Professional Documents
Culture Documents
Protective Relaying Testing ST6
Protective Relaying Testing ST6
CMC356 7UM85
IA,B,C
Stator
Case 1 Out of zone three phase fault at the HVP 47-2 bus.
The injected signals are shown in the next figure.
The 51V pick-up is changed depending on the phase to phase The remote feeder faults at HVP 47-2 and HVP 70 are
voltage. dynamically tested to check setting value of 51V function.
Case 2 Out of zone three phase fault at the HVP 70.
In this case the relay reacted the same as for faults at HVP 47-2.
The simultaneous trip K20-1, field breaker trip, back-up relay trip
are issued at the same time. The fault recording of the relay
showed a trip time of 3 msec by Idiff>> in phase C.
The pick-up is lowered due to the fact that the voltage is almost
zero, so min pick-up is 0.25*1.1*Ip.
The 87G will trip after the second ground fault in 12 msec. This
is within the specification.
In the fault log the trip sequence is shown. First the 67N is
tripping then the 50N&59N and the last defense on SFG 90% at
3 sec. The ground fault detection will generate a simultaneous
trip.
In the fault log the pick-up and drop off of the 32R is function is
shown. The trip valves are connected to an input of the 7UM85.
This contact is simulated with the Omicron output. Figure 22 Inadvertent energization scenario.
The breaker is tripped after 13msec. The fault log is shown V. Conclusion
below. The protective relaying settings in the 7UM85 are tested. The
test results comply with the specification and DOW
requirements. The testing proved compliance to the LPP16.6.
VI. Thanks
My special thanks to the test team EPDS, Martijn Van
Fraeijenhove en Koen van Wijck.
VII. Literature
[1] ATP Rule book
Figure 23 Fault log inadvertent energization.
[2] Protective relaying J.L. Blackburn
[3] ETAP 11
Case 12 Sequential trip
[4] Siemens Sigra
According the LPP 16.6 the over-excitation 24 and under-
frequency 81 are sequential trips. These two functions will trip
the turbine first. With tripping the turbine the trip valves are
closed and the generator will motorize. The 32R function will trip
the generator circuit breaker. The confirmation of the open
position of the generator breaker will trip the field breaker. This
sequential tripping sequence is written in CFC logic. The logic is
tested statically and dynamically tested. K20-2 is the sequential
trip relay that trips the turbine.
The underfrequency function 81 is also set in the relay. This
function is also tested with the sequential trip mode. See next
figure, K20-2 is tripped first.
Breaker failure.
In both relays breaker failure is programmed. A re-trip of the
own breaker is done after 200msec. If this is not clearing the
fault the breaker failure function will issue a trip to the feeding
breakers. This trip will be made after 400msec. The breaker
failure function is done on the current measurement and
auxiliary contact of the breaker. The last is needed for the
voltage related functions. The tripping of the feeder breakers is
done via the GOOSE protocol.
Overvoltage settings.
Two over voltage stages are set in the 7UM85. Stage one is
115%-10sec and stage 2 is set at 130% for 1 sec. Both stages are
tested statically and no false tripping during the dynamic
injection.