METHOD STATEMENT FOR

NSRP VISUAL INSPECTION


*DOCUMENT NO :
DCSM PROJECT D-P5-BV-MS-013
2019

Contractor’s Name : BUREAU VERITAS VIETNAM


Company’s Name : Nghi Son Refinery and Petrochemical LLC.
Plant Location : Nghi Son, Viet Nam
W/ Order No. :
Package No. :5
Scope of Work : METHOD STATEMENT FOR REMOTE VISUAL INSPECTION
Discipline : DCSM
NSRP DCSM PROJECT 2019
Discipline
Receiving Date
Reviewed By
Review Date
Review Result code
Document Review codes:
1- Rejected (Revise and resubmit), 2- Comments as Noted (Revise and resubmit. Work
may proceed subject to full compliance with comments), 3- Minor Comments
(Acceptable, Works may proceed. Revise & Resubmit as “Certified Final), 4- No
comments (Works may Proceed)
Returned on
Next Submission Due
Date

Reviewed
Rev. Date Description Prepared By Approved By
by
0 26/09/2019 Issued For
Approval

Annamalai
Nguyen Gia Annamalai
Natarajan
Dinh Natarajan
Project Manager

Section Description Page No.

1 Scope of Work 3

Page 1 of 4
METHOD STATEMENT FOR

NSRP VISUAL INSPECTION


*DOCUMENT NO :
DCSM PROJECT D-P5-BV-MS-013
2019

2 Loading and Unloading of Equipment. 3

3 Site survey to do VI 3

4 Mobilization of the equipment outside & inside the Client location. 3

5 Unloading of Equipment and transfer to the site location. 4

6 VI at working on the ground level. 4

7 VI at working on the above ground level. (working at Height) 4

8 Housekeeping. 4

1. SCOPE OF WORK
This documented is intended to detect loss by visual examination that may be performed on any number of
items or components such as structural welds, tools, threaded connections, castings, forgings or other
machined parts and Refinery equipment

2. LOADING AND UNLOADING OF EQUIPMENT

Page 2 of 4
METHOD STATEMENT FOR

NSRP VISUAL INSPECTION


*DOCUMENT NO :
DCSM PROJECT D-P5-BV-MS-013
2019

2.1. During Loading the equipment and accessories Hand gloves to be worn.
2.2. Ensure all equipment is stack away from the edge of the lorry bed and secure properly to prevent
falling.
2.3. Ensure provide training on safe handling & manual lift of material to the workforce.
2.4. Hand gloves shall be worn when perform the entire work.

3. SITE SURVEY TO DO VISUAL INSPECTION


3.1. Ensure the proper planning.
3.2. Ensure the isometric drawing with site layout plan is in place.

4. MOBILISATION OF THE EQUIPMENT OUTSIDE & INSIDE THE CLIENT LOCATION.


4.1. Valid licenses as required by Client.
4.2. All personnel shall completed training prior to enter the site.
4.3. All workers to have DCSM sticker pasted on their safety hat.
4.4. Ensure only authorized and trained person involved in the live plant work are allowed to enter in
the area.
4.5. General Work Permit shall be applied by Permit requestor and approved prior to commencement of
work.
4.6. Pre-Job Safety Briefing shall be conducted by site supervisor in accordance to the MSRA, Daily
work plan and Journey Plan.
4.7. Ensure that all the workers had sufficient rest prior commencing the task.
4.8. Safety glasses, hard hat, long sleeve jacket pants, protective industrial products hand gloves and,
safety boots, Safety Goggle, Ear Plug as per Client PPE policy.
4.9. Before entering to Client site, check the radiation source using survey meter and ensure no leak.
4.10. Site supervisor shall ensure that there is no obstruction in mobilization route and loading and
unloading area.
4.11. Driver shall follow the Site road safety regulation 20 km/h on the road in the plant area.
4.12. Ensure pickup/van operator shall obtain valid license during the entire work.
4.13. Valid Fire Extinguisher with stands. (9kg, ABC type) for vehicle in place.
4.14. No vehicle is allowed for parking except for short delivery during working hour.
4.15. All materials, tools and equipment to be placed and stored in an orderly manner.
4.16. Drink more water when working under the hot climate.
5. UNLOADING OF EQUIPMENT AND TRANSFER TO THE SITE LOCATION.
5.1. During Loading/ unloading the equipment and accessories hand gloves to be worn.
5.2. Ensure all equipment is stack away from the edge of the pickup bed and secure properly to
prevent.
5.3. Ensure provide training on safe handling & manual lift of material to the workforce.

Page 3 of 4
METHOD STATEMENT FOR

NSRP VISUAL INSPECTION


*DOCUMENT NO :
DCSM PROJECT D-P5-BV-MS-013
2019

5.4. Leather hand glove s shall be worn when perform the entire work.
5.5. PPE must be worn at all times while performing the entire work.

6. VISUAL INSPECTION AT WORKING ON THE GROUND LEVEL


6.1. Verify the cable is in good condition.
6.2. Insufficient lighting will be informed to the concern supervisor.
6.3. Ensure Gas tester done before carryout job.
6.4. During the job 4 in one gas monitor available on site.
6.5. Ensure all the obstruction materials shall remove from site immediately.
6.6. Ensure the area is free from all obstruction materials prior to start work.
6.7. Remind worker report to supervisor worker not feeling well or dizzy.
6.8. Insufficient lighting will be informed to the concern supervisor.
6.9. Ensure the proper lighting before entering the site.
6.10. No proper lighting, no work activities.

7. VISUAL INSPECTION AT WORKING ON THE ABOVE GROUND LEVEL (WORKING AT HEIGHT)


7.1. Ensure workers maintain communication with each other during passing of material
7.2. Always stay away from line of fire when passing on different level of scaffold platform.
7.3. Use tool bag to carry the equipment by using rope.
7.4. General Work Permit Form is issued and approved by relevant parties.
7.5. The workers must complete the course before entering to the work site.
7.6. Hook up SRL at/ above waist level.
7.7. 100% tie-off at strong anchorage point.
7.8. Harness & SRL to be inspected with tag and check prior to use.

8. HOUSEKEEPING
8.1. Housekeeping is a must "Before, During & End" of work day.
8.2. Materials must never be left on the ground but stacked neatly on stillage and hard barricaded.
8.3. Work area must be swept clean of all times.