Sewer Network Works Method of Measurement

Table of Contents
Page

DIVISION 1 : GENERAL REQUIREMENTS ....................................................................................... 3


1.1 TEMPORARY WORKS ....................................................................................................... 3
1.2 CONTROL OF MATERIALS AND STANDARDS FOR SAMPLING AND
TESTING............................................................................................................................3
1.3 CONTRACTOR'S PLANT AND EQUIPMENT.................................................................. 3
1.4 TEMPORARY FACILITIES ................................................................................................ 3
DIVISION 2: EARTHWORK..................................................................................................................... 4
2.1 PAY ITEMS.......................................................................................................................... 4
2.2 SITE CLEARING ................................................................................................................. 4
2.2.1 Measurement .............................................................................................................. 4
2.3 REMOVAL OR REALIGNMENT OF OBSTRUCTIONS AND UTILITIES..................... 4
2.4 STRUCTURAL EXCAVATION AND BACKFILL............................................................ 5
2.4.1 Measurement .............................................................................................................. 5
2.5 EARTHWORK FOR PIPE TRENCHES .............................................................................. 6
2.5.1 Measurement .............................................................................................................. 6
DIVISION 3: ROADWORKS REINSTATEMENT OF SURFACES AND PAVEMENT
COATINGS.......................................................................................................................... 9
3.1 Measurement ......................................................................................................................... 9
DIVISION 4 : PIPEWORKS AND APPURTENANCES..................................................................... 11
4.1 PAY ITEMS........................................................................................................................ 11
4.2 PIPES, FITTINGS AND ACCESSORIES.......................................................................... 11
4.2.1 Measurement ............................................................................................................ 11
4.3 VALVES, STOPS, HOUSE CONNECTIONS AND SUNDRY WORKS......................... 13
4.3.1 Measurement ............................................................................................................ 13
4.4 BEDDING, SURROUND, HAUNCHING, ENCASEMENT AND THRUST
BLOCKS ............................................................................................................................. 15
4.4.1 Measurement ............................................................................................................ 15
4.5 MANHOLES AND INSPECTION CHAMBERS .............................................................. 16
4.5.1 Measurement ............................................................................................................ 16
4.6 VALVE CHAMBERS ON FORCE MAINS ...................................................................... 17
4.6.1 Measurement ............................................................................................................ 17

S0487-RPT-PM-08 REV A TOC - i


Sewer Network Works Method of Measurement

PREAMBLE

SCOPE AND BASIS OF PAYMENT

Scope of Payment

The Contractor shall consider that all items shown in contract and corresponding to BOQ
shall include full payment for all labour, material, tools, equipment, organizational costs,
insurance, shipping, duties and other charges, overheads, profit, royalties, transport,
handling, setting up, payments to others for land or use of land or damage to property of
others, all temporary works, incidental works necessary for proper completion of the Works
and which shall not be paid for directly but shall be considered as subsidiary works the costs
of which shall be deemed to be included in the Contract Rates and Amounts for related Pay
Items.

Basis of Payment

A. Quantities determined in accordance with this Standard Method of Measurement for


sewer works shall be paid for at the respective Contract Rates and Amounts and Contract
rates per unit of measurement, for each of the particular Pay Items shown in the Bills of
Quantities, which rates and amounts shall be full compensation for furnishing everything
necessary for the proper execution, completion of the Works.

B. Wherever any "Measurement" rule, as contained in this Standard Method of


Measurement for sewer works, states that no measurement shall be made for direct payment
of works prescribed in a particular Section of the Specification, performance of such works
shall not be paid for directly but shall be considered as subsidiary works the costs of which
shall be deemed to be included in the Contract Rates and Amounts for related Pay Items.

C. The measurement rules contained in this Standard Method of Measurement for sewer
works may not cross reference to all the Sections of the Specification. Wherever these rules
are absent, the works prescribed in those particular Sections of the Specification shall not be
measured for direct payment, unless shown as Pay Items in the Bills of Quantities, but shall
be considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

D. Unless shown as Pay Items in the Bill of Quantities, all other works prescribed in the
various Sections of the Specification, shall not be measured for direct payment, but shall be
considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

S0487-RPT-PM-08 REV A Page 1 of 18


Sewer Network Works Method of Measurement

E. In the case of works or drawings details that are not mentioned in BOQ, these works
and details shall be considered included in other items of BOQ.

F. All length measurements shall be horizontal to the nearest 1/100m. All area
measurements shall be the nearest 1/100m2. Volumetric measurements shall be to the
nearest 1/100m3.

G. Abbreviations:

L.m. = Linear meter m3 = meter cube


m2 = meter square L.s. = Lump sum

All rates and amounts shall be quoted in Saudi Riyals (S.R).

S0487-RPT-PM-08 REV A Page 2 of 18


Sewer Network Works Method of Measurement

DIVISION 1 : GENERAL REQUIREMENTS

1.1 TEMPORARY WORKS

A. All works, other than works prescribed in Section 1.04 of the Specification, shall not
be measured for direct payment, but shall be considered as subsidiary works, the costs of
which shall be deemed to be included in the Contract Rates and Amounts for related Pay
Items.

1.2 CONTROL OF MATERIALS AND STANDARDS FOR SAMPLING AND


TESTING

A. Unless shown as Pay Items in the Bill of Quantities, sampling, testing, and retesting,
material sources, quality requirements, certificates' inspections, storage and handling
requirements, standard specifications to be furnished, and all other works prescribed in
Section 1.05 of the Specification, shall not be measured for direct payment, but shall be
considered as subsidiary works, the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

1.3 CONTRACTOR'S PLANT AND EQUIPMENT

A. The works prescribed in Section 1.06 of the Specification shall not be measured for
direct payment, but shall be considered as subsidiary works, the costs of which shall be
deemed to be included in the Contract Rates and Amounts for related Pay Items.

1.4 TEMPORARY FACILITIES

A. Unless shown as Pay Items in the Bill of Quantities, all other works prescribed in
Section 1.08 of the Specification shall not be measured for direct payment, but shall be
considered as subsidiary works, the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

S0487-RPT-PM-08 REV A Page 3 of 18


Sewer Network Works Method of Measurement

DIVISION 2 : EARTHWORK

2.1 PAY ITEMS

Unless shown as Pay Items in the Bill of Quantities, all other works prescribed in Division 2
of the Specification, shall not be measured for direct payment, but shall be considered as
subsidiary works the costs of which shall be deemed to be included in the Contract Rates
and Amounts for related Pay Items.

2.2 SITE CLEARING

2.2.1 Measurement

Unless shown as a Pay Item in the Bill of Quantities, which would be included in square
meters, clearing and grubbing shall not be measured for direct payment, but shall be
considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

2.3 REMOVAL OR REALIGNMENT OF OBSTRUCTIONS AND


UTILITIES

a) Location of Obstructions:

Pursuant to status of clause (d) of art 1-3-6 of specifications, no measurement or payment


shall be effected against any limitation of location of obstructions and utilities existing under
ground and / or culverts and other obstructions.

b) Relocation or realignment of present installation and utilities:

Payment shall be affected for works of relocation of services in linear meter to cover costs
of full works required for execution, covering excavations, bedding, backfills, supply, repair
of surfaces, asphalting and concrete protection… etc., covering also any incidental expenses
and any sum paid by contractor to any competent public or private authority.

PAY ITEMS UNIT OF MEASUREMENT

1- Relocation or Replacement of Existing Utilities Linear Meter (L.M)

S0487-RPT-PM-08 REV A Page 4 of 18


Sewer Network Works Method of Measurement

c) Intersection with existing installations and obstructions:

No payment shall be effected against intersection with existing installations and


obstructions, whether underground, surface or outstanding, in the course of execution.

d) Backfill and removal or replacement of septic tanks:

Payment shall be effected against number of present tanks that should be fully removed and
replaced, or the area in m2 of septic tanks that will be partially removed, at unit rates
specified in bills of quantity. Works are to cover all requirements, like providing facilities
of temporary drainage, excavation, destruction, breakage, rebuilding of walls in case of
partial destruction, disposal of residues, emptying tanks, backfill of ruined area, repair of
surfaces, asphalting works … etc., settlement of said costs represents full compensation for
supply of all material, providing labour force and equipment, in line with specifications and
directions of project engineer.

PAY ITEMS UNIT OF MEASUREMENT

1- Backfill and removal or replacement of septic tanks Nr.

2- Partial removal of septic tanks m2

2.4 STRUCTURAL EXCAVATION AND BACKFILL

2.4.1 Measurement

A. Works of structural excavation and backfilling related to pipe laying (Manholes,


Inspection Chambers, valve chambers … etc). shall not be measured for direct payment, but
shall be considered as subsidiary works the costs of which will be deemed to be included in
the Contract Rates and Amounts for related Pay Items.

B. All other structural excavation, of whatever type, shall be measured as "unclassified


excavation", which shall be deemed to include all materials encountered of any nature,
including silt, clay, sand, gravel and granular materials and fractured, jointed and solid rock.

C. Structural excavation shall be measured by cubic meter of material excavated for the
major structures, hauled away and disposed of as directed, or stockpiled on, or in the vicinity
of the Works, and the excavated areas backfilled, completed and accepted.

D. Measurement of structural excavation shall commence from original ground


elevations to the bottom of structure base. Limits shall not be greater than vertical planes

S0487-RPT-PM-08 REV A Page 5 of 18


Sewer Network Works Method of Measurement

500 mm from the maximum dimension, on each side of the footing or other controlling
portion of the structure.

E. Additional excavation in unstable material or other unsuitable material encountered


below foundation level shall be measured as part of the unclassified structural excavation.

F. Undeclared overdepth and overwidth excavation in soil and rock and the backfill
material including blinding concrete required in such cases, shall not be measured for direct
payment, but shall be considered as subsidiary works the costs of which will be deemed to
be included in the Contract Rates and Amounts for related Pay Items.

G. Temporary cofferdams, temporary support system, bailing, drainage, pumping,


sheeting, concrete blinding layers and all other Temporary Works shall not be measured for
direct payment, but shall be considered as subsidiary works the costs of which will be
deemed to be included in the Contract Rates and Amounts for related Pay Items.

H. Permeable drainage layer shall be measured by the cubic meter of material


successfully placed and accepted.

I. Borrow excavation shall be measured by cubic meter of suitable material excavated


hauled and used for formation of embankments including trimming of slopes preparation
and completion of roadway subgrades and shoulders.

J. Backfilling works without excavation shall be measured by cubic meter at required


locations like Wadi crossings and dirt roads.

PAY ITEMS UNIT OF MEASUREMENT

1- Permeable Drainage Layer Cubic Meter (m3)

2- Borrow excavation backfill Cubic Meter (m3)

3- Backfilling without excavation Cubic Meter (m3)

2.5 EARTHWORK FOR PIPE TRENCHES

2.5.1 Measurement

A. Trench excavation and backfill shall be paid for per meter cube measured in
horizontal layers for the different depth categories shown in the list of Pay Items. The depth

S0487-RPT-PM-08 REV A Page 6 of 18


Sewer Network Works Method of Measurement

of each layer shall be the average depth. Trench length shall be measured between outer
surfaces of manholes or chambers after subtracting 50cm from each side, which are included
in excavation for manholes and chambers. Trench width shall be as specified in
specifications or shown on Drawings. Trench depth shall be measured from the finished
road level to the bottom of pipe bedding.

B. The following, related to trench excavation and backfill, shall not be measured for
direct payment, but shall be considered as subsidiary works the costs of which shall be
deemed to be included in the Contract Rates and Amounts for related Pay Items:

- Excavating in any material encountered excluding rock for which an extra over item
is provided.

- Blasting, barring, wedging or other methods for rock excavation.

- Excavation at any level and to any depth.

- Excavation curved on plan.

- Allowance for working space.

- Increase in bulk for excavating.

- Excavating below water table and dewatering as necessary.

- Keeping excavations free from water.

- Levelling, ramming, trimming and grading bottoms and trimming sides and bottoms
of excavation.

- Planking and strutting and supporting the sides of excavation except for areas where
soil support system is required.

- Returning, filling and ramming selected excavated material around structures,


manholes, or chambers; multiple handling of excavated material and excavation
from borrows pits and transporting about the Site.

- Segregation of the various classes of excavated spoil and stock piling as may be
directed by the Engineer.

- Disposal of surplus excavated material including depositing and consolidating where


directed on Site or removing from Site and depositing at a tip to be provided and
paid for by the Contractor.

- Trench final backfill.

- Consolidation of final backfill material using water or hand tamping.

S0487-RPT-PM-08 REV A Page 7 of 18


Sewer Network Works Method of Measurement

- Any other necessary works for completing the work.

C. Thrust boring works for crossing highways and railways shall be measured by linear
meter for the different diameters, and it shall include all necessary material, works,
coordination with concerned parties and all that is necessary to complete works according
to the technical specifications and drawings.

PAY ITEMS UNIT OF MEASUREMENT

1- Trench excavation and backfilling

- Depth up to 2.5 m Cubic meter (m3)


- Depth between 2.5 and 4.0 m Cubic meter (m3)
- Depth between 4.0 and 6.0 m Cubic meter (m3)
- Depth between 6.0 and 8.0 m Cubic meter (m3)
- Depth exceeding 8.0 m Cubic meter (m3)

2- Extra over trench excavation for excavation Cubic meter (m3)


in rock

3- Thrust boring Works (state diameter) Linear meter (m)

S0487-RPT-PM-08 REV A Page 8 of 18


Sewer Network Works Method of Measurement

DIVISION 3 : ROADWORKS REINSTATEMENT OF SURFACES AND


PAVEMENT COATINGS

3.1 Measurement

A. Surface reinstatement works should be executed according to the specifications of


the Ministry of Transport, and municipalities specifications, and Contractor should refer to
the latest edition of these specifications.

B. Sealing of cracks shall not be measured for direct payment but shall be considered
as subsidiary works the costs of which will be deemed to be included in the Contract Rates
and Amounts for related Pay Items.

C. Pavement repairs shall be measured by the square meters of repair, prepared, filled,
compacted, completed and accepted. This area shall be calculated based on payable trench
width as shown in the table of the trench excavation detail. Measurement shall be of the
areas shown on the Drawings or ordered by the Engineer.

D. Trench reinstatement and asphalting works shall be measured by cubic meters for
works of reinstatement, preparation, filling, compaction, completion and acceptance. This
volume shall be calculated based on payable reinstatement trench width as shown in the
table of the trench excavation detail drawing with an additional 15 cm from each side.
Measurement shall be made for surfaces and thicknesses as shown on drawing or as
directed. Where allowable trench width is exceeded, Contractor shall bear the cost of
additional excavation as well as the cost of surface reinstatement and asphalting.

E. Sidewalk reinstatement shall be measured by the meter square including bedding,


tiles, mortar, curbstone, and all necessary works for reinstatement.

F. Reinstatement of curbstones as per specifications and concerned authorities shall be


measured by linear meter.

G. Bituminous layers or materials for pavement and for base and sub-base layers and
traffic signs and cat eyes and others shall not be measured for direct payment.

PAY ITEMS UNIT OF MEASUREMENT

1- Roadwork Reinstatement Square meters (m2)

S0487-RPT-PM-08 REV A Page 9 of 18


Sewer Network Works Method of Measurement

2- Reinstatement of curbstones Linear meter (m)

3- Trench Reinstatement Cubic meters (m3)

3.1- Ordinary Asphalting Type A Cubic meters (m3)

3.2- Ordinary Asphalting Type B Cubic meters (m3)

3.3- Ordinary Asphalting Type C Cubic meters (m3)

3.4- Type A Asphalting with spreading machine Cubic meters (m3)

3.5- Type B Asphalting with spreading machine Cubic meters (m3)

3.6- Type C Asphalting with spreading machine Cubic meters (m3)

3.7- Type A Asphalting with milling and spreading Cubic meters (m3)
machines

3.8- Type B Asphalting with milling and spreading Cubic meters (m3)
machines

3.9- Type C Asphalting with milling and spreading Cubic meters (m3)
machines

S0487-RPT-PM-08 REV A Page 10 of 18


Sewer Network Works Method of Measurement

DIVISION 4 : PIPEWORKS AND APPURTENANCES

4.1 PAY ITEMS

A. Unless shown as Pay Items in the Bill of Quantities, all other works prescribed in
Division 4 of the Specification, shall not be measured for direct payment, but shall be
considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

4.2 PIPES, FITTINGS AND ACCESSORIES

4.2.1 Measurement

A. Trench excavation, bedding and backfilling shall be measured and paid for as
indicated in Section "Earthworks for Pipe Trenches".

B. Pipes shall be paid for per linear metre measured as a straight line between the
external faces of consecutive manholes. This includes fittings, couplings (2No.) on each side
of the external wall of manholes. No allowance will be made for cut ends and waste.

C. Connection to existing pipelines shall not be measured for direct payment, but shall
be considered as subsidiary works the costs of which will be deemed to be included in the
Contract Rates and Amounts for the related Pay Items.

D. The following, related to pipes, shall not be measured for direct payment, but shall
be considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items:

- Staking out, field surveying and preparation of shop Drawings.

- Pipe fittings, specials and couplings.

- Y connection for empty plots or plots under construction with spindles for a depth
greater than 2.5m.

- Additional sections adjacent to bends and manholes.

- Thrust block for bends, tees and tapers for force mains.

- Transportation to and hauling about the Site, loading, unloading and lowering
materials in the trench.

S0487-RPT-PM-08 REV A Page 11 of 18


Sewer Network Works Method of Measurement

- Lubricating agent used for assembling the pipe sections.

- Cutting, machining, chamfering, etc. of standard length pipes.

- Assembling the pipes and couplings and connecting to fittings and valves, or
chambers, manholes and or structures as applicable.

- Tape wrapping for DI pipes with 55% overlap, where required and as
specified

- Warning tape for metal pipes and dielectric tape for non-metal pipes.

- Testing as per specifications.

- Ancillary works and materials.

- Flushing, cleaning, painting, lining and coating.

- Any other requirements to accomplish work completely.

E. Unless stated as pay items in the BOQ, all items like excavation, sheeting or
backfilling, pipes connections, painting equipment, forms, tools, furnishing and placing of
material and all required items to complete works appropriately will not be measured for
direct payment but shall be considered as subsidiary works the costs of which will be
deemed to be included in the Contract Rates and Amounts for the related Pay Items.

F. Pipes shall be paid for in two payments. The first payment shall constitute 50% of
the item’s value after completion of trench excavation, bedding, and laying of pipes,
accomplishing testing successfully, and the second payment will constitute 50% of the
item’s value after completing final backfilling and after connection to existing pipes.

PAY ITEM UNIT OF MEASUREMENT

1- Pipe (State size and type) Linear Meter (m)

S0487-RPT-PM-08 REV A Page 12 of 18


Sewer Network Works Method of Measurement

4.3 VALVES, STOPS, HOUSE CONNECTIONS AND SUNDRY WORKS

4.3.1 Measurement

A. Unless shown as Pay Items in the Bill of Quantities, items of work such as
excavation, sheeting or backfilling, or for breaking into existing pipes, blinding works,
painting, equipment, forms, tools, furnishing and placing materials, labour, or any other item
necessary for the proper completion of the work, shall not be measured for direct payment,
but shall be considered as subsidiary works the costs of which shall be deemed to be
included in the Contract Rates and Amounts for related Pay Items.

B. Isolation valves on force mains (gate or butterfly) shall be paid for per unit installed
according to size indicated in the Bill of Quantities.

C. Air valves on force mains shall be paid for per unit installed according to size
indicated in the Bill of Quantities.

D. The following, and/or any other requirements to accomplish the work related to
isolation valves (gate or butterfly) completely, shall not be measured for direct payment, but
shall be considered as subsidiary works the costs of which shall be deemed to be included in
the Contract Rates and Amounts for related Pay Items:

- Lowering into the trench and installing.

- Over excavation for concrete supports.

- Concrete supports and thrust blocks.

- Appropriate fittings and/or couplings and dismantling joint for connecting to


adjacent pipe or fitting.

- Flanged or socket adaptors necessary for connecting to adjacent spigot ends.

- Gaskets, dismantling couplings and puddle flanges.

- Bolts, nuts, gaskets operating key, or hand wheel and others.

- Ancillary works and material required including sign posts.

- Painting, lining and coating.

- Extension spindles plus square nuts to fit spindles.

- Valve marker post and plate.

S0487-RPT-PM-08 REV A Page 13 of 18


Sewer Network Works Method of Measurement

- All other requirements necessary to complete works.

E. The following, and any other requirements to accomplish the work completely
related to air valves on force mains, shall not be measured for direct payment, but shall be
considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items:

- Gaskets, dismantling couplings and puddle flanges.

- Isolating gate valve.

- Drilling and fixing the flanged spool outlets for air valve connections.

- Ancillary works and material required including sign posts.

- Painting lining and coating.

- Valve marker post and plate.

- All other necessary requirements to complete works.

F. Sewer connections shall be measured as three different components; connection to


main sewer, inspection chambers, and connection pipes.

G. The following, and/or any other requirements to accomplish the work completely
related to house connections to sewer network by mean of “Y” connections or saddles or
manholes shall not be measured for direct payment, but shall be considered as subsidiary
works the costs of which shall be deemed to be included in the Contract Rates and Amounts
for related Pay Items:

- Supply of all materials, pipes sections, couplings, spindles sections, protection


works, encasement, manholes opening, and special pipes, etc…

- Mounting connecting, testing, and commissioning

- Supplying and installing pipes, fittings, and all necessary works for connections
between inspection chambers and plot limit.

H. Inspection chambers (refer to section 4.5).

I. Connecting pipes: payment for connecting pipes shall cover payment for excavation
and earthworks as per section 2.5 and the payment for pipes and accessories as per section
4.2

S0487-RPT-PM-08 REV A Page 14 of 18


Sewer Network Works Method of Measurement

J. Cleanouts: payment for cleanouts shall include all materials and connections as well
as mounting connecting, testing and commissioning

PAY ITEM UNIT OF MEASUREMENT

1- Isolation Valves (gate or butterfly) Number (Nr)


on force mains (Stating type and size /diameter)

2- Air valves on force mains Number (Nr)


(Stating type and size /diameter)

3- Sewer service connection per connection installed Number (Nr)

4- Connecting tubes (Stating type and size) Linear meter (Lm)

4.4 BEDDING, SURROUND, HAUNCHING, ENCASEMENT AND THRUST


BLOCKS

4.4.1 Measurement

A. Granular bedding and initial backfill shall be paid for by cubic meter where the depth
is measured from bottom of trench to 30 cm above pipe crown, and the payable width shall
be as mentioned in the specifications. Pipe length shall be measured from the outer surfaces
of manholes or valve chambers. The volume of pipe calculated based on outside diameter
shall be deducted from the total volume of excavations.

B. Bedding and initial backfill cost shall include supply, backfill, compaction with
suitable equipment as per manufacturer’s recommendations and all other requirements to
complete the Works.

C. Concrete Encasement shall be paid for by cubic meter where the width and depth of
concrete encasement shall be 40 cm plus the outside diameter of pipe as shown on drawings.
Length of pipe shall be measured on site, and pipe volume based on outside diameter shall
be deducted from the total volume of concrete.

D. All other works shall not be measured for direct payment, but shall be considered as
subsidiary works the costs of which shall be deemed to be included in the Contract Rates
and Amounts for related Pay Items.

S0487-RPT-PM-08 REV A Page 15 of 18


Sewer Network Works Method of Measurement

PAY ITEM UNIT OF MEASUREMENT

1- Granular bedding and initial backfill Cubic meter (m3)

2- Concrete encasement for pipes Cubic meter (m3)

3- Concrete cradle Cubic meter (m3)

4.5 MANHOLES AND INSPECTION CHAMBERS

4.5.1 Measurement

A. Manholes shall be paid for per unit and according to the depth categories shown in
the Bill of Quantities.

B. Inspection chambers shall be paid for per unit complete, including all necessary
connections to adjacent networks or houses.

C. No separate measurement or payment shall be made for any excavation, shoring,


sheeting or backfilling or for breaking into existing pipes or culverts in order to install new
manholes. All such additional items shall not be measured for direct payment, but shall be
considered as subsidiary works the costs of which shall be deemed to be included in the
Contract Rates and Amounts for related Pay Items.

D. No separate payment shall be made for blinding, painting, equipment, forms, tools,
furnishing and placing materials, labour, or any other item necessary for the proper
completion of the work. All such additional items shall not be measured for direct payment,
but shall be considered as subsidiary works the costs of which shall be deemed to be
included in the Contract Rates and Amounts for related Pay Items.

E. The following, related to manholes and inspection chambers, shall not be measured
for direct payment, but shall be considered as subsidiary works the costs of which shall be
deemed to be included in the Contract Rates and Amounts for related Pay Items whether
pre-cast or cast-in-situ:

- Excavating in any material including rock. Excavation shall be 50cm greater than
largest manhole section from each face of the manhole. This includes soil support,
dewatering, backfilling and carting away.

- Concrete, reinforcing steel, blinding, beds, surrounds, benching and suspended slab
in accordance with the preambles for ‘Concrete Work’ as specified.

S0487-RPT-PM-08 REV A Page 16 of 18


Sewer Network Works Method of Measurement

- Fittings, inside manhole wall with each pipe section, short pieces within manholes
and within the external faces of the walls or the protrusions,and the concrete
surround of manhole back drop.

- Half pipe sections, isolated openings and coupling sections mounted with the
manhole for all house connections.

- Granolithic rendering to benching (cement treated with epoxy).

- Internal lining and external protection to exposed faces of concrete.

- Concrete rings as required to make up levels.

- Supply and fixing of covers, grates and frames with all ancillary works and
protective coating.

- Testing structures for water tightness and any subsequent re-testing.

- Ladders or rungs and puddle flanges built into walls.

- All ancillary items as specified and as shown on drawings and all other requirements
necessary to complete the work.

PAY ITEM UNIT OF MEASUREMENT

1- Manhole (Stating size and depth) Number (Nr)

2- Inspection chamber (Stating size and depth) Number (Nr)

4.6 VALVE CHAMBERS ON FORCE MAINS

4.6.1 Measurement

A. Valve chamber (for butterfly valves, air valves, and washout valves) shall be paid
per unit. Payment shall include excavation, soil support, backfilling, surface reinstatement,
concrete works, frames, covers, and all ancillary works to make a complete unit.

B. No separate measurement or payment shall be made for any excavation, sheeting or


backfilling, or for breaking into existing pipes or culverts in order to install valve chambers.
All such additional items shall not be measured for direct payment, but shall be considered
as subsidiary works the costs of which shall be deemed to be included in the Contract Rates
and Amounts for related Pay Items.

S0487-RPT-PM-08 REV A Page 17 of 18


Sewer Network Works Method of Measurement

C. No separate payment shall be made for blinding, painting, equipment, forms, tools,
furnishing and placing materials, labour, or any other item necessary for the proper
completion of the work. All such additional items shall not be measured for direct payment,
but shall be considered as subsidiary works the costs of which shall be deemed to be
included in the Contract Rates and Amounts for related Pay Items.

D. The following, related to valve chambers, shall not be measured for direct payment,
but shall be considered as subsidiary works the costs of which shall be deemed to be
included in the Contract Rates and Amounts for related Pay Items whether pre-cast or cast-
in-situ:

- Excavating in any material including rock in accordance with the preambles for
‘Excavation and Earthworks’ including soil support, dewatering, backfilling and
carting away.

- Concrete, reinforcing steel, blinding, beds, surrounds, benching and suspended slab
in accordance with the preambles for ‘Concrete Work’.

- Necessary fittings, couplings, short pieces and concrete surrounds for drop
manholes.

- Granolithic rendering to benching (cement treated with epoxy).

- Internal lining and external protection to exposed faces of concrete.

- Concrete rings as required to make up levels.

- Supply and fixing of covers, grates and frames with all ancillary works and
protective coating.

- Testing structures for water tightness and any subsequent re-testing.

- Ladders, rungs and puddle flanges built into walls.

- All ancillary items.

PAY ITEM UNIT OF MEASUREMENT

1- Butterfly valve chambers (Stating type and size) Number (Nr)

2- Air Release valve chambers (Stating type and size) Number (Nr)

3- Other valve chambers (Stating type and, size) Number (Nr)

S0487-RPT-PM-08 REV A Page 18 of 18


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
1 Obstacles :

This includes location and relocation of different


existing service lines as per the directions of
related concerned authorities and the Engineer.

1-1 Relocation of telephone lines L.m


1-2 Relocation of Fiber Optic Cables L.m
1-3 Relocation of low voltage electrical cables (≤500V) L.m

1-4 Relocation of high voltage electrical cables (>500V) L.m

1-5 Relocation of existing water supply pipes and all


accessories including all requirements to complete
the works for the following diameters:

1-5-1 Small diameters up to 160mm L.m


1-5-2 Diameters between 160mm and 300mm (inclusive) L.m

1-5-3 Diameters between 300mm and 600mm (inclusive) L.m

1-5-4 Diameters between 600mm and 1200mm L.m


(inclusive)
1-6 Relocation of stormwater lines with all accessories
including all requirements to complete the works for the
following diameters:
1-6-1 400 mm L.m
1-6-2 500 mm L.m
1-6-3 600 mm L.m
1-6-4 700 mm L.m
1-6-5 800 mm L.m
1-6-6 1000 mm L.m
1-7 Relocation of sewer lines with all accessories including
all requirements to complete the works for the following
diameters:

1-7-1 300 mm L.m


1-7-2 400 mm L.m
1-7-3 500 mm L.m
1-7-4 600 mm L.m
1-8 Removal and backfilling of existing septic tanks. The
cost shall include supplying temporary sewerage
outlets, including excavation, removal of tank top slab
and walls surfaces as necessary, and removal and
transport of removed material and existing house
connections and emptying tanks and backfilling the area
with selected material and surface reinstatement:

1-8-1 Septic tanks up to 20 m² surface area Nr.


1-8-2 Septic tanks with surface area greater than 20m² and Nr.
less than or equal to 40m².

S0487-RPT-PM-10 REV A Page 1 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
1-9 Removal and backfilling of existing septic tanks. The
cost shall include supplying temporary sewerage
outlets, including excavation, removal of tank top slab
and walls surfaces as necessary, and removal and
transport of removed material and existing house
connections and emptying tanks and reconstruction of
boundary walls at approved locations and backfilling the
area with selected material and surface reinstatement:

1-9-1 Partial removal of septic tanks m² Nr.

Total Obstacles

S0487-RPT-PM-10 REV A Page 2 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
2 Earthworks
2-1 Trench excavation to a depth of 2.0m and the m³
width as per specification and drawings. Works
include getting required permissions, secure
safety guards, signboards, excavating, soil
support dewatering and removing excavated
material, backfilling, and all requirements needed
to complete works of laying pipes.

2-1-1 Trench excavation for Depth from 2.01 to 3.0 m as m³


described in item (2-1)
2-1-2 Trench excavation for Depth from 3.01 m to 4.0 as m³
described in item (2-1)
2-1-3 Trench excavation for Depth from 4.01 to 5.0 as m³
described in item (2-1)
2-1-4 Trench excavation for Depth from 5.01 m to 6.0 as m³
described in item (2-1)
2-1-5 Trench excavation for Depth from 6.01 m to 7.0 as m³
described in item (2-1)
2-1-6 Trench excavation for Depth from 7.01 m to 8.0 as m³
described in item (2-1)
2-1-7 Trench excavation for Depth from 8.01 m to 9.0 as m³
described in item (2-1)
2-1-8 Trench excavation for Depth from 9.01 m to 10.0 m³
as described in item (2-1)
2-1-9 Trench excavation for Depth from 10.1 m to 11.0 m³
as described in item (2-1)
2-1-10 Trench excavation for Depth from 11.01 m to 12.0 m³
as described in item (2-1)
2-1-11 Trench excavation for depth greater than 12 m as m³
described in item (2-1)
2-2 Extra over for trench excavation in rock for all m³
depths.
2-3 Bedding and initial backfill including supply initial m³
backfill and compaction with suitable equipment
and all requirements to complete work.

2-4 Backfill works for borrow pits as per specifications m³


and drawings and all requirements to complete
work.
2-5 Backfill works without excavation as per m³
specifications and drawings and all requirements
to complete work.
2-6 Supply and installation of geotextile fabric for m²
protection, permeable, woven or bonded non-
woven, polypropylene UV resistant and as
specified.

2-7 Concrete encasement as per drawings and m³


specifications and all requirements to complete
work
2-8 Concrete craddle as per drawings and m³
specifications and all requirements to complete
work.

S0487-RPT-PM-10 REV A Page 3 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
2-9 Highway and railways crossing by pipe jacking
according to technical specifications and
authorities specifications and the price shall
include all works and material needed for laying
pipes and coordination with authorities and all
requirements to complete work for the following
diameters:
2-9-1 200 mm L.m

2-9-2 300 mm L.m

2-9-3 400 mm L.m

2-9-4 500 mm L.m


2-9-5 600 mm L.m
2-9-6 800 mm L.m
2-9-7 900 mm L.m

2-9-8 1200 mm L.m

2-9-9 1500 mm L.m

2-9-10 > 1500 mm L.m

Total Trench Excavation

S0487-RPT-PM-10 REV A Page 4 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
3 Pipelines :
3-1 Supply and install vitrified clay pipes with standard
strength. Work includes supply, installation and
protection for pipes and fittings, thrust blocks,
leakage tests, operation surveying works and all
necessary works as per specifications for the
following pipe diameters:

3-1-1 200 mm L.m


3-1-2 250 mm L.m
3-2 Supply and installation of vitrified clay pipes with
extra strength as per item (3-1) for the following
pipes diameters:
3-2-1 300 mm L.m
3-2-2 350 mm L.m

3-2-3 400 mm L.m


3-2-4 500 mm L.m
3-2-5 600 mm L.m
3-3 Supply and installation of GRP pipes with stiffness
(5000N/m2) including protection, as per item (3-1)
and as specified for the following pipe diameters:

3-3-1 700 mm L.m

3-3-2 800 mm L.m

3-3-3 900 mm L.m

3-4 Supply and installation of concrete pipes with a


polyethylene linning (PE) as per item (3-1) for the
following pipe diameters:

3-4-1 1000 mm L.m

3-4-2 1100 mm L.m

3-4-3 1200 mm L.m


3-4-4 1400 mm L.m
3-4-5 1500 mm L.m
3-4-6 1600 mm L.m
3-4-7 1700 mm L.m
3-4-8 1800 mm L.m

Total Pipelines Works

S0487-RPT-PM-10 REV A Page 5 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
4 Force Main :
4-1 Supply, install test and commission of ductile iron
pipe class K9 with polyethylene lining as per item
(3-1) for the following pipe diameters:

4-1-1 250 mm L.m


4-1-2 300 mm L.m
4-1-3 400 mm L.m
4-1-4 500 mm L.m
4-1-5 600 mm L.m
4-1-6 700 mm L.m
4-1-7 800 mm L.m
4-1-8 900 mm L.m
4-1-9 1000 mm L.m
4-1-10 1200 mm L.m

Total Force Main Works

S0487-RPT-PM-10 REV A Page 6 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
5 Network Accessories :

5-1 Supply and install gate valves-16 bar (NP). Work


shall include supply and installation of all valve
accessories such as service box, stem, marker
post, couplings concrete base and surface box
following specifications and drawings for the
following diameters:
5-1-1 100 mm Nr.
5-1-2 150 mm Nr.
5-1-3 200 mm Nr.
5-1-4 250 mm Nr.
5-2 Supply and install butterfly valves-16 bar (NP) on
sanitary force main. Work shall include supply
and installation of all valve accessories, couplings,
marker post and concrete base and all
requirements according to specifications and
drawings for the following diameters:
5-2-1 300 mm Nr.
5-2-2 400 mm Nr.
5-2-3 500 mm Nr.
5-2-4 600 mm Nr.
5-2-5 700 mm Nr.
5-2-6 800 mm Nr.
5-3 Supply and install double air valves with isolation
valves and NP16 bars. Work shall include supply
and installation of all parts, couplings,
accessories, marker post as per specifications and
drawings on the force mains of the following
diameters:
5-3-1 Less than 300 mm (valve dia 40 mm) Nr.

5-3-2 300 mm - 600 mm (valve dia 60 mm) Nr.


5-3-3 700 mm - 800 mm (valve dia 100 mm) Nr.
5-4 Supply and construction of reinforced concrete
chambers for single isolation valves as shown in
drawings and as per specifications and work shall
include excavating, backfilling, concrete and
reinforced concrete works, casting, supply and
installation of covers, stairs and all necessary
accessories and pipes to connect the valve, and
surface reinstatement and all requirements to
complete works as mentioned below:

5-4-1 Single isolating valve chamber Type (1), internal Nr.


dimensions not less than 1500 mm x 1500 mm
for valves less than 300 mm diameter.

5-4-2 Single isolating valve chamber Type (2), internal Nr.


dimensions not less than 2000 mm x 1500 mm
for valves from 300 mm to 400 mm diameter.

S0487-RPT-PM-10 REV A Page 7 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
5-4-3 Single isolating valve chamber Type (3), internal Nr.
dimensions not less than 2500 mm x 2000 mm
for valves from 500 mm to 800 mm diameter.

5-5 Supply and construction of a reinforced concrete Nr.


chamber for Air Release Valves as per item (5-3)
as follows:
5-5-1 Air valve chamber Type (1), internal dimensions Nr.
not less than 1500mm x 1200mm for valves on
300 mm diameter pipelines and less.

5-5-2 Air valve chamber Type (2) , internal dimensions Nr.


not less than 2000mm x 1500mm for valves on
400mm - 600 mm diameter pipelines.

5-5-3 Air valve chamber Type (3) , internal dimensions Nr.


not less than 2500mm x 2000mm for valves on
700mm - 800mm diameter pipelines.

Manholes :
5-6 Supply and construct circular manholes of precast
/ cast in-situ concrete with internal diameter of
1.2m and/or square manholes 1.2 x 1.2 m
including excavating backfilling, internal and
external coating, stairs and covers according to
specifications and drawings and surface
reinstatement and all requirements to complete
the works for the following depth categories:

5-6-1 Depth up to 3m Nr.


5-6-2 Depth greater than 3.0 and up to 4.0 m Nr.
5-6-3 Depth greater than 4.0 and up to 5.0 m Nr.
5-6-4 Depth greater than 5.0 and up to 6.0 m Nr.
5-6-5 Depth greater than 6.0 and up to 8.0 m Nr.
5-7 Supply and construct circular manholes of precast
/ cast-in-situ concrete, with internal diameter 1.5m
and/or square 1.5x1.5m as per item (5-6) for the
following depth categories:
5-7-1 Depth up to 3m Nr.

5-7-2 Depth greater than 3.0 and up to 4.0 m Nr.

5-7-3 Depth greater than 4.0 and up to 5.0 m Nr.

5-7-4 Depth greater than 5.0 and up to 6.0 m

5-7-5 Depth greater than 6.0 and up to 8.0 m Nr.

5-7-6 Depth greater than 8.0 and up to 10.0 m Nr.

5-7-7 Depth greater than 10.0 and up to 12.0 m Nr.

5-7-8 Depth greater than 12.0 m Nr.

5-8 Supply and construct circular manholes of precast


/ cast-in-situ concrete with internal diameters 2m
and/or square 2.0x2.0 m as per item (5-6) for the
following depth categories:
5-8-1 Depth up to 3m Nr.

S0487-RPT-PM-10 REV A Page 8 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
5-8-2 Depth greater than 3.0 and up to 4.0 m Nr.
5-8-3 Depth greater than 4.0 and up to 5.0 m Nr.
5-8-4 Depth greater than 5.0 and up to 6.0 m Nr.
5-8-5 Depth greater than 6.0 and up to 8.0 m Nr.
5-8-6 Depth greater than 8.0 and up to 10.0 m Nr.
5-8-7 Depth greater than 10.0 and up to 12.0 m Nr.
5-8-8 Depth greater than 12.0 m Nr.
5-9 Supply and construct drop manholes with depth up
to 5.0m and the item shall include all works and
necessary material needed to accomplish works
according to specifications and drawings for the
following depth categories:
5-9-1 Drop manholes up to 1.5m depth for the following Nr.
diameters:

5-9-1-1 200 mm Nr.


5-9-1-2 300 mm Nr.
5-9-1-3 400 mm Nr.
5-9-1-4 500 mm Nr.
5-9-1-5 600 mm Nr.
5-9-1-6 700 mm Nr.
5-9-2 Drop manholes greater than 1.5m depth for the
following diameters:
5-9-2-1 200 mm Nr.
5-9-2-2 300 mm Nr.
5-9-2-3 400 mm Nr.
5-9-2-4 500 mm Nr.
5-10 Supply and construct drop manholes with depth
greater than 5.0m and the item includes all works
and needed material to finish work according to
specifications and drawings for the following
depths:
5-10-1 Drop manholes up to 1.5m depth for the following
diameters:
5-10-1-1 200 mm Nr.
5-10-1-2 300 mm Nr.
5-10-1-3 400 mm Nr.
5-10-1-4 500 mm Nr.
5-10-2 Drop manholes greater than 1.5m depth for the Nr.
following diameters:
5-10-2-1 200 mm Nr.
5-10-2-2 300 mm Nr.
5-10-2-3 400 mm Nr.
5-10-2-4 500 mm Nr.

Total Network Accessories

S0487-RPT-PM-10 REV A Page 9 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
6 House Connections :
6-1 Supply and construct vitrified clay sewer
connections to the manholes with a length up to
5m according to specifications and drawings.
Work shall include "Y" connections excavating,
backfilling, bedding, surfaces reinstatement,
removal of excavated material, getting the
permissions, secure the site with safety guards
and to supply vitrified clay standard strength
pipes, including all connection works for the
following diameters:
6-1-1 H.C. 100 mm Nr.
6-1-2 H.C. 150 mm Nr.
6-1-3 H.C. 200 mm Nr.
6-2 Supply and construct uPVC (class 4) sewer
connections to the manholes with a length up to
5m according to specifications and drawings.
Work shall include "Y" connections excavating,
backfilling, bedding, surfaces reinstatement,
removal of excavated material, getting the
permissions, secure the site with safety guards
and to supply uPVC pipes, including all connection
works for the following diameters:

6-2-1 H.C. 110 mm Nr.


6-2-2 H.C. 160 mm Nr.
6-2-3 H.C. 200 mm Nr.
6-3 Supply and construct vitrified clay sewer
connections to the pipelines with diameters up to
400 mm with a length up to 5m according to
specifications and drawings. Work shall include
"Y" or saddle connections, excavating,
backfilling, bedding, surfaces reinstatement,
removal of excavated material, getting the
permissions, secure the site with safety guards
and to supply vitrified clay standard strength
pipes, including all connection works for the
following diameters:
6-3-1 H.C. 100 mm Nr.
6-3-2 H.C. 150 mm Nr.
6-3-3 H.C. 200 mm Nr.
6-4 Supply and construct uPVC class 4 sewer
connections to the pipelines with diameters up to
400 mm with a length up to 5m according to
specifications and drawings. Work shall include
"Y" or saddle connections, excavating,
backfilling, bedding, surfaces reinstatement,
removal of excavated material, getting the
permissions, secure the site with safety guards
and to supply uPVC class 4 pipes, including all
connection works for the following diameters:

6-4-1 H.C. 110 mm Nr.


6-4-2 H.C. 160 mm Nr.
6-4-3 H.C. 200 mm Nr.

S0487-RPT-PM-10 REV A Page 10 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
6-5 Additional cost for connection lines of vitrified clay,
extra lengths greater than 5m and works shall be
as per item (6-1) for the following diameters:
6-5-1 H.C. 100 mm L.m.
6-5-2 H.C. 150 mm L.m.
6-5-3 H.C. 200 mm L.m.
6-6 Additional cost for uPVC connection lines, extra
lengths greater than 5m and works shall be as per
item (6-1) for the following diameters:
6-6-1 H.C. 110 mm L.m.
6-6-2 H.C. 160 mm L.m.
6-6-3 H.C. 200 mm L.m.
6-7 Supply and construct cleanouts from uPVC pipes
and the item includes all works, material and
necessary connections needed to finish work
according to specifications and drawings for the
following diameters:
6-7-1 H.C. 150 mm Nr.
6-7-2 H.C. 200 mm Nr.
6-8 Supply and construct inspection chambers on Nr.
sewer line connections and work shall include all
excavation works, backfilling, concrete,
connections and surfaces reinstatement as per
specifications and drawings and all requriements
to finish work for the following diameters:
6-8-1 60 cm diameter Nr.
6-8-2 90 cm diameter Nr.
6-9 provide and apply "Y" connection on major pipe
lines for the following house connection diameters

6-9-1 200 mm Nr.


6-9-2 300 mm Nr.
6-9-3 400 mm Nr.
6-9-4 500 mm Nr.
6-9-5 600 mm Nr.
6-10 Supply and construct cleanouts from standard
strenght vitrified clay at the end of sewer lines
6-10-1 150 mm Nr.
6-10-2 200 mm Nr.

Total House Connections

S0487-RPT-PM-10 REV A Page 11 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
................. Water Directorate

Unit Price Total Price


Item No. Description Unit Qty.
In Nr. In Words (S.R.)
7 Surface Reinstatement Works :

7-1 Curbs reinstatement for pipe trenches as per m²


specifications and requirements of related
authorities.
7-2 Curb tiles reinstatement for pipe trenches as per m²
specifications and requirements of related
authorities.
7-3 Curbstones reinstatement for pipe trenches as per L.m
specifications and requirements of related
authorities.
7-4 Surface reinstatement as per related authorities
and municipalities regulations
7-4-1 Ordinary asphalting Type "A" m
3

7-4-2 Ordinary asphalting Type "B" m3


7-4-3 Ordinary asphalting Type "C" m3
7-4-4 Type "A" asphalting with spreading machine. m3
7-4-5 Type "B" asphalting with spreading machine. m3
7-4-6 Type "C" asphalting with spreading machine. m3
7-4-7 Type "A" asphalting with spreading and milling m3
machine.
7-4-8 Type "B" asphalting with spreading and milling m3
machine.
7-4-9 Type "C" asphalting with spreading and milling m3
machine.

Total Rehabilitation Works

S0487-RPT-PM-10 REV A Page 12 / 13


Ministry of Water and Electricity Standard Bill of Quantities for Sewer Networks
.............. Water Directorate

Total Project Works

Part Total in Nr. Total in Words (S.R.)

Total Obctacles

Total Earthworks

Total Pipelines Works

Total Force Main Works

Total Network Accessories

Total House Connections

Total Surface Reinstatement Works

Total for the project (S.R.)

Page 13/13