.
d) Do not lift any cargo which exceeds the allowable weight limit of the crane.
In both cases, care should be taken to the pictorial mark on cargos.(refer to Table A)
All workmen cargoes should comply with these pictorial marks when handling cargoes.
7
Pictorial mark Indication Note
This mark stands for the center of gravity. Be
CENTER OF BALANCE sure to set the crane hook right on this mark.
8
B. Unpacking procedure
(1) Removing the top
a) First, remove the top boarding and check whether the beam, beam retainer and other
internal bracing members are in order.
(Note) Water-proof paper is furnished between the top boarding and the beams;
therefore, remove it together with the top boarding.
b) Next, remove the beams and the beam retainer.
9
Upper layer Water-proof paper
Under layer top sheathing Double layer
top sheathing
sheathed top
Joist stringer
Top joist
Bridging
End panel
Joint support
Upper frame
member
Side panel
Under frame
member
Auxiliary Header
Diagonal strut
Strut
Rubbing
strip
skid
Non-load bearing
floor member
Middle skid load bearing
floor member
End panel
Side panel
10
C. Storage procedure
C-1 General
Dunnages should be used beneath the cargo at the setting position ±200 mm or less from the
lifting mark. When the cargo is long, dunnages should be used in the middle of the cargo, as
shown in Fig. C1.
Product
supporting
point
Base hoard
Dunnage
11
Upper cargo
Dunnage for
Lower cargoes
> > > >
・Ambient temperature should be kept between 10 and 40 deg C (50 and 104 deg F)
・Ambient humidity should be adjusted low enough to prevent condensation.
・Vacuum packing should be kept. (Do not unpack the package of equipment)
・The packed equipment should be stored away from any wind or moisture.
・The packed equipment should be stored away from direct sunlight.
・The packed equipment should be protected against vermin such as rats, mice, termites,
insects and etc.
12
(2) Indoor storage
After cleaning, the cargoes be stored indoors under the conditions below untill their
installation. The performance of these products and materials should not be impaired by
entry of water or dust.
・The packed equipment should be stored away from any wind or moisture.
・The packed equipment should be stored away from direct sunlight.
・The packed equipment should be protected against vermin such as rats, mice, termites,
insects and etc.
・Storage area should be flat, dry place and free from salt water and dust.
・Storage area should be leveled and graveled.
・Cargoes should be stored at a proper height from the level of the ground, using dunnages to
prevent damage due to entry of rain water.
・Water proof sheet (plastic protection sheet) should be used for protection against rain, dust,
etc. Care should be taken not to tear the sheet by the corners or projections of products.
・Covered cargoes should be bound with rope in order to protect the products from being
exposed.
・The proper ventilation should be kept in order to prevent any sweating on equipments
・The packed equipment should be stored away from rain and/or water infiltration. If water
gathered, it should be removed
13
Cover
(Plastic protection sheet)
Rope
Package
14
Table C. Storage Area for Equipments
For storage area, characters such as “AA”, “BA”, etc. indicate acceptable storage condition for each
of equipment.
First character is for package before unpacking
Second character is for package after unpacking
A: Indoor without air-conditioner, power supply is required for some electrical panel’s space heater
B: Outdoor (but countermeasure from water, sunshine, etc. should be taken.)
C: Indoor with air-conditioner
D: Specific Place (complying with the instruction of each material)
X: Long term storage is prohibited (Only applied for unpacked thermal Insulation.)
15
Lube Oil Cooler BA
Accumulator Stand BA
Miscellaneous (1),(2) BA
Main Stop Valve BA
Main Control Valve Stand (1),(2) BA
IP Combined Valve Casing (R),(L) BA
IP Combined Valve Casing Support BA
Reheat Stop Valve (RSV L,R) BA
Intercept Valve (ICV L,R) BA
Main Stop Valve Actuator (MSV) BA
Main Control Valve Actuator (MCV) BA
Reheat Stop Valve Actuator (RSV) BA
Intercept Valve Actuator (ICV) BA
Main Steam Strainer BA
Reheat Steam Strainer (L,R) BA
Reheat Steam Strainer Casing (L,R) BA
Cold Reheat Check Valve BA
Gland Steam Control Valve BA
Gland Steam Condenser BA
Gland Steam Exhaust Fan BA
Spare Parts for Turbine BA
2. Generator
Stator Complete AA
Rotor Complete AA
Bearing Stand, Metal, Packing Ring AA
Air Shield, FAN Guide AA
Air Duct AA
Sub Sole Plate BA
Oil Piping BA
Air Coolers AA
Bed Plate and Foundation Bolt BA
Exciter Stator and Cover AA
CT Cover AA
Special Tool (Unit-1,Unit-2) AA
Spare Parts (Unit-2, Unit-2) AA
16
Miscellaneous Parts BA
3. Electrical Equipment
Generator Neutral Grounding Cubicle AC
DC Motor Starting Panel AC
Generator Protection Panel -1, -2 AC
Panel Insert for Synchronizing (Meter) AC
Panel Insert for Synchronizing (Operation) AC
Turbine Protection Panel AC
Turbine Generator Regulator Panel AC
Field Instruments AC
Local Push Button Box AC
Control Valve (Bypass) No.1 & No.2 AA
Control Valve (Spray) AA
Control Valve (Bypass Acc Unit-1,2) AA
Control Valve (Spray Acc Unit-1,2) AA
Spare Parts for Panel AC
4. Plant
STG Enclosure AA
Manual Valve BA
Drain Piping and Support BA
Steam Trap BA
Air Operated Valve BA
5. Erection Material
Impulse Piping BA
6. Mechanical Erection Material
Thermal Insulation Materials (1),(2),(3),(4),(5) AX
Sub Sole Plate etc. for Auxiliary Item BA
Miscellaneous BA
17
D. Repair and Repack procedure
Damaged Potion
Gum-tape Gum-tape
A A
Patching material
Damage to packing 10mm(0.39in)
State of repair
18
Damaged Potion Patching material
50mm (1.97in) Patching Patching
100mm material material
(3.94 in)
B
B
50mm
Damage to Patching
Folding of patch (1.97in)
packing (use a patch at least 100
(fold inside the damaged
mm (3.94 in) larger than B-B section (enlarged)
portion as shown)
the damaged area)
C portion
[For example]
a) Silica-gel White grains with a few blue ones. When the blue grains
turn to red (pink), it is an indication of moisture
absorption. Then, all the grains should be replaced.
b) KALAHARI DRY The Kalahari Dry solidifies to signal the user when
maximum absorbency has been reached.
19
(2) Replacement of desiccant into the package
When the packing is damaged, the desiccant should be replaced before repairing.
a) When sealing the barrier, put the polyethylene sides together and attach HEAT
SEALER from the aluminum side. (It will not be sealed if attached from the opposite
side.)
b) Attach the HEAT SEALER for about 1-2 seconds. If it is too short, the barrier cannot
be sealed sufficiently. If it is too long, the HEAT SEALER will be melted. In either
case, perfect sealing cannot be expected.
20
(4) Deaeration before completion of repair
a) Before sealing the final portion with HEAT SEALER, evacuate the inside of the
packing.
Barrier
packing
Final sealing
portion
Compressor or
Vacuum cleaner
(5) When unpacking, the barrier should be cut with a sharp knife or the like with
consideration for replacement of desiccant. Do not tear the packing by hand, as it
makes the repair difficult.
(6) Upon completion of repair, cover the packing with a sheet and store it indoors.
21