Field Inspection and Testing Report: Insullation Resistance & Continuity Test For Power Cable
Field Inspection and Testing Report: Insullation Resistance & Continuity Test For Power Cable
Field Inspection and Testing Report: Insullation Resistance & Continuity Test For Power Cable
MAIN CONTRACTOR : PT ALTRAK 1978 SYSTEM NAME : INSULLATION RESISTANCE & CONTINUITY TEST
Test Voltage
Purpose of Test (Tick Appropriate Box) After Cable Pulling Test Duration
(1000Volt.)
Cond. Size
Cable No. Cable Rated Voltage From To M Ohm Continuity Passed Or Failed
( mm2 )
R1 - GRD 0,6/1,2kV 240 mm² GCP Transformer 400 OK Passed
Note :
MAIN CONTRACTOR : PT ALTRAK 1978 SYSTEM NAME : INSULLATION RESISTANCE & CONTINUITY TEST
Test Voltage
Purpose of Test (Tick Appropriate Box) After Cable Pulling Test Duration
(5000Volt.)
Cond. Size
Cable No. Cable Rated Voltage From To M Ohm Continuity Passed Or Failed
( mm2 )
R - GRD 12/20kV 50 mm² Transformer MV Panel OK Passed
S - GRD 12/20kV 50 mm² Transformer MV Panel OK Passed
T - GRD 12/20kV 50 mm² Transformer MV Panel OK Passed
R-T 12/20kV 50 mm² Transformer MV Panel OK Passed
S-T 12/20kV 50 mm² Transformer MV Panel OK Passed
T-R 12/20kV 50 mm² Transformer MV Panel OK Passed
Note :
PT ALTRAK 1978
Cond. Size
Cable No. Cable Rated Voltage From To M Ohm Continuity Passed Or Failed
( mm2 )
PT PLN Persero
FIELD INSPECTION AND TESTING REPORT
Result
No. Point of Earthing Remarks
(Ohm)
1 Body Transformer
1.00
2 Lightning 1
0.24
3 Lightning 2
0.24
4 Body Generator
0.27
5 Earthing Test for Existing PLN
0.87
Note :