METHOD STATEMENT FOR

NSRP NEAR FIELD TEST *DOCUMENT NO :


D-P5-BV-MS-009
DCSM PROJECT
2019

Contractor’s Name : BUREAU VERITAS VIETNAM


Company’s Name : Nghi Son Refinery and Petrochemical LLC.
Plant Location : Nghi Son, Viet Nam
W/ Order No. :
Package No. :5
Scope of Work : METHOD STATEMENT FOR NEAR FIELD TEST
Discipline : DCSM
NSRP DCSM PROJECT 2019
Discipline
Receiving Date
Reviewed By
Review Date
Review Result code
Document Review codes:
1- Rejected (Revise and resubmit), 2- Comments as Noted (Revise and resubmit. Work may
proceed subject to full compliance with comments), 3- Minor Comments (Acceptable, Works
may proceed. Revise & Resubmit as “Certified Final), 4- No comments (Works may Proceed)
Returned on
Next Submission Due
Date

Rev. Date Description Prepared By Reviewed by Approved By

0 Issued For
26/09/2019
Approval
Nguyen Gia Annamalai Annamalai
Dinh Natarajan Natarajan
Project Manager

DESCRIPTION

Page 1 of 5
METHOD STATEMENT FOR

NSRP NEAR FIELD TEST *DOCUMENT NO :


D-P5-BV-MS-009
DCSM PROJECT
2019

Section Description Page No.

Scope of Work
1 3

2 Loading of NFT testing equipment 3

3 Site survey to do Near Field Testing. 3

4 Mobilization of NFT inside Working area. 3

5 Unloading of NFT Equipment transfer to the site location. 4

6 Near Field testing inspection at working on the ground level. 4

7 NFT inspection at working on Working at the height. 5

8 Loading of NFT equipment. 5

9 House Keeping 5

1. SCOPE OF WORK:

Page 2 of 5
METHOD STATEMENT FOR

NSRP NEAR FIELD TEST *DOCUMENT NO :


D-P5-BV-MS-009
DCSM PROJECT
2019

This documented is intended to detect the corossion, erosion, pitting & remaining thickness of pressure
piping, boiler or power piping and made of carbon steels using NFT Equipment with Required probes –
Portable, Dry Cloth.

2. LOADING OF NFT TESTING EQUIPMENT:

 During Loading the equipment and accessories Leather hand glove shall be worn.

 Ensure all equipment is stack away from the edge of the lorry bed and secure properly to prevent
falling.

 Ensure provide training on safe handling & manual lift of material to the workforce.

 Leather hand glove shall be worn when perform the entire work.

3. SITE SURVEY TO DO NFT TESTING:

 Ensure the proper planning.

 Ensure the isometric drawing with site layout plan is in place.

4. MOBILIZATION OF NFT TESTING EQUIPMENT INSIDE WORKING AREA:

 Valid pẻmit, are required in Client.

 All personnel shall complete Client SIC training prior to enter the site.

 All personnel to obtain security pass prior to entry.

 Ensure that all the workers had sufficient rest prior starting the task.

 Ensure authorized an trained person involved in the live plant work are allowed to enter in the
area.

 General Work Permit shall be applied by Permit requestor and approved prior to start the work.

 Ensure that the entire worker had sufficient rest prior commencing the task.

 Safety glasses, hard hat, pants, protective industrial products hand gloves, safety boots, Safety
Goggle, Ear Plug as per Client PPE safety requirement.

 Driver shall follow the Client road safety regulation 15km/h on the road in the plant area.

Page 3 of 5
METHOD STATEMENT FOR

NSRP NEAR FIELD TEST *DOCUMENT NO :


D-P5-BV-MS-009
DCSM PROJECT
2019

 Ensure pickup / van operator shall obtain valid license during the entire work.

 Metal wheels choke for vehicle in place.

 Valid Fire Extinguisher with stands. (9kg, ABC type) for vehicle in place.

 No vehicle is allowed for parking except for short delivery during working hour. Working hour.

 Workers shall bring along their individual refill water bottle.

5. UNLOADING OF NFT TESTING EQUIPMENT TRANSFER TO THE SITE LOCATION:

 During Loading / unloading the equipment and accessories Leather glove shall be worn.

 Ensure all equipment is stack away from the edge of the pickup bed and secure properly to
prevent falling.

 Leather hand glove shall be worn when perform the entire work.

6. NFT INSPECTION AT WORKING ON THE GROUND LEVEL:

 Verify the cable is in good condition.

 Insufficient lighting will be informed to the concern supervisor.

 Ensure Gas tester done before carryout job.

 During the job 4 in one gas monitor available on site.

 Ensure all the obstruction materials shall remove from site immediately.

 Ensure the area is free from all obstruction materials prior to start work.

 Remind worker report to supervisor worker not feeling well or dizzy.

 Insufficient lighting will be informed to the concern supervisor.

 Ensure the proper lighting before entering the site.

 No proper lighting, no work activities.

7. NFT TESTING INSPECTION AT WORKING ON THE (WORKING AT HEIGHT)

Page 4 of 5
METHOD STATEMENT FOR

NSRP NEAR FIELD TEST *DOCUMENT NO :


D-P5-BV-MS-009
DCSM PROJECT
2019

 Ensure workers maintain communication with each other during passing of material

 Always stay away from line of fire when passing on different level of scaffold platform.

 Use tool bag to carry the equipment by using rope.

 Work Permit & WAH Form is issued and approved by relevant parties.

 The workers must complete the WAH course before entering to the work site.

 Hook up SRL at/ above waist level.

 100% tie-off at strong anchorage point.

 Harness & SRL to be inspected with tag and check prior to use.

 Ensure proper donning of harness and SRL by workers (Buddy system checks prior to use).

8. LOADING OF NFT EQUIPMENT:

 During Loading the equipment and accessories Leather hand glove to be worn.

 Ensure all equipment is stack away from the edge of the lorry bed and secure properly to prevent
falling.

 Ensure provide training on safe handling & manual lift of material to the workforce.

 Leather hand glove shall be worn when perform the entire work.

9. HOUSEKEEPING:

 Housekeeping is a must "Before, During & End" of work day.

 Materials must never be left on the ground but stacked neatly on stillage and hard barricaded.

 Work area must be swept clean of all times.

 Work area must be swept clean of all times.

Page 5 of 5