ORA-ZED TOWERS PHASE 1B

Method Statement for Installation


of Electrical PVC Conduits and
Accessories in the Concrete Slabs,
Columns, Block Works and
Concrete Walls

28.11.2020
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In The
Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

REVISION HISTORY

Description/ Reason for Approvals


Rev.No. Date
Issue Prepared Checked Approved

00 28.11.2020 Issue for approval M.H M.H M.H


Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 3 of12


TABLE OF CONTENTS

Para Page Revision Status


Description
No. No.

1 PURPOSE 4

2 SCOPE 4

3 REFERENCE 4

4 DEFINITIONS AND ABBREVIATIONS 5

4.1 MATERIALS 5

5 METHODS OF INSTALLATIONS 5

5.1 PRE-INSTALLATION WORKS 7

6 FIXING OF CONDUITS 8

7 RESPONSIBILITY 10

8 EQUIPMENT REQUIREMENTS 11

9 HEALTH AND SAFETY 12

10 MATERIALS HANDLING AND STORAGE 12


Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 4 of12

1. PURPOSE

This method statement explains the detailed requirements and procedures for the
installation of PVC Conduits and accessories in the concrete slabs, columns, block
works and concrete walls.

2. SCOPE

The methodology covers the procedure to be followed for the sequence of work. The
main works involve in the installation of PVC Conduits and accessories in the concrete
slabs, columns, block works and concrete walls with specifications.

3. REFERENCES

o Tender Documents
o Specifications
o Drawings and details.
o Quality plan.
o Standards mentioned at each of the technical specs.
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 5 of12

4. DEFINITIONS AND ABBREVIATIONS

4.1. Materials

Material used will be as approved by the engineer. The sizes and routes routing will be as
per the approved shop drawing.

5. METHODS OF INSTALLATIONS

Electrical PVC Conduit

5.1. Pre-Installation Works

1. Drawings checks. Ensure all drawings are the latest revision and approved for

Construction issue. Ensure all drawings are fully co-coordinated with all other

Services and installations. Builders work drawings shall be submitted for approval

Prior to the commencement of installation.


[

2. Ensure all work areas are released by the main contractor, before proceeding
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 6 of12


[[

With the works.


[[

3. Ensure a copy of approved for construction piping layout and detailed


[[

Drawings showing floor plans, elevations, details of wall / floor penetrations are

Available.

4. Mark all pipe routes on the slab using chalk lines. Make sure all routes are as
[[

Per the approved shop drawings.

5. Check the location of structural openings in relation to piping routes as


[

Indicated on the drawings.

6. Check the location of the piping within risers to ensure adequate space has
[

Been allowed to facilitate the services.

7. During the course of the installation of the conduit system, procedures for working and

Dressing the installation as recommended shall be employed.

8. All bends and sets shall be in accordance with IEE regulation 522-08 formed with the

aid of a helical spring fitted internally, with if necessary, the conduit warmed

sufficiently for it to move without avoidable wall thinning of the outside of the bend.

9. Conduit system shall be installed so as to ensure compliance with the requirements of

Specified Standard and Regulation.

10. Joints between PVC conduit and fittings shall be made with suitable adhesive, but

expansion couplings shall be installed where any length of conduit, inclusive of draw in

boxes etc., exceeds five meters in length.


Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 7 of12


11. The minimum and maximum sizes of conduit to be employed shall be 20mm and

32mmdiameter respectively, unless otherwise stated in subsequent sections of

the specification.

12. Conduits in floors shall be routed and installed so as to avoid the fixings of floor

standing equipment to be installed on the floor.


[

13. Check all the HSE requirements are OK

a. All personnel will be equipped as minimum with the necessary

Personal protection equipment’s as mentioned below:

 Helmet.
 Steel Toe Boots.
 Safety gloves and Goggles.
 Reflective vests.
 Safety barricades for lifting, hydrotesting operations.
 All safety equipment, warring devices shall be provided and used by the
working personnel.

b. All testers will be aware of all site dangers and will be briefed in accordance with
“Site Rules”
c. The joint cooperation of personnel and management shall provide

clean working conditions and free of environmental hazards.

System Group Chief (site engineer) shall direct their staff and

manpower, and supervise them for conformance of Quality

Manual.

d. Daily housekeeping at each working space, collection and disposal of

Debris at a certain area.

14. The work starts with the acknowledgement to the Contractor. Any obstruction
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 8 of12


Or difficulty arising from other disciplines’ works or hindering situation is reported

To the Contractor immediately.

15. The foreman in charge gives brief information to the installation team about the work
to be done, materials, fitting, tools and key points of the installation.

6. FIXING OF CONDUITS

Electrical PVC Conduit Fittings

When conduits are run on shuttering, prior to the laying of concrete insitu, additional

security must be provided near to every box and at intervals of not more than 1.2 meters

by binding short lengths of steel wire, of not less than 2mm diameter twisted around the

conduit and reinforcing steel. The conduits shall be adequately fixed to prevent excessive
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 9 of12

Movement and damage during the pouring and setting of concrete and shall be protected

from mechanical damage. Check there is no damage before screed / concrete is poured.

Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to

plastered over conduits shall not be less than 5mm.

Where conduits are left "open ended" prior to wiring they shall be protected by caps or

plugs to prevent the ingress of building material.

All conduits runs must be designed to permit wiring to be readily installed after the

complete erection of the conduits through the available draw-in, accessory and luminary

suspension boxes.

Where surface mounted equipment (other than luminaries) is specified, all concealed

conduits shall be terminated and an adaptable box installed recessed into the wall at

every surface mounted equipment position.

Where conduits pass through an external wall/roof the conduit box shall be fitted on the

side and after wiring filled with an inert, permanently plastic compound having a high

insulation value.

Make provision in conduit and trunking, installation where building expansion joints are

crossed or settlement is likely

Ensure conduits are not concealed until works has been inspected and approved. Ensure

that conduit and fittings buried in concrete or behind plaster are protected against

corrosion or electrolytic action prior to rendering


Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 10 of12


7. RESPONSIBILITY

 Project Manager:

* To ensure that all the preparation and application works are carried out according to

the Contract Specification and with the approved drawings.

* To ensure that the progressing of work is carried out according to the planned program

and as per the approved method of statement.

* To ensure that all the equipment and materials required to execute the work are

available according to the planned construction program.

* To co –ordinate with the Main contractor, MEP Coordinator and Safety Officer, for a safe

and proper execution of the works.

 Site Engineer:

* To ensure that the works are carried out according to the Contract Specifications,

approved method statement and the shop drawings.

* To provide all necessary information and distribute responsibilities to his construction

team.

* To monitor the progress of work in relation with the work program and to report to the

Project Manager.

* To co-ordinate with the safety officer and to ensure that the works are carried out in safe

practicing methods.
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 11 of12


 Foreman:

* The foreman will carry out his duties by maintaining continuous coordination with the

site engineer on daily basis, and ensure proper distribution of the workforce in the

required and planned locations.

* To ensure that his assistant foreman/ charge hand are aware of the job requirements

and they have enough information to carry out their duties properly.

* To ensure in consultation with the site engineer that the manpower involved in the works

are moving as agreed and planned for the work.

* To ensure that the daily work is progressing as planned and advise the site engineer of

any requirement for additional resources.

* To control disposal of waste materials according to the instructions received from the

site engineer.

* To ensure full coordination with the safety officer to maintain safe working and proper

housekeeping of the site, following the approved safety measures and further ensure that

all his working team are aware of the same to prevent accident and losses.

* To inform the site engineer and of the areas ready for inspection.

Distribution and the control of material shall be monitored by foreman and store keeper

8. EQUIPMENT REQUIREMENTS

The requirements that will be engaged for PVC Conduiting works will be as follows:

 Hack saw

 Measuring tape
Method Statement For Installation Of Electrical Method Statement For
Installation Of Electrical PVC Conduits And Accessories In
The Concrete Slabs, Columns, Block Works And Concrete Walls

Engineer: ECG Project: ORA-ZED TOWERS PHASE 1B

Page No. 12 of12


 Cutting plier

 Knife (End cutter)

 Bending spring

 Drilling Machine

9. HEALTH AND SAFETY

Strictly followed as per the manufacturer’s Health and Safety recommendations for

handling and use of the materials. Ensure all involved personnel shall be aware of the

same.

10. MATERIALS HANDLING AND STORAGE

1. All materials shall be submitted for approval prior to procurement and delivery to site.

Materials shall be inspected upon delivery to site, to ensure compliance with the

approved submittal,

2. Pipe and fittings shall be unloaded in a proper manner, by mechanical means, crane or

forklift.

3. Materials shall not be dropped to the ground, but lowered carefully.

4. Material shall be stored properly; pipes shall be stored on Suitable place, fittings shall

be stored on pallets or placed on shelving within the store area.

5. Pipes shall be stacked or maintained in their original packing. Pipes of differing sizes

and different schedules shall be stacked separately.

6. Factory applied end caps shall be maintained during delivery, storage and handling.