ITP For MCC HV LV Switchgear Boards Pane
ITP For MCC HV LV Switchgear Boards Pane
ITP For MCC HV LV Switchgear Boards Pane
Ltd, Mumbai
SHEET 1 OF 2
Oil , Gas & Petrochemical Division, Inspection Dept.
8 H P X Factory Acceptance Test as per FAT procedure including Routine test as per IS specification:
- Visual & dimensional check including accessories & name plate, paint shade, bus size, creepages, clearances,
bus marking, sleeving and joint shrouding , Bill of material etc.
- Compartmentalisation, interchangeability of CBS, termination space, glanding, operation height, earthling, cable
sizes, accessibility of components etc.
- Electrical performance / operation check ( wiring and scheme check) as per approved drawings at worst voltage
conditions
- Relay operation check including fault annucaition check ( primary and secondary injection )
- HV test
Final documentation before shipment to site , spares & issue of Inspection Release Note / Inspection
10 I H H X
Report.
___________
MMCI
11 H P X Site Acceptance Test of the complete items as per SAT procedure consisting of:
- ON / OFF Operation of breaker both manually & electrically in test as well as service positions.
- Interface PLC Panel functional and simulation test with TAS as well as from PLC Panel in
totality for L.V. Switchgear.
12 I H H X Final site documentation , spares & issue of site Inspection Report/ IRN
LEGENDS: H - Hold Point :- An activity , which requires inspection / Verification and acceptance by HPCL/MMCI /TPIA before any further
processing is permitted. The vendor shall not process activity/item beyond a hold point without written approval.,
W- Witness:- An activity, which requires witnessing by HPCL/ MMCI/ TPIA with prior notification of the same inspection agency. Vendor
is not obliged to hold further processing. Basis of acceptance shall be as per relevant technical specification/ drawings/PR/MR.
R - Review :-To examine the inspection records for confirming compliance to requirements.; A- Approval : -To approve the inspection
documents for conforming compliance to requirements.; P- Perform/Prepare; W/R- Witness or Review; I- Information; X- Submit,
PWHT- Post weld Heat Treatment, PO- Purchase Order,MR/PR- Material /Purchase Requisition, PS- Purchase Specification,
NDT- Non destructive Testing, TPIA - Third Party Inspection Agency, MMCI - Mott MacDonald Consultants (India) Pvt. Ltd
Note: This is an Indicative Inspection & Test Plan identifying scope of inspection & review of documents by MMCI / TPI Agency / HPCL
as a minimum requirement.
Detailed Quality Assurance/Control Plan indicating all specified requirements after issue of PO / PR/MR / PS to be generated by
Vendor & same duly approved by MMCI / TPI agency to be submitted to HPCL for review/comments.
___________
MMCI