Professional Documents
Culture Documents
Complete House Estimate
Complete House Estimate
Q. Prepare a detailed estimate of building from the given plan & sections as shown in
below–
( )
Page 1
“Learn Civil Tech & Tricks”
Storage
( )
Total length of Centre Line =
21.20+10.50+3.30+8.60+7.60+14.92+10.60+16.60+10.60+3.10+4.08 = 111.10 m
No. of Junctions, n = 18
Measurement Sheet:-
Sr. Particulars of item No. Length Width Height Quantity Remark
No.
(m.) (m.) (m.)
1. Earthwork in excavation 1 100.30 1.20 1.10 132.40 m3 L = 111.10 - ½(18×1.2)
= 100.30 m
Bed rooms 2 4.90 3.10 0.30 9.114 m3 (Deduct Plinth thickness form
wall 40-30 = 10 cm)
Bath & W.C. 2 2.90 1.75 0.30 3.045 m3
This Value deduct from floor
Kitchen 1 3.40 3.90 0.30 3.978 m3 area
Open area(in front of study) 1 1.10 5.10 0.30 1.683 m3 Open area (st.) = 1.20×5.20
Open area(in front of storage) 1 1.20 1.64 0.30 0.59 m3 Open area (stg.) = 1.30×1.74
Total = 24.48+41.194 =
Total = 41.194 m3 67.674 m3
Page 2
“Learn Civil Tech & Tricks”
Total = 55.108 m3
Total = 29.49 m2
Parapet wall
Long Side 2 16.40 0.20 0.90 5.90 m3 Ls = 16.40 m
Ss = 10.90–2×0.20 = 10.50 m
Short Side 2 10.50 0.20 0.90 3.78 m3
Total = 5.90 + 3.78 = 9.68 m3
Deduction
Door Opening, D1 2 1.20 0.30 2.10 1.51 m3
D2 5 1 0.30 2.10 3.15 m3
D3 3 0.90 0.30 2.10 1.70 m3
Window Opening, W1 6 1.50 0.30 1.20 3.24 m3
W2 3 1.20 0.30 1.20 1.30 m3
Ventilation, V 2 0.75 0.30 0.45 0.20 m3
Lintels over Door 2 1.50 0.30 0.15 1.08 m3
5 1.30 0.30 0.15 0.30 m3
3 1.20 0.30 0.15 0.16 m3 Load Bearing 15 cm.
Lintels over Window 6 1.80 0.30 0.15 0.49 m3
3 1.50 0.30 0.15 0.20 m3
Page 3
“Learn Civil Tech & Tricks”
R.C.C. work in Beam (1:2:4) 1 108.40 0.30 0.40 13.01 m3 L = 111.10 - ½(18×0.3)
= 108.4 m
If you don’t know, then Thumb-
R.C.C. work in Column (1:2:4) 15 0.30 0.35 3.35 5.28 m3 rule for decide no. col. divide
total area by 6, 7 to get no. of
column (m2), 70, 80 (sq. ft.).
R.C.C. work in Lintel (1:2:4) 6 1.80 0.90 0.15 1.46 m3 Total=1.46+0.61 = 2.07 m3
3 1.50 0.90 0.15 0.61 m3
8. Quantity of Steel = 1% of (Slab + Beam + Column + Lintel) Density of steel = 7850kg/m3
=1%×(26.81+13.01+5.28+2.07) = 0.472 m3 Wt. of steel ≅ 37.05 Quintal
Weight of Steel = 0.472×7850 = 3705.20 kg
9. 1.5 cm Thick Plaster (1:4)
Bedroom (Both)
Long side 4 5 – 3.35 67 m2 Total = 109.88 m2
Short side 4 3.20 – 3.35 42.88 m2
Bathroom & W.C.
Long side 4 3 – 3.35 40.20 m2 Total = 68 m2
Short side 4 1.85 – 3.35 27.80 m2
Hall
Long side 2 8 – 3.35 53.60 m2 Total = 87.10 m2
Short side 2 5 – 3.35 33.50 m2
Kitchen
Long side 2 4 – 3.35 26.80 m2 Total = 50.25 m2
Short side 2 3.50 – 3.35 23.45 m2
Dining
Long side 2 3.50 – 3.35 23.45 m2 Total = 42.61 m2
Short side 2 2.86 – 3.35 19.16 m2
Storage
Long side 2 2.20 – 3.35 14.74 m2 Total = 32.23 m2
Short side (+outside also) 3 1.74 – 3.35 17.49 m2
Study
Long side 2 5 – 3.35 33.50 m2 Total = 52.26 m2
Short side 2 2.80 – 3.35 18.76 m2
Outer Complete
Long side 2 16.40 – 3.35 109.88 m2 Total = 182.91 m2
Short side 2 10.90 – 3.35 73.03 m2
Outer area (Bed)
Long side 2 4 – 3.35 26.80 m2 Total = 48.24 m2
Short side 2 3.20 – 3.35 21.44 m2
Outer area (Study)
Long side 2 5.20 – 3.35 34.84 m2 Total = 38.86 m2
Short side 1 1.20 – 3.35 4.02 m2
Outer area (Storage) 2 1.30 – 3.35 8.71 m2 Total = 8.71 m2
Page 4
“Learn Civil Tech & Tricks”
Deduction
Door Opening, D1 2 1.20 – 2.10 1.51 m2 We have to deduct from
D2 5 1 – 2.10 3.15 m2 both faces of wall
D3 3 0.90 – 2.10 1.70 m2 Total area for deduction =
Window Opening, W1 6 1.50 – 1.20 3.24 m2 2× area of deduction
W2 3 1.20 – 1.20 1.30 m2
Ventilation, V 2 0.75 – 0.45 0.20 m2
Parapet wall
Long Side 4 16.40 – 0.90 59.04 m2 Total = 96.84 m2
Short Side 4 10.50 – 0.90 37.80 m2
Total = 146.24 m2
Page 5
“Learn Civil Tech & Tricks”
Abstract Sheet:-
Sr. Particulars of item Unit Quantity Rate Amount
No. ₹ P.
13. Add 1.5% for Misc. items & fitting 1.5% of 13,83,590.00 20,753 85
14. Add 10% for Water Supply & 10% of 13,83,590.00 1,38,359 00
Sanitation
Total = ₹ 7,67,892.45
Page 6