Professional Documents
Culture Documents
Method Statement For Installation of Electrical PVC Conduits and Accessories in The Concrete Slabs, Columns, Block Works and Concrete Walls
Method Statement For Installation of Electrical PVC Conduits and Accessories in The Concrete Slabs, Columns, Block Works and Concrete Walls
28.11.2020
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In The
Concrete Slabs, Columns, Block Works And Concrete Walls
REVISION HISTORY
1 PURPOSE 4
2 SCOPE 4
3 REFERENCE 4
4.1 MATERIALS 5
5 METHODS OF INSTALLATIONS 5
6 FIXING OF CONDUITS 8
7 RESPONSIBILITY 10
8 EQUIPMENT REQUIREMENTS 11
1. PURPOSE
This method statement explains the detailed requirements and procedures for the
installation of PVC Conduits and accessories in the concrete slabs, columns, block
works and concrete walls.
2. SCOPE
The methodology covers the procedure to be followed for the sequence of work. The
main works involve in the installation of PVC Conduits and accessories in the concrete
slabs, columns, block works and concrete walls with specifications.
3. REFERENCES
o Tender Documents
o Specifications
o Drawings and details.
o Quality plan.
o Standards mentioned at each of the technical specs.
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls
4.1. Materials
Material used will be as approved by the engineer. The sizes and routes routing will be as
per the approved shop drawing.
5. METHODS OF INSTALLATIONS
1. Drawings checks. Ensure all drawings are the latest revision and approved for
Construction issue. Ensure all drawings are fully co-coordinated with all other
Services and installations. Builders work drawings shall be submitted for approval
2. Ensure all work areas are released by the main contractor, before proceeding
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls
Drawings showing floor plans, elevations, details of wall / floor penetrations are
Available.
4. Mark all pipe routes on the slab using chalk lines. Make sure all routes are as
[[
6. Check the location of the piping within risers to ensure adequate space has
[
7. During the course of the installation of the conduit system, procedures for working and
8. All bends and sets shall be in accordance with IEE regulation 522-08 formed with the
aid of a helical spring fitted internally, with if necessary, the conduit warmed
sufficiently for it to move without avoidable wall thinning of the outside of the bend.
10. Joints between PVC conduit and fittings shall be made with suitable adhesive, but
expansion couplings shall be installed where any length of conduit, inclusive of draw in
the specification.
12. Conduits in floors shall be routed and installed so as to avoid the fixings of floor
Helmet.
Steel Toe Boots.
Safety gloves and Goggles.
Reflective vests.
Safety barricades for lifting, hydrotesting operations.
All safety equipment, warring devices shall be provided and used by the
working personnel.
b. All testers will be aware of all site dangers and will be briefed in accordance with
“Site Rules”
c. The joint cooperation of personnel and management shall provide
System Group Chief (site engineer) shall direct their staff and
Manual.
14. The work starts with the acknowledgement to the Contractor. Any obstruction
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls
15. The foreman in charge gives brief information to the installation team about the work
to be done, materials, fitting, tools and key points of the installation.
6. FIXING OF CONDUITS
When conduits are run on shuttering, prior to the laying of concrete insitu, additional
security must be provided near to every box and at intervals of not more than 1.2 meters
by binding short lengths of steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed to prevent excessive
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls
Movement and damage during the pouring and setting of concrete and shall be protected
from mechanical damage. Check there is no damage before screed / concrete is poured.
Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to
Where conduits are left "open ended" prior to wiring they shall be protected by caps or
All conduits runs must be designed to permit wiring to be readily installed after the
complete erection of the conduits through the available draw-in, accessory and luminary
suspension boxes.
Where surface mounted equipment (other than luminaries) is specified, all concealed
conduits shall be terminated and an adaptable box installed recessed into the wall at
Where conduits pass through an external wall/roof the conduit box shall be fitted on the
side and after wiring filled with an inert, permanently plastic compound having a high
insulation value.
Make provision in conduit and trunking, installation where building expansion joints are
Ensure conduits are not concealed until works has been inspected and approved. Ensure
that conduit and fittings buried in concrete or behind plaster are protected against
Project Manager:
* To ensure that all the preparation and application works are carried out according to
* To ensure that the progressing of work is carried out according to the planned program
* To ensure that all the equipment and materials required to execute the work are
* To co –ordinate with the Main contractor, MEP Coordinator and Safety Officer, for a safe
Site Engineer:
* To ensure that the works are carried out according to the Contract Specifications,
team.
* To monitor the progress of work in relation with the work program and to report to the
Project Manager.
* To co-ordinate with the safety officer and to ensure that the works are carried out in safe
practicing methods.
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls
* The foreman will carry out his duties by maintaining continuous coordination with the
site engineer on daily basis, and ensure proper distribution of the workforce in the
* To ensure that his assistant foreman/ charge hand are aware of the job requirements
and they have enough information to carry out their duties properly.
* To ensure in consultation with the site engineer that the manpower involved in the works
* To ensure that the daily work is progressing as planned and advise the site engineer of
* To control disposal of waste materials according to the instructions received from the
site engineer.
* To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure that
all his working team are aware of the same to prevent accident and losses.
* To inform the site engineer and of the areas ready for inspection.
Distribution and the control of material shall be monitored by foreman and store keeper
8. EQUIPMENT REQUIREMENTS
The requirements that will be engaged for PVC Conduiting works will be as follows:
Hack saw
Measuring tape
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls
Bending spring
Drilling Machine
Strictly followed as per the manufacturer’s Health and Safety recommendations for
handling and use of the materials. Ensure all involved personnel shall be aware of the
same.
1. All materials shall be submitted for approval prior to procurement and delivery to site.
Materials shall be inspected upon delivery to site, to ensure compliance with the
approved submittal,
2. Pipe and fittings shall be unloaded in a proper manner, by mechanical means, crane or
forklift.
4. Material shall be stored properly; pipes shall be stored on Suitable place, fittings shall
5. Pipes shall be stacked or maintained in their original packing. Pipes of differing sizes
6. Factory applied end caps shall be maintained during delivery, storage and handling.