ETAP

Project: STUDY KELAYAKAN PV COCA-COLA Page: 1


12.6.0H
Location: CIBITUNG Date: 18-02-2020
Contract: 01 SN:
Engineer: ALVI HANDIKA SIREGAR Revision: Base
Study Case: LF
Filename: COCA-COLA DENGAN PV DAN PLN Config.: Normal

Bus Loading Summary Report

Directly Connected Load Total Bus Load

Bus Constant kVA Constant Z Constant I Generic


Percent
ID kV Rated Amp MW Mvar MW Mvar MW Mvar MW Mvar MVA % PF Amp Loading

Bus1 150.000 0 0 0 0 0 0 0 0 11.076 85.8 42.6

Bus2 20.000 0 0 0 0 0 0 0 0 10.942 86.8 319.7

Bus3 20.000 0 0 0 0 0 0 0 0 11.122 85.0 326.8

Bus4 20.000 3.808 2.360 0.952 0.590 0 0 0 0 5.600 85.0 161.7

Bus5 20.000 0 0 0 0 0 0 0 0 5.600 85.0 161.7

Bus6 20.000 7.616 4.720 1.837 1.139 0 0 0 0 11.122 85.0 326.8

* Indicates operating load of a bus exceeds the bus critical limit ( 100.0% of the Continuous Ampere rating).

# Indicates operating load of a bus exceeds the bus marginal limit ( 95.0% of the Continuous Ampere rating).
ETAP
Project: STUDY KELAYAKAN PV COCA-COLA Page: 2
12.6.0H
Location: CIBITUNG Date: 18-02-2020
Contract: 01 SN:
Engineer: ALVI HANDIKA SIREGAR Revision: Base
Study Case: LF
Filename: COCA-COLA DENGAN PV DAN PLN Config.: Normal

Branch Loading Summary Report

Transformer
CKT / Branch Cable & Reactor
Ampacity Loading Capability Loading (input) Loading (output)

ID Type (Amp) Amp % (MVA) MVA % MVA %

P.BOTOL Cable 422.40 108.94 25.79

P.KAYU Cable 422.40 108.94 25.79

P.PAGAR Cable 422.40 108.94 25.79

TRAFO 1 Transformer 60.000 11.076 18.5 10.942 18.2

* Indicates a branch with operating load exceeding the branch capability.


ETAP
Project: STUDY KELAYAKAN PV COCA-COLA Page: 3
12.6.0H
Location: CIBITUNG Date: 18-02-2020
Contract: 01 SN:
Engineer: ALVI HANDIKA SIREGAR Revision: Base
Study Case: LF
Filename: COCA-COLA DENGAN PV DAN PLN Config.: Normal

Branch Losses Summary Report

Vd
CKT / Branch From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop
ID MW Mvar MW Mvar kW kvar From To in Vmag

TRAFO 1 9.499 5.697 -9.493 -5.441 5.7 255.5 100.0 98.8 1.21

P.BOTOL 3.164 1.814 -3.151 -1.953 13.3 -139.1 98.8 98.2 0.56

P.KAYU 3.164 1.814 -3.151 -1.953 13.3 -139.1 98.8 98.2 0.56

P.PAGAR 3.164 1.814 -3.151 -1.953 13.3 -139.1 98.8 98.2 0.56

45.5 -161.8
ETAP
Project: STUDY KELAYAKAN PV COCA-COLA Page: 4
12.6.0H
Location: CIBITUNG Date: 18-02-2020
Contract: 01 SN:
Engineer: ALVI HANDIKA SIREGAR Revision: Base
Study Case: LF
Filename: COCA-COLA DENGAN PV DAN PLN Config.: Normal

Alert Summary Report

% Alert Settings
Critical Marginal
Loading
Bus 100.0 95.0

Cable 100.0 95.0

Reactor 100.0 95.0

Line 100.0 95.0

Transformer 100.0 95.0

Panel 100.0 95.0

Protective Device 100.0 95.0

Generator 100.0 95.0

Inverter/Charger 100.0 95.0

Bus Voltage
OverVoltage 105.0 102.0

UnderVoltage 95.0 98.0

Generator Excitation
OverExcited (Q Max.) 100.0 95.0

UnderExcited (Q Min.) 100.0


ETAP
Project: STUDY KELAYAKAN PV COCA-COLA Page: 5
12.6.0H
Location: CIBITUNG Date: 18-02-2020
Contract: 01 SN:
Engineer: ALVI HANDIKA SIREGAR Revision: Base
Study Case: LF
Filename: COCA-COLA DENGAN PV DAN PLN Config.: Normal

SUMMARY OF TOTAL GENERATION , LOADING & DEMAND

MW Mvar MVA % PF

Source (Swing Buses): 14.259 8.647 16.676 85.51 Lagging

Source (Non-Swing Buses): 0.000 0.000 0.000

Total Demand: 14.259 8.647 16.676 85.51 Lagging

Total Motor Load: 11.424 7.080 13.440 85.00 Lagging

Total Static Load: 2.789 1.729 3.282 85.00 Lagging

Total Constant I Load: 0.000 0.000 0.000

Total Generic Load: 0.000 0.000 0.000

Apparent Losses: 0.046 -0.162

System Mismatch: 0.000 0.000

Number of Iterations: 2