Professional Documents
Culture Documents
S1 2018 364749 Complete
S1 2018 364749 Complete
Author:
ABDURROHMAN
14/364749/TK/42002
ii
DECLARATION
I hereby declare that there is no work attached in this final project ever
submitted to earn a degree at a University, also there is no work or opinion ever
written or published by another person, unless is cited and mentioned in the
bibliography.
Abdurrohman
iii
ACKNOWLEDGEMENT
For the ancestors who paved the path before me upon whose
shoulders I stand. This is also dedicated to my family and the
many friends who supported me on this journey. Thank you.
“Jalesveva Jayamahe!”
In the ocean we triumph!
iv
PREFACE
First of all, the author wishes to express his deepest gratitude to God for His
blessing and guidance which has led the author to finish this Final Project entitled
“Designَ ofَ Coalَ Unloadingَ Portَ (Caseَ Study:َ Coalَ Firedَ Steamَ Power Plant of
Bangka-1A,َ Bangkaَ Belitung)”. This Final Project is submitted in partial
fulfillment of the requirements to achieve Bachelor’s Degree in Civil Engineering
at Department of Civil and Environmental Engineering, Faculty of Engineering,
Universitas Gadjah Mada.
There are many words to express my gratitude to all parties who were
involved in this Final Project, Prof. Dr. Ir. Bambang Triatmodjo, CES., DEA. for
his supervision and guidance as my Final Project supervisor, Prof. Ir. Radianta
Triatmadja, Ph.D. and Kartika Nur Rahma Putri, S.T., M.T. for their positive
advices as my Final Project examiners. My sincere thank also goes to Prof. Ir. Joko
Sujono, M.Eng., Ph.D as the Head of Civil and Environmental Engineering
Department, also Prof. Dr. Ir. Sunjoto, Dip.HE., and Ir. Rachmad Jayadi, M.Eng.,
Ph.D as my student advisor.
Furthermore, the author is truly thankful for the presence of Regina Betalia,
Hasta Agsoinna Alhaqqi, and Rizaldi Wisnu Nugroho as my Final Project partners
who have shared ideas and spirits. My special thanks to Ihza Aulia Imawan, Wahyu
Dwiyantoro, Farah Amrina, Helmi Zakaria, Yesinia Nur Alvin, Nur Muhammad
Naufaldo, Fahmi Arasyi M., Shintawati Setyo M., Rizki Prana A, Vina Verisya,
and Genta Auni A. as my mentors who shared knowledges for my Final Project.
iii
who have been the best partners through all the ups and downs of my college life
especially during my final project period.
Last but not least, I would like to thank Tedjo Kusumo Yohanes Adi for his
guidance during my college life, my parents for their encouragement and endless
prayers, and my siblings for their generosity to share thoughts and ideas.
Finally, I truthfully hope that this Final Project will bring utmost advantages
for the readers and all students of Civil and Environmental Engineering Department
Universitas Gadjah Mada in particular. Although this Final Project is still far from
perfect, the author welcomes any critics and suggestions in relation to this Final
Project Report.
Abdurrohman
iv
TABLE OF CONTENTS
v
CHAPTER 3 THEORITICAL BASIS ..................................................................... 17
3.1 Jetty Design .............................................................................................. 17
3.1.1 Astronomical tides ............................................................................. 17
3.1.2 Berthing force ................................................................................... 22
3.1.3 Mooring force ................................................................................... 22
3.1.4 Current force ..................................................................................... 25
3.1.5 Vessel characteristics ......................................................................... 27
3.1.6 Elevation of jetty ............................................................................... 28
3.2 Fender Design........................................................................................... 29
3.2.1 Approach velocity.............................................................................. 29
3.2.2 Berthing energy ................................................................................. 30
3.2.3 Fender selection ................................................................................. 34
3.2.4 Fender pitch ...................................................................................... 39
3.3 Approach Channel Design ......................................................................... 40
3.3.1 Channel depth ................................................................................... 40
3.3.2 Channel width ................................................................................... 40
3.4 Basin Design ............................................................................................ 42
3.4.1 Turning basin .................................................................................... 42
3.4.2 Basin depth ....................................................................................... 43
3.4.3 Dredged area ..................................................................................... 43
3.5 Load and Load Combinations .................................................................... 43
3.5.1 Load combinations............................................................................. 44
3.5.2 Dead load .......................................................................................... 45
3.5.3 Live load ........................................................................................... 45
3.6 Design Earthquake Load............................................................................ 45
3.6.1 Occupancy importance factor and risk category ................................... 45
3.6.2 Site classification ............................................................................... 47
3.6.3 Design response spectrum .................................................................. 48
3.6.4 Equivalent lateral force procedure ....................................................... 51
3.7 Pile Foundation Design ............................................................................. 54
3.7.1 Standard penetration test .................................................................... 54
3.7.2 Pile load capacity ............................................................................... 56
vi
3.7.3 Lateral load capacity .......................................................................... 58
3.7.4 Lateral deflection ............................................................................... 60
3.7.5 Critical axial load .............................................................................. 61
3.7.6 Inclined pile foundation...................................................................... 63
3.7.7 Modulus of subgrade reaction ............................................................. 65
vii
4.7.7 Load combinations............................................................................. 85
viii
BIBLIOGRAPHY ................................................................................................. 122
APPENDIX........................................................................................................... 126
ix
LIST OF TABLES
xi
LIST OF FIGURES
xiv
ABSTRACT
Bangka-1A Coal Fired Steam Power Plant is using coal fuel to generate electrical power and having
installed capacity of 2 × 50 MW. Raw coal used in electricity generation is produced from coal
mines and transported by coal barges through river or sea. A port is needed to unload the coal shipped
by coal barges and then conveyed to the coal yard. The port shall be able to accommodate a coal
barge with a capacity of 10,000 DWT.
This final project is to design coal unloading port of Bangka-1A Coal Fired Steam Power Plant. The
design includes the waterway and basin, the mooring and berthing facilities, and the foundations to
support the considered loads for each structure. The design methods started with data analysis
including topography and bathymetry maps, meteorological and hydro oceanographic data, as well
as seismic and geotechnical data. The axial load capacity of the pile was calculated using Meyerhof
(1976) while the lateral load capacity was calculated using Broms (1964) method. The loading and
structural analysis were performed using SAP2000.
According to astronomical tides, the jetty and mooring dolphin crowns are set at +3.00 mMSL.
Based on the size of the coal barge, the approach channel is designed with a depth of 6.4 m and a
width of 125 m. The port basin has bed elevation of -7.3 mMSL and turning basin with a diameter
of 151 m. SH 1000 V-fender type is used to absorb the berthing energy. Steel pipe pile foundations
with a diameter of 800 mm and a thickness of 25 mm driven to an elevation of -31.3 mMSL are used
as foundations of the structure including jetty head and mooring dolphins and safe to accommodate
the considered loads.
xv
INTISARI
Pembangkit Listrik Tenaga Uap (PLTU) Bangka-1A menggunakan bahan bakar batubara untuk
membangkitkan tenaga listrik dan memiliki kapasitas terpasang sebesar 2 × 50 MW. Batubara yang
digunakan untuk membangkitkan listrik dihasilkan dari tambang batubara dan diangkut
mengunakan tongkang batubara melalui sungai maupun laut. Pelabuhan dibutuhkan untuk
membongkar muatan batubara yang diangkut oleh tongkang dan kemudian dipindahkan ke lapangan
penumpukan batubara. Pelabuhan dirancang untuk dapat melayani kapal tongkang batubara dengan
kapasitas 10.000 DWT.
Tugas akhir ini bertujuan untuk merancang pelabuhan bongkar batubara untuk PLTU Bangka-1A.
Perancangan meliputi kolam pelabuhan dan alur pelayaran, fasilitas sandar dan tambat, serta fondasi
untuk menahan beban yang diperhitungkan pada masing-masing struktur. Metode perancangan
dimulai dengan melakukan analisis data seperti peta topografi dan batimetri, data meteorologi dan
hidro oceanografi, serta data seismik dan geoteknik. Kapasitas dukung aksial tiang dihitung
menggunakan metode Meyerhof (1976), sedangkan kapasitas dukung lateral tiang dihitung
menggunakan metode Broms (1964). Pembebanan dan analisis struktur dilakukan dengan
menggunakan SAP2000.
Berdasarkan pasang surut air laut, jetty dan mooring dolphin dirancang dengan elevasi puncak +3,00
mMSL. Berdasarkan ukuran tongkang batubara, alur pelayaran dirancang dengan kedalaman 6,4 m
dan lebar 125 m. kolam pelabuhan memiliki elevasi dasar -7,3 mMSL dan kolam putar dengan
diameter sebesar 151 m. Fender tipe V SH 1000 digunakan untuk menyerap energi benturan kapal.
Fondasi tiang pipa baja dengan diameter 800 mm dan tebal 25 mm yang dipancang hingga elevasi
-31,3 mMSL digunakan sebagai fondasi struktur jetty head dan mooring dolphin dan aman untuk
menahan beban yang diperhitungkan.
xvi
CHAPTER 1
INTRODUCTION
1.1 Background
Energy plays important role in supporting both national and regional development,
especially for the industrial sector. Energy development is focused on providing
sufficient energy supply at an affordable price. Along with the regional
development growth, especially in industrial sector, electricity demand will
continue to rise. Moreover, within the next few years, the development of
communities from rural to urban will stimulate new demand of electricity.
Furthermore, improvement of democratic economy development will also increase
the demand in rural areas.
Bangka Belitung is one of the provinces that will become one of the regions
experiencing the growth of energy due to the new industry and tourism. The growth
of electrical energy must be balanced with the growth of new power plants in order
to maintain the stability of energy supply and demand in Bangka.
Answering the short-term energy crisis as well as reducing diesel consumption due
to Diesel Power Plant (PLTD) and concerning growth of electricity demand, PLN
intends to build a Steam Power Plant (PLTU). One of the proposed power plants is
PLTU Bangka-1A which is located at Air Anyir, Bangka Island, Bangka Belitung.
This power plant lays at coordinate 2°4'50.14"S and 106°9'4.76"E. Construction of
this plant in the future will replace the number of power plants that still use diesel
fuel in Bangka Belitung.
Bangka-1A Power Plant is using coal fuel to generate electricity power and having
installed capacity of 2 x 50 MW. Raw coal used in electricity generation is
produced from coal mines and transported by coal barges through river or sea. A
port is needed to unload the coal shipped by coal barges and then conveyed to the
coal yard. The port shall be able to accommodate a coal barge with a capacity of
10,000 DWT.
1
2
Coal unloading port should be designed so that the coal barge can unload the coal
safely and quickly. The design includes approach channel, port basin, mooring and
berthing facilities, jetty platform, and foundations. Jetty shall be designed
considering the loads applied to the structure and be able to support the loads.
Two units of fixed grab crane with an average rate capacity of 600 tons/hour for
each crane will be installed to serve 10,000 DWT coal barge. Each grab crane will
be positioned at the both end of the jetty assisted by hopper on the jetty. The
dimension of the jetty is influenced by operation and maintenance facilities built on
the jetty. Belt conveyor system shall be established to transport the coal from jetty
to coal storage area.
11. The inertial force of the mass of the displaced water due to earthquake is not
considered.
2.1 Ports
A port is a sheltered harbor where marine terminal facilities are provided, consisting
of piers or wharves at which ships berth while loading or unloading cargo, transit
sheds and other storage areas where ships may discharge incoming cargo, and
warehouses where goods may be storage for longer periods while awaiting
distribution or sailing (Quinn, 1972).
In terms of operation, two types of ports are general ports and specific ports. In
terms of business, there are enterprise ports and non-enterprise ports. For national
and international trade purposes, there are ocean ports and inland-waterway ports.
In terms of utilization, there are six types of ports which are fishing ports, oil ports,
cargo ports, passenger ports, mixed ports, and military ports. Three types of ports
related to geographic locations are natural ports, artificial ports, and semi-natural
ports.
1. General cargo includes item that are shipped as units, like automobiles and
machinery, and materials in any kind of package, like bales, bags, barrels,
or boxes.
2. Bulk cargo includes free-flowing dry materials like grain, ore, portland
cement, sugar, sand, and coal, and liquids like water, oil, and petroleum
products.
3. Container is a large metal box as package used for shipping goods.
Containers have standard sizes as follows:
5
6
2.1.1 Docks
A dock is a general term used to describe a marine structure for the mooring or
tying up of vessels, for loading and unloading cargo, or for embarking and
disembarking passengers. The factors to determine the type of dock to be
constructed are the size of ships to use the dock, the direction of waves and wind,
soil conditions, particularly if dredging is to be considered, and last but of
considerable importance – the determination of the most economical type of
construction (Quinn, 1972).
Docks can differ into three types which are wharves, piers, and jetties as shown in
Figure 2.1.
A wharf is a dock which parallels the shore and generally contiguous with the shore.
A pier is a dock which is located on the shore and projected out from the shore
7
Fenders are made of elastic materials such as wood or rubber. A wood fender is
usually a timber fastened to the face of the dock or a wood driven pile. Nowadays
wood fenders are high-priced and causing environmental problems due to logging.
Rubber fenders which are manufactured by many factories are the most widely used
due to their performance and they are available on the market in many types.
1. Fenders which are installed at the dock structure, can be divided into
buckling fender, like V-type fender, A-type fender, and cell-type fender, and
non-buckling fender, like rubber-tired wheel fender and cylindrical-type
fender.
2. Fenders which are floating between the ship and the dock, like pneumatic
fender (Triatmodjo, 2010)
8
2.1.3 Moorings
A mooring is a construction that is used for following purposes:
A mooring may be located at shore (dock) and in the water. According to the
construction types, moorings can be divided into three types as follows:
1. Mooring fittings
2. Mooring buoys
3. Dolphins
a. Mooring fittings
A berthing ship will tie up to a dock with bow and stern lines, spring and breast
lines. Figure 2.2 shows the method of tying up ship to the dock. These lines
will be fastened to mooring fittings known as bollard, single or double, which
are located along the face of the dock. Larger fittings called corner mooring
posts are sometimes located at the outshore corners of a pier or at the ends of a
wharf (Quinn, 1972).
Bollards are used for tying up ship to the dock on normal weather conditions.
Corner mooring posts are not only used for tying up ship to the dock on normal
and stormy weather conditions, but also used principally while bringing the
ship into the dock or while it warps around the corner of the pier or turning
dolphin (Triatmodjo, 2010).
b. Mooring buoys
Mooring buoys are located at a port basin or offshore. The ships which will load
and unload the cargo cannot always directly berth to the dock due to operation
and maintenance of the dock. Therefore, the ships must wait outside the dock
and idle. If the ships are outside the breakwater protection, they can anchor their
own anchors.
However, the waves outside the breakwater protection are not always calm thus
the ships are recommended anchoring their anchors inside the breakwater
protection. Since the limited area of breakwater protection, the ships anchoring
their own anchors can interfere the other ships due to the 360-degree-rotary
motion of the ships with the result that they require a large area. To reduce the
rotary movement of the ships, several mooring buoys are required.
Besides as a tying up of vessels, a mooring buoy can be used to assist the turning
of vessels. The turning vessels can endanger the berthing vessel in narrow areas.
Therefore, some mooring buoys are installed between two piers to assist the
turning of vessels and reduce undesired risks. These mooring buoys also can be
used to assist the breaking of vessels. Figure 2.3 shows the function of mooring
buoys for turning the vessels.
10
c. Dolphins
A dolphin is a construction which is used as mooring and berthing facilities of
vessels. Jetty which projects into the water that is used for docking tankers or
coal barges is equipped with dolphins. After berthing, vessels or barges are
moored at the dolphins. Dolphins are usually used at bulk cargo shipping
terminals for the loading and/or unloading of bulk cargo. Dolphins are designed
principally for the horizontal loads of impact and/or wind and current forces
from a ship when it is docking and during the time that it is moored (Quinn,
1972).
Dolphins are divided into two types which are breasting dolphins and mooring
dolphins. Breasting dolphins are larger than mooring dolphins because the
breasting dolphins are designed for the horizontal loads of impact from berthing
ships and tractive forces from the ships due to wind, current, and waves.
Breasting dolphins are equipped with fenders to hold the ships off the dock, and
mooring posts to fasten the mooring lines, assist the moving of the ships, and
hold the tractive force from moored ships.
11
Mooring dolphins are not used to hold the horizontal loads of impact from
berthing ships, they are only used as mooring facilities. Mooring dolphins are
located around theَjettyَformingَanَangleَofَaboutَ45˚َtoَbow and stern lines.
Mooring dolphins are also equipped with mooring posts. Figure 2.4 shows
breasting dolphins and mooring dolphins.
1. An outer channel in open water and exposed to waves that can produce
significant vertical ship motions of heave, pitch, and roll.
2. An inner channel that lies in relatively sheltered waters and is not subject to
wave action of any significance to large ships.
The channel normally terminates at its inner end in a maneuvering area (turning
and/or berthing area) which allows stopping, turning, and berthing maneuvers to be
undertaken (PIANC, 2014).
12
The channel is a feature of waterway that has a width and depth that is sufficient to
allow safe passage of the design ships. It might be dredged or may be naturally
occurring. The fairway is defined as the wider navigable waterway for all vessels
and can be marked with buoys to indicate the limits of safe navigation. The fairway
markers may be positioned to allow the passage of smaller vessels on either side of
the dredged or design ship channel. In some cases, both the deep-water channel and
the outer lanes for smaller vessels may be marked (PIANC, 2014). Figure 2.5
shows the definition of channel and fairway.
If terminals are located along the boundary of a channel or river, the width of the
channel or river may need to be widened to allow an appropriately sized turning
area. When using such a turning area, other marine traffic will be prevented from
13
using the channel which may cause additional waiting times. This could be avoided
by placing the turning area outside the channel section, where possible, or through
traffic management (PIANC, 2014). Figure 2.6 shows the layout of approach
channel with turning basin.
1. Free-flowing dry materials including mining products such as coal, iron ore,
bauxite, and agricultural products such as grain, sugar, flour, etc.
2. Liquids which are shipped by tanker such as petroleum, palm oil, liquid
chemicals, etc.
A bulk cargo shipping terminal is usually designed for a single function, such as
loading grain or unloading ore. A bulk cargo shipping terminal must be equipped
with storage facilities and loading and/or unloading facilities depending on the bulk
cargo which is handled.
The type of storage facilities varies according to the shipping requirements and the
nature of the material. They may take the form of extensive railroad yards for
storing loaded cars, tanks for liquids, silos or warehouses for material requiring
protection from weather, or open ground storage for nonperishable materials, like
crushed stone, ore, and coal (Quinn, 1972).
Belt conveyors are the most versatile for rapid movement of a wide variety of
powdered, granular, and lumpy materials. They can carry large quantities for long
distances,َ horizontallyَ orَ upَ andَ downَ slopesَ ofَ 15˚َ toَ 20˚.َ Withَ appropriateَ
auxiliary equipment, they can be loaded or discharged at their terminals or at
intermediate points. They are used to move material into and out of storage and into
theَship’sَholds (Quinn, 1972).
Buckets are used to unload bulk materials. The clamshell bucket is the most used
piece of equipment for high-speed unloading of bulk cargo. The tower may be
stationary or travelling. The travelling type is a timesaver because it can be moved
from hatch to hatch faster than the ship can be move to a new position in front of a
fixed tower (Quinn, 1972).
is one of fossil fueled power plant that uses heat energy generated from burning
coal to produce electrical energy. The coal-fired steam power plant is the most
common type of thermal power station widely used around the world. Figure 2.7
is an overview of coal-fired steam power plant.
The raw coal used in electricity generation is produced from coal mines and
transported by barges or bulk cargo ships trough river or sea. A coal-fired power
plant is usually situated along a river or on the coast and has its own jetty for coal
unloading facility. The unloaded raw coal then conveyed to the stockpile commonly
known as coal yard. The coal received may vary in sizes and sometimes it must be
crushed first into similar sizes then sent by belt conveyor to a storage pile. The
system boundary of the electricity coal supply chain is defined as the system starts
with the mining process, coal transportation process, and coal burning process
(Wang & Mu, 2014). Figure 2.8 shows the system boundary of the electricity coal
supply chain.
16
Design of jetty requires data of bathymetry, tides, wind, current, and forces acting
on the jetty structure. Forces acting on the jetty structure include vertical loads due
to self-weight of the jetty and the weight of coal unloader, wind load, current force,
earthquake load, berthing force, and mooring force due to wind and current.
17
18
High tide and low tide occur once daily, but sometimes high tide and low
tide occur twice daily with inequalities in tidal periods and amplitudes.
The fluctuation of sea water level due to astronomical tides can be modeled with
the function of time in accordance with Equation (3.1).
𝑛 𝑛
ℎ𝑡𝑖 = 𝑍0 + ∑ 𝐴𝑛 cos(𝜔
̅𝑛 𝑡𝑖 ) − ∑ 𝐵𝑛 sin(𝜔
̅𝑛 𝑡𝑖 ) (3.1)
1 1
where:
2𝜋
𝜔
̅𝑛 = (3.2)
𝑇𝑛
The tide data can be obtained from tidal observation using tide gauge. the tide data
represent the relationship between water elevation and time. The values of 𝐴𝑛 and
𝐵𝑛 for each tidal constituent can be determined from the tide data in accordance
with Equation (3.3).
𝑍0
𝐴1
ℎ𝑡1 1 cos(𝜔
̅1 𝑡1 ) − sin(𝜔
̅1 𝑡1 ) ⋯ cos(𝜔
̅9 𝑡1 ) − sin(𝜔
̅ 9 𝑡1 )
𝐵
[ ⋯ ] = [1 ⋯ ⋯ ⋯ ⋯ ⋯ ] 1 (3.3)
⋯
ℎ𝑡𝑥 1 cos(𝜔
̅1 𝑡𝑥 ) − sin(𝜔
̅1 𝑡𝑥 ) ⋯ cos(𝜔
̅9 𝑡𝑥 ) −sin(𝜔̅9 𝑡𝑥 )
𝐴9
[𝐵9 ]
𝐻𝑛 = √𝐴𝑛 2 + 𝐵𝑛 2 (3.4)
The rise and fall of sea water level can be estimated in accordance with Equation
(3.1). The values of 𝐴𝑛 and 𝐵𝑛 shall be determined in accordance with Equation
(3.6) and Equation (3.7).
𝐴𝑛 = 𝐻𝑛 cos 𝑔𝑛 (3.6)
20
𝐵𝑛 = 𝐻𝑛 sin 𝑔𝑛 (3.7)
where:
ℎ𝑡𝑖 = water elevation at i-time
𝑍0 = average water level
𝑇𝑛 = period of tidal constituent
𝜔
̅𝑛 = angular velocity of tidal constituent
𝑡𝑖 = time
𝐻𝑛 = amplitude of tidal constituent
𝑔𝑛 = phase of tidal constituent
The definitions for the representative type of water level are as follows:
The lowest water level occurring in the period from 2 days before to 4 days
after the day of lunar syzygy.
8. Lowest Astronomical Tide (LAT)
The lowest level which can be predicted to occur under average
meteorological conditions.
𝐻 = 𝑍0 + 𝑀2 + 𝑆2 + 𝐾2 + 𝐾1 + 𝑂1 + 𝑃1 + 𝑁2 (3.8)
𝐻 = 𝑍0 + 𝑀2 + 𝑆2 + 𝐾2 + 𝐾1 + 𝑂1 + 𝑃1 (3.9)
𝐻 = 𝑍0 + 𝑀2 + 𝐾1 + 𝑂1 (3.10)
𝐻 = 𝑍0 (3.11)
𝐻 = 𝑍0 − (𝑀2 + 𝐾1 + 𝑂1 ) (3.12)
𝐻 = 𝑍0 − (𝑀2 + 𝑆2 + 𝐾1 + 𝑂1 ) (3.13)
𝐻 = 𝑍0 − (𝑀2 + 𝑆2 + 𝐾2 + 𝐾1 + 𝑂1 + 𝑃1 ) (3.14)
𝐻 = 𝑍0 − (𝑀2 + 𝑆2 + 𝐾2 + 𝐾1 + 𝑂1 + 𝑃1 + 𝑁2 ) (3.15)
Formzahl Number (𝐹𝑧 ) is used to classify the type of tide based on the ratio of
diurnal amplitudes and semidiurnal amplitudes components. Formzahl Number
shall be determined in accordance with Equation (3.16).
22
𝐾1 + 𝑂1 (3.16)
𝐹𝑧 =
𝑀2 + 𝑆2
where:
𝐹𝑧 < 0.25 for semidiurnal tide
0.25 < 𝐹𝑧 < 1.5 for mixed predominantly semidiurnal tide
1.5 < 𝐹𝑧 < 3.0 for mixed predominantly diurnal tide
𝐹𝑧 > 3.0 for diurnal tide
loading or unloading process. The tractive forces of the ship applied to the mooring
fittings due to wind and current are known as mooring forces.
𝑅𝑤 = 0.42𝑄𝑎 𝐴𝑤 (3.17)
2) Longitudinalَforceَdueَtoَwindَgustsَfromَsternَdirectionَ(αَ=َ180˚)
𝑅𝑤 = 0.5𝑄𝑎 𝐴𝑤 (3.18)
3) Lateralَforceَdueَtoَwindَgustsَfromَbeamَdirectionَ(αَ=َ90˚)
𝑅𝑤 = 1.1𝑄𝑎 𝐴𝑤 (3.19)
and
𝑄𝑎 = 0.063𝑉 2 (3.20)
where:
𝑅𝑤 = force due to wind (kg)
𝑄𝑎 = wind pressure (kg/m2)
𝑉 = wind velocity (m/s)
𝐴𝑤 = projected area of hull above water as viewed from the wind direction (m2)
𝑉𝑐 2 (3.21)
𝑅𝑎 = 𝐶𝑐 𝛾𝑤 𝐴𝑐
2𝑔
where:
𝑅𝑎 = force due to current (kg)
𝐴𝑐 = projected area of submerged hull viewed from the current direction (m2)
𝛾𝑤 = density of fluid (kg/m3)
𝑉𝑐 = current velocity (m/s)
𝐶𝑐 = current pressure coefficient
The value of 𝐶𝑐 which is according to the shape of the ship and the depth of
water in front of the moorings, may be determined in accordance with following
values.
The values of 𝐶𝑐 for calculating the longitudinal current force vary from 0.2 for
the deep water and 0.6 for the ratio between water depth and ship draft is
approximately equal to 1.
The fluid forces due to current acting on submerged body of structure are divided
into the drag force acting in the direction of the current and lift force acting in the
direction perpendicular to the current.
The drag force caused by the current shall be determined in accordance with
Equation (3.22).
1 (3.22)
𝐹𝐷 = 𝐶 𝜌 𝐴𝑈2
2 𝐷 0
where:
𝐹𝐷 = drag force acting on the object in the direction of the current (kN)
26
𝐶𝐷 = drag coefficient
𝜌0 = density of water (ton/m3)
𝐴 = projected area of the object in the direction of the current (m 2)
𝑈 = flow velocity (m/s)
Circular cylinder
Dℓ 1.0َ(ℓ>D)
(rough surface)
a/bَ=َ1َ→َ1.12
a/bَ=َ2َ→َ1.15
a/bَ=َ4َ→َ1.19
Flat plate ab
a/bَ=َ10َ→َ1.29
a/bَ=َ18َ→َ1.40
a/bَ=َ∞َ→َ2.01
Cube D2 1.3~1.6
𝐷𝑇 = 𝛼 (𝐷𝑊𝑇)𝛽 (3.23)
Lateral and longitudinal projected area of hull, and surface area of submerged hull
can be determined in accordance with Equation (3.24).
𝐴 = 𝛼 (𝐷𝑊𝑇)𝛽 (3.24)
𝐸𝑁 = 0.5𝑀𝐷 𝑉𝐵 2 𝐶𝑀 𝐶𝐸 𝐶𝐶 𝐶𝑆 (3.27)
where:
𝐸𝑁 = normal berthing energy to be absorbed by the fender (kNm)
𝑀𝐷 = displacement of vessel (ton)
𝑉𝐵 = approach velocity component perpendicular to the berthing line (m/s)
𝐶𝑀 = added mass coefficient
𝐶𝐸 = eccentricity coefficient
𝐶𝐶 = berth configuration coefficient
𝐶𝑆 = softness coefficient
31
Abnormal impacts arise when the normal energy is exceeded. Causes may include
human error, malfunctions, exceptional weather conditions or combination of these
factors. The abnormal energy to be absorbed by the fender can be calculated in
accordance with Equation (3.28).
𝐸𝐴 = 𝐹𝑆 𝐸𝑁 (3.28)
where:
𝐸𝐴 = abnormal berthing energy to be absorbed by the fender (kNm)
𝐹𝑆 = safety factor for abnormal berthing
PIANC recommends that the factor of abnormal impact when derived should not
be less than 1.1 nor more than 2.0 unless exception circumstance prevail. Table 3.6
shows the factors of safety recommended by PIANC.
The value of added mass coefficient depends on the body of water carried along
with the ship as it moves sideways trough the water. As the ship is stopped by the
fender, the entrained water continues to push against the ship, effectively increasing
its overall mass. Ueda (1981) recommended that the value of added mass coefficient
shall be determined in accordance with Equation (3.29).
𝜋𝐷 (3.29)
𝐶𝑀 = 1 +
2𝐶𝐵 𝐵
32
where:
𝐷 = draft of vessel (m)
𝐵 = beam of vessel (m)
𝐶𝐵 = block coefficient
The block coefficient is a function of the hull shape and determined in accordance
with Equation (3.30).
𝑀𝐷 (3.30)
𝐶𝐵 =
𝐿𝐵𝑃 𝐵𝐷𝜌
where:
𝐿𝐵𝑃 = length between perpendiculars (m)
𝜌 = fluid density (ton/m3)
The eccentricity coefficient allows the energy dissipated by rotation of the ship
about its point of impact with the fenders. The correct point of impact, berthing
angle, and velocity vector angle are all important for accurate calculation of the
eccentricity coefficient. In practice, 𝐶𝐸 often varies between 0.3 and 1.0 for
different berthing cases. Figure 3.6 shows the parameters of eccentricity
coefficient. The value of eccentricity coefficient can be determined in accordance
with Equation (3.31).
𝐾 2 + 𝑅2 cos 2 ∅ (3.31)
𝐶𝐸 =
𝐾 2 + 𝑅2
where:
𝑅 = center of mass to point of impact (m)
𝐾 = radius of gyration (m)
The value of 𝑅 and 𝐾 shall be determined in accordance with Equation (3.32) and
Equation (3.33).
𝐵 2 (3.32)
√ 2
𝑅 = 𝑦 +( )
2
33
𝐿𝐵𝑃 (3.34)
𝑥+𝑦 =
2
The value of 𝑥 is according to the berthing cases. For common berthing cases, the
value of 𝑥 is determined in accordance with following equations.
a. Quarter-point berthing
𝐿𝐵𝑃 (3.35)
𝑥=
4
b. Third-point berthing
𝐿𝐵𝑃 (3.36)
𝑥=
3
c. Midships berthing
𝐿𝐵𝑃 (3.37)
𝑥=
2
Berth configuration coefficient allows the energy dissipated by the water between
hull and jetty acts as a cushion when ships berth at small angles against solid
structures. The extent to which this factor contributes depends on dock structure
design, under keel clearance, velocity angle of approach, projection of fender, and
vessel hull shape.
34
PIANC recommends the value of 𝐶𝐶 is equal to 1.0 for open structures including
berthَcorners,َberthingَanglesَmoreَthanَ5˚,َveryَlowَberthingَvelocities,َandَlarge
under keel clearance. The value of 𝐶𝐶 is equal to 0.9 for solid quay walls, berthing
anglesَlessَthanَ5˚,َand under clearance less than 15% of the vessel draught. When
the under-keel clearance has already been considered for added mass (𝐶𝑀 ), the berth
configuration coefficient 𝐶𝐶 = 1 is usually assumed. Figure 3.7 shows the type of
dock structure.
Fenders are divided into two types of fender, there are fender with type I and type
II (Versteegt, 2013). Fender of type I is buckling type fender which will exert forces
on the ship from the beginning of contact and cause the maximum reaction
compatible with the resistance of the hull. Some types of buckling fender are
circular shape of the buckling fender with panel contact, longitudinal shape of the
buckling fender with panel contact, and buckling fender with direct contact. The
35
different types of energy absorbing from fender of type I is shown in Table 3.7 and
the example of relation between kinetic energy and reaction force for fender of type
I curve is shown in Figure 3.8.
D/H
60 9
500/300
- -
Circular shape -
4660 4840
of the buckling 3200/2000
fender with D/H
56 10
panel contact 650/400
- -
-
5688 6570
3350/3000
H/L
66 9
300/600
Longitudinal - -
-
shape of the 1708 1260
1800/2000
buckling fender
with panel H/L
140 22
contact 400/500
- -
-
6900 7000
2500/4000
H/L
150 15
250/1000
- -
-
2290 940
1000/2000
H/L
Buckling 150 10
200/1000
fender with - -
-
direct contact 3400 1500
1300/3500
H/L
45 6
300/600
- -
-
646 297
1000/2000
Figure 3.8 Relation between kinetic energy and reaction force for fender of type I
(Source: Versteegt, 2013)
Fender of type II is side loaded type fender and pneumatic type fender which is used
to reduce the tension on the ropes and the movement of the ship when subjected to
wave action. The examples of type II are air block fender, pneumatic fender, foam
filled fender, and cylindrical fender. The different types of energy absorbing from
type II fender is shown in Table 3.8 and the example of relation between kinetic
energy and reaction force for type II fender curve is shown in Figure 3.9.
Figure 3.9 Relation between kinetic energy and reaction force for type II fender
(Source: Versteegt, 2013)
37
Selected type of fender must have sufficient capacity to absorb the normal and
abnormal energies of berthing ships. There are two fundamental criteria for
selection of fenders as follows:
1. The energy capacity of the fender under the worst operating conditions must be
greater than the abnormal design berthing energy.
2. The reaction force created by the fender onto the structure must be less than the
capacity limit of the structure.
There are few things that need to be reviewed and will be used as consideration in
fender selection as follows:
1. Kinetic energy that is determined in accordance with Equation (3.28)
2. Fender catalogue
3. Design deflection of fender = 45% (Triatmodjo, 2010)
Start
E100% calculation
𝐸
𝐸100% =
𝐸%
𝐸𝑓𝑒𝑛𝑑𝑒𝑟 > N
E100%
Finish
(3.38)
𝑃 ≤ 2√𝑅𝐵 2 − (𝑅𝐵 − ℎ + 𝐶 )2
where:
𝑃 = pitch of fender (m)
𝑅𝐵 = bow radius (m)
ℎ = fender projection when compressed, measure at centerline of fender (m)
𝐶 = clearance between vessel and dock (m)
1 𝐵 𝐿𝑂𝐴2 (3.39)
𝑅𝐵 = ( + )
2 2 8𝐵
where:
𝐵 = beam of vessel (m)
𝐿𝑂𝐴 = vessel length overall (m)
1. Water related factors include the reference level or datum of the selected
design water level and meteorological effects on this water level.
2. Ship related factors include static draught of the ship and the Gross
underkeel clearance (UKC). The Gross UKC is composed of six factors
including allowance for static draught uncertainties, change in water
density, ship squat and dynamic trim, dynamic heel, wave response
allowance, and Net UKC.
3. Bottom related factors include allowance for bed level uncertainties,
allowance for bottom changes between dredging, and dredging execution
tolerance.
As for small ships, when the above standard area cannot be provided due to
topographic conditions, turning basin may be reduced to the following level by
using mooring anchors, winds, or tidal currents:
1. Bow turning without assistance of tugboats, circle having a diameter of 2L
2. Bow turning using tugboats, circle having a diameter of 1.5L
43
D : dead load due to weight of the structural elements and the permanent
features on the structure
L : live load due to occupancy, including impact loads, but excluding
environmental load such as wind, rain, etc.
Lr : roof live load produced during maintenance by workers, equipment, and
materials or during the service life of the structure by movable objects
E : earthquake (seismic load)
R : rain or ice load (not including ponding)
S : snow load
W : wind load
Combination 1: 1.4D
Combination 2: 1.2D + 1.6L + 0.5(Lr or S or R)
Combination 3: 1.2D + 1.6(Lr or S or R) + (L or 0.5W)
Combination 4: 1.2D +1.0W + L + 0.5(Lr or S or R)
Combination 5: 1.2D + 1.0E + L + 0.2S
Combination 6: 0.9D + 1.0W
Combination 7: 0.9D + 1.0E
In combinations 3, 4, and 5, the load factor on L can be reduced to 0,5 if L is no
greater than 100 pounds per square foot (4.79 kN/m2), except for garages or places
of public assembly. In combinations with wind or earthquake loads, you should use
a direction that produces the worst effects.
45
2. Category II, includes all buildings and other structures except those listed in
Categories I, III, and IV, but not limited to, housings, stores, offices, markets,
apartments, trade centers, industrial buildings, manufacturing facilities, and
factories.
3. Category III, includes all buildings and other structures that represent a
substantial hazard to human life in the event of failure including, but not limited
to, cinemas, halls, stadiums, health care facilities but not having surgery or
emergency treatment facilities, day care facilities, jails and detention facilities,
power generation stations and other public utility facilities not included in
Category IV such as water and waste water treatment plants. This category also
includes buildings and other structures not included in Category IV (including,
but not limited to, facilities that manufacture, process, handle, store, use, or
dispose such substances as hazardous fuels, hazardous chemicals, hazardous
waste, or explosives) containing sufficient quantities of hazardous materials to
be dangerous to the public if released.
4. Category IV, includes all buildings and other structures designated as essential
facilities including, but not limited to, monumental buildings, schools and
educational facilities, hospitals and other health care facilities having surgery or
emergency treatment facilities, fire, rescue, ambulance, and police stations and
emergency vehicle garages, designated earthquake, hurricane, or other
emergency shelters, designated emergency preparedness, communication, and
operation centers and other facilities required for emergency response, power
generating stations and other public utility facilities required in an emergency,
and ancillary structures (including, but not limited to, communication towers,
fuel storage tanks, cooling towers, electrical substation structures, fire water
storage tanks or other structures housing or supporting water, or other fire-
suppression material or equipment) required for operation of Category IV
structures during an emergency.
47
From the risk category above, the values of occupancy importance factor (𝐼𝑒 ) are
obtained for each category. Based on SNI 1726:2012, an occupancy importance
factor (𝐼𝑒 ) should be assigned to each structure in accordance with Table 3.10.
Where:
𝑣̅𝑠 = average shear wave velocity in top 30 m
̅
𝑁 = average field standard penetration resistance for the top 30 m
̅𝑐ℎ
𝑁 = average standard penetration resistance for cohesionless soil layers for
the top 30 m
𝑠̅𝑢 = average undrained shear strength in top 30 m
𝑆𝑀𝑆 = 𝐹𝑎 𝑆𝑠 (3.41)
𝑆𝑀1 = 𝐹𝑣 𝑆1 (3.42)
Where:
𝑆𝑀𝑆 = maximum considered earthquake spectral response acceleration at short
periods
𝑆𝑀1 = maximum considered earthquake spectral response acceleration at a
period of 1-sec
𝑆𝑠 = the mapped maximum considered earthquake spectral response
acceleration at short periods
𝑆1 = the mapped maximum considered earthquake spectral response
acceleration at a period of 1-sec
𝐹𝑎 = acceleration-based site coefficient (at short periods)
𝐹𝑣 = velocity-based site coefficient (at 1-sec period)
The value of SDS and SD1 shall be determined by Equation (3.43) and Equation
(3.44) as follows:
2 (3.43)
𝑆𝐷𝑆 = 𝑆
3 𝑀𝑆
2 (3.44)
𝑆𝐷1 = 𝑆𝑀1
3
50
Where:
𝑆𝐷𝑆 = the design spectral response acceleration at short periods
𝑆𝐷1 = the design spectral response acceleration at 1-sec period
1. For periods less than 𝑇0, the design spectral response acceleration, 𝑆𝑎 , shall be
taken as given by Equation (3.45)
𝑇 (3.45)
𝑆𝑎 = 𝑆𝐷𝑆 (0.4 + 0.6 )
𝑇0
2. For periods greater than or equal to 𝑇𝑠 , the design spectral response
acceleration, 𝑆𝑎 , shall be taken as given by Equation (3.46)
𝑆𝐷1 (3.46)
𝑆𝑎 =
𝑇
Where:
𝑆𝑎 = the design spectral response acceleration
𝑇 = the fundamental period of the structure (sec)
𝑆
𝑇0 = 0.2𝑆𝐷1
𝐷𝑆
𝑆
TS = 𝑆𝐷1
𝐷𝑆
The seismic base shear (𝑉) is the main parameter defined in this procedure. The
seismic base shear shall be determined in accordance with the Equation (3.47).
𝑉 = 𝐶𝑠 𝑊 (3.47)
Where:
𝑉 = seismic base shear
𝐶𝑠 = seismic response coefficient
𝑊 = effective seismic weight
The effective seismic weight based on chapter 7.7.2 of SNI 1726:2012 shall include
the total dead load and other load mentioned below:
1. In areas used for storage, a minimum of 25% of the floor live load (floor live
load in public garage and open parking structures, also floor load in areas used
for storage which not greater than 5% of the effective seismic load, need not
be included).
2. Where an allowance for partition load is included in the floor load design, the
actual partition weight or a minimum weight of 0.48 kN/m2 of floor area,
whichever is greater.
3. Total operating weight of permanent equipment.
4. Landscape weight and other roof garden and other similar area load
The seismic response coefficient (𝐶𝑠 ) shall be determined in accordance with the
Equation (3.48).
52
𝑆𝐷𝑆
𝐶𝑠 = (3.48)
𝑅
𝐼𝑒
The value of 𝐶𝑠 calculated in accordance with the Equation (3.48) shall not be
taken greater than Equation (3.49)
𝑆𝐷1
𝐶𝑠 = (3.49)
𝑅
𝑇 (𝐼 )
𝑒
As addition, for structure located in area where the value of S1 is equal to or greater
than 0.6g, then the value of 𝐶𝑠 shall not be taken less than Equation (3.51)
0.5𝑆1
𝐶𝑠 = (3.51)
𝑅
𝐼𝑒
Where:
𝑆𝐷𝑆 = the design spectral response acceleration at short periods
𝑆𝐷1 = the design spectral response acceleration at 1-sec period
𝑆1 = the mapped maximum considered earthquake spectral response
acceleration at 1-sec period
𝑅 = the response modification factor (shown in Table 3.14)
𝐼𝑒 = the occupancy importance factor
𝑇 = the fundamental period of the structure (sec)
The value of fundamental period of the structure (𝑇), in the considered direction
shall be established using structural properties and deformational characteristics of
the resisting elements in a properly substantiated analysis. The value of
fundamental period of the structure shall not exceeded the product of the coefficient
for upper limit on calculated period and the approximate fundamental period (𝑇𝑎 ).
as an alternative to performing an analysis to determine the value of fundamental
period of the structure (𝑇), it shall be permitted to use the approximate fundamental
period (𝑇𝑎 ) calculated in accordance with the Equation (3.52).
53
𝑇𝑎 = 𝐶𝑡 ℎ𝑛𝑥 (3.52)
Where:
𝑇𝑎 = the approximate fundamental period
𝐶𝑡 , 𝑥 = the approximate period parameter
ℎ𝑛 = the height above the base to the highest level of the structure (m)
Table 3.14 Response modification factor, 𝑅 for moment resisting frame systems
Moment Resisting Frame Systems 𝑅
Special steel moment frames 8
Special steel truss moment frames 7
Intermediate steel moment frames 4.5
Ordinary steel moment frames 3.5
Special reinforced concrete moment frames 8
Intermediate reinforced concrete moment frames 5
Ordinary reinforced concrete moment frames 3
Special composite moment frames 8
Intermediate composite moment frames 5
Composite partially restrained moment frames 6
Ordinary composite moment frames 3
Special masonry moment frames 5,5
(Source: SNI 1726:2012)
The values of 𝐶𝑡 and 𝑥 are obtained from Table 3.15 based on the structure type.
Structure types listed in Table 3.15 are moment resisting frame systems in which
the frames resist 100% of the required seismic force and are not enclosed or
adjoined by more rigid components that will prevent the frames from deflecting
when subjected to seismic forces.
54
where:
𝑎 = ground acceleration (m/s2)
The N-values need to be corrected due to field procedures and overburden pressure
before they are used for foundation design. Correction of SPT value for field
55
procedures is a function of the input driving energy and its dissipation around the
sampler around the surrounding soil. The corrected SPT N-value for field
procedures shall be determined in accordance with Equation (3.53).
𝐸𝐻 𝐶𝐵 𝐶𝑆 𝐶𝑅 𝑁 (3.53)
𝑁60 =
0.6
where:
𝑁60 = corrected SPT N-value for field procedures
𝐸𝐻 = hammer efficiency (shown in Table 3.16)
𝐶𝐵 = borehole diameter correction (shown in Table 3.16)
𝐶𝑆 = sampler correction (shown in Table 3.16)
𝐶𝑅 = rod length correction (shown in Table 3.16)
𝑁 = measured SPT N-value in field
where:
𝑁60 ′ = corrected SPT N-value for field procedures and overburden pressure
𝐶𝑁 = overburden pressure correction factor
Peck et al. (1974) suggested the field SPT value are to be corrected by the correction
factor (𝐶𝑁 ) given in Equation (3.55).
20 (3.55)
𝐶𝑁 = 0.77 log ( )
𝑃0 ′
where:
𝑃0 ′ = effective overburden pressure (ton/ft2)
𝑛
′
𝑃0 = ∑ 𝛾𝑖 ℎ𝑖 (3.56)
𝑖=1
where:
𝛾𝑖 = in situ density of soil layer (kN/m3)
ℎ𝑖 = height of soil layer (m)
a. End-bearing resistance
To calculate the end-bearing resistance in accordance with depth factor,
Meyerhof (1976) suggested as follows:
1) For piles in granular soils, the unit tip bearing capacity shall be determined
in accordance with Equation (3.57).
𝐿 (3.57)
𝑓𝑏 = 40𝑁60 ′ ( ) ≤ 400𝑁60 ′
𝑑
2) For piles in cohesive soils, the unit tip bearing capacity shall be determined
in accordance with Equation (3.58).
𝐿 (3.58)
𝑓𝑏 = 40𝑁60 ′ ( ) ≤ 300𝑁60 ′
𝑑
where:
𝑓𝑏 = unit end-bearing resistance (kN/m2)
𝐿 = depth of pile penetration (m)
𝑑 = diameter of pile (m)
𝑓𝑠 = 2𝑁60 (3.59)
2) For piles in cohesive soils, the unit skin friction resistance shall be
determined in accordance with Equation (3.60).
𝑓𝑠 = 1.8𝑁60 (3.60)
where:
𝑓𝑠 = unit skin friction resistance (kN/m2)
𝑄𝑏 = 𝐴𝑏 𝑓𝑏 (3.61)
𝑄𝑠 = 𝐴𝑠 𝑓𝑠 (3.62)
𝑄𝑢 = 𝑄𝑏 + 𝑄𝑠 − 𝑊𝑝 (3.63)
where:
𝑄𝑏 = ultimate end-bearing resistance (kN)
𝐴𝑏 = area of pile end (m2)
𝑄𝑠 = ultimate skin friction resistance (kN)
𝐴𝑠 = area of pile surface (m2)
𝑄𝑢 = net ultimate load capacity (kN)
𝑊𝑝 = weight of pile (kN)
Pile needs to be classified in accordance with connection detail between the pile
and pile cap because of its effect on pile stiffness to carry lateral loads.
Therefore, piles are divided into two types including fixed head pile and free
head pile as shown in Figure 3.17. McNulty (1956) defined a fixed head pile as
a pile which has embedment length to pile cap more than 60 cm. Consequently,
a pile which has embedment length to pile cap less than 60 cm is called free
head pile.
Figure 3.17 Definition of free head pile and fixed head pile (McNulty, 1956)
(Source: Hardiyatmo, 2010)
Lateral load capacity of free head pile in granular soil can be determined by using
Broms (1964) methods as following equations.
𝜑 (3.65)
𝐾𝑝 = tan2 (45° + )
2
2𝑓 (3.66)
𝑀𝑚𝑎𝑥 = 𝐻𝑢 (𝑒 + )
3
𝐻𝑢 (3.67)
𝑓 = 0.82√
𝑑𝐾𝑝 𝛾
where:
𝐾𝑝 = coefficient of passive earth pressure
𝜑 = internal friction angle
𝑀𝑚𝑎𝑥 = maximum moment due to lateral load (kNm)
60
1/5
𝑛ℎ (3.68)
𝛼=( )
𝐸𝑝 𝐼𝑝
61
Free head pile and fixed head pile are considered as short pile if 𝛼𝐿 < 2 and as long
pile if 𝛼𝐿 > 4. The lateral deflection of long free head pile shall be determined in
accordance with Equation (3.69).
2.4𝐻 1.6𝐻𝑒
𝑦0 = + (3.69)
2/5 3/5
(𝑛ℎ )3/5(𝐸𝑝 𝐼𝑝 ) (𝑛ℎ )2/5 (𝐸𝑝 𝐼𝑝 )
where:
𝑦0 = lateral deflection of pile (m)
𝐻 = lateral load applied to pile (kN)
𝑛ℎ = coefficient of soil modulus variation (kN/m3)
𝐸𝑝 = elastic modulus of pile (kN/m2)
𝐼𝑝 = inertia moment of pile (m4)
𝑒 = height of lateral load eccentricity measured from ground surface (m)
5 𝐸𝑝 𝐼𝑝 (3.70)
𝑇= √
𝑛ℎ
𝑧𝑓 = 1.8𝑇 (3.71)
The equivalent length of pile (𝐿𝑒 ) shall be determined in accordance with Equation
(3.72).
𝐿𝑒 = 𝑒 + 𝑧𝑓 (3.72)
The critical buckling load (𝑄𝑐𝑟 ) for free head pile shall be determined in accordance
with Equation (3.73).
𝜋 2 𝐸𝑝 𝐼𝑝
𝑄𝑐𝑟 = (3.73)
4𝐿𝑒 2
Large inclination of a pile gives large lateral load resistance despite the difficult and
costly pile driving. Therefore, the commonly used inclination of pile is 1H : 12V to
5H : 12V.
The calculation of batter piles is analytically determined by assuming the pile group
as a certain static system. Piles are assumed to carry the axial loads only.
Furthermore, pile cap is considered as a very rigid structure and the soil influence
is not considered.
The calculation is started by determining the resultant force applied to the pile. The
resultant force is directed along the vertical and horizontal axes. The vertical load
which is applied to each pile shall be determined in accordance with Equation
(3.74) to Equation (3.76).
𝑉 𝑀𝑦 𝑥 𝑀𝑥 𝑦 (3.74)
𝑄𝑣 = + +
𝑛 ∑ 𝑥2 ∑ 𝑦2
𝑀𝑥 = 𝑒𝑦 𝑉 (3.75)
𝑀𝑦 = 𝑒𝑥 𝑉 (3.76)
where:
𝑄𝑣 = vertical load applied to each pile
𝑛 = amount of piles
𝑥, 𝑦 = distance of piles to x-axis and y-axis, respectively
𝑉 = total vertical loads at the center of pile group
𝑒𝑥 , 𝑒𝑦 = eccentricity to x-axis and y-axis, respectively
𝑀𝑥 , 𝑀𝑦 = moment about x-axis and y-axis, respectively
64
Each pile is assumed to carry the axial load (𝑄𝑛 ). The magnitude of axial load
applied to a single vertical pile is equal to 𝑄𝑣 . The magnitude of axial load applied
to a batter pile can be determined in accordance with Equation (3.77).
𝑄𝑣 (3.77)
𝑄𝑛 =
cos 𝜃
Where 𝜃 is the angle formed by pile and vertical axis.
The vertical load applied to a batter pile with an inclination of cot 𝜃 or 𝑚 ∶ 1, can
be determined in accordance with Equation (3.78).
√1 + 𝑚2 (3.78)
𝑄𝑛 = 𝑄𝑣
𝑚
The horizontal load applied to a batter pile with an inclination of 𝑚 can be
determined in accordance with Equation (3.79).
𝑄𝑣 𝑄𝑛
𝑄ℎ = or 𝑄ℎ = (3.79)
𝑚 √1 + 𝑚2
The value of subgrade reaction modulus (𝑘ℎ ) shall be considered for each depth of
pile in accordance with Equation (3.80).
𝑘𝑠 = 𝑘ℎ 𝐴𝑠 (3.80)
where:
𝑘𝑠 = modulus of subgrade reaction for each depth (MN/m)
𝑘ℎ = modulus of subgrade reaction (MN/m3)
𝐴𝑠 = area of pile surface (m2)
CHAPTER 4
DESIGN CRITERIA
The design of waterway and basin is to obtain the capital dredging area. Generating
3D analysis using software of SAP2000 V.14 is to perform structural analysis for
obtaining the most feasible design for the foundations to support the upper
structures due to the considered loads.
Figure 4.1 Site location of Bangka-1A Coal Fired Steam Power Plant
(Source: Site Investigation Report of PLTU Bangka-1A, 2017)
66
67
4.3 Flowchart
The procedure of design in this final project follows the flowchart shown in Figure
4.2.
Start
Literature study
Loading and No
structural analysis
using SAP2000
Yes
Conclusions and recommendations
Finish
Figure 4.3 Aerial imagery of Bangka-1A Coal Fired Steam Power Plant
(Source: Google Earth, 2018)
PGA = 0.025g
FPGA = 2.500
PGAM = 0.025g × 1.600 = 0.04g
SS (g) = 0.055
S1 (g) = 0.075
CRS = 0.976
CR1 = 0.931
4.5.3 Bollards
Tee head bollards are chosen for the design because they are the most commonly
utilized bollards with kind wrap angles and ease of release. Figure 4.10 and Table
4.8 show the tee head bollard dimensions and specifications.
Two unit of fix grab crane, two coal hoppers, and belt conveyor are provided to
assist the coal unloading process of 10,000 DWT coal barge in 16 hours with an
average rate of 625 ton per hour. Figure 4.12 shows the layout of jetty.
4.7 Loading
Jetty shall be designed considering the loads which are applied to the structure. The
loads are used to determine the minimum strength of the supporting structure. In
this final project, loads are used in designing the pile foundations to support all
loads and meet all the requirements needed in design.
𝐷𝑒𝑝𝑡ℎ
∑ = 2,188
𝑁
30 30
̅=
𝑁 = = 13.710
𝐷𝑒𝑝𝑡ℎ 2.188
∑
𝑁
According to Table 3.11, the soil properties which average field standard
penetration resistance for the top 30 m is less than 15, the site is classified as site
class E (soil).
81
According to Sub subchapter 3.6.1, the coal unloading jetty is classified as Risk
Category III which is for power generation stations and facilities that handle such
substances as hazardous fuels containing sufficient quantities of hazardous
materials to be dangerous to the public if released.
𝑆𝑠 = 0.055g
𝑆1 = 0.075g
𝐹𝑎 = 2.5 (based on Table 3.12 for site class E and SS ≤َ0.25)
𝐹𝑣 = 3.5 (based on Table 3.13 for site class E and S1 ≤َ0.1)
𝑆𝑀𝑆 = 𝐹𝑎 𝑆𝑠
= 2.5 × 0.055𝑔
= 0.138g
𝑆𝑀1 = 𝐹𝑣 𝑆1
= 3.5 × 0.075𝑔
= 0.264g
2
𝑆𝐷𝑆 = 𝑆
3 𝑀𝑆
2
= × 0.138𝑔
3
= 0.092g
2
𝑆𝐷1 = 𝑆
3 𝑀1
2
= × 0.264𝑔
3
= 0.176g
𝑆𝐷1
𝑇0 = 0.2
𝑆𝐷𝑆
82
0.176𝑔
= 0.2 ×
0.092𝑔
= 0.381 sec
𝑆𝐷1
𝑇𝑠 =
𝑆𝐷𝑆
0.176𝑔
=
0.092𝑔
= 1.905 sec
Based on Figure 3.16, Equation (3.45), and Equation (3.46), the design response
spectrum curve is as shown in Figure 4.13.
0.05
0.04
0.03
0.02
0.01
0
0 1 2 3 4 5
T (second)
The dominant direction of current at jetty area is west and east. The current hitting
the structure forms angles with the axis of structure as shown in Figure 4.18. The
current load applied to the hull as berthing force to the structure is not considered.
𝐾1 + 𝑂1 0.460 + 0.343
𝐹𝑍 = = = 7.90
𝑀2 + 𝑆2 0.041 + 0.060
88
89
The design water levels in accordance with Equation (3.8) to Equation (3.15) are
as follows:
a. Forward movement
The forward movement of ship is mostly influenced by the current force due to
high tide. The mooring force forward is determined in accordance with
Equation (3.21) as follows:
b. Backward movement
The backward movement of ship is mostly influenced by the current force due
to low tide. The mooring force backward is equal to the mooring force forward
in opposite direction.
c. Sideward movement
The sideward movement of ship is mostly influenced by the wind force due to
the highest wind velocity blows from northeast. The lateral projected area of
hull is calculated in accordance with Equation (3.24) as follows:
d. Bollard selection
Based on Table 3.2, bollards are designed to resist tractive force of 300 kN for
10,000 DWT ship and the interval between bollards is 15 m. According to Table
4.8, the dimensions of selected bollard are shown in Figure 5.1.
𝐹𝐷 1 2
= 2 𝐶𝐷 𝜌0 𝐴𝑈
𝑙 𝑙
1
𝐹𝐷 /𝑙 = 𝐶𝐷 𝜌0 𝑑𝑈2
2
1
(𝐹𝐷 /𝑙)𝐷=0 = × 1 × 1 × 0.8 × 0.762
2
= 0.231 kN/m
1
(𝐹𝐷 /𝑙)𝐷=1 = × 1 × 1 × 0.8 × 0.7472
2
= 0.223 kN/m
1
(𝐹𝐷 /𝑙)𝐷=2 = × 1 × 1 × 0.8 × 0.692
2
= 0.190 kN/m
1
(𝐹𝐷 /𝑙)𝐷=3 = × 1 × 1 × 0.8 × 0.7282
2
= 0.212 kN/m
The coal barge has a draft of 5.4 m based on Table 4.1, thus the water depth is more
than 4.5 m. According to Table 3.5, the crown of jetty shall be set 1.0 to 2.0 m
above the highest astronomical tide (HAT). The elevation of HAT is +1.304 mMSL
based on Table 5.2. Thus, the elevation of jetty crown is taken as +3.00 mMSL.
The elevation of channel bottom is designed for two conditions. The first condition
is when the coal barges can berth every time whether at high tide or low tide. The
second condition is when the coal barge can only berth during high tide.
The elevation of channel bottom for the first condition is calculated as follows:
The elevation of channel bottom for the second condition is calculated as follows:
The approach channel is designed as one-way channel since the coal is transported
infrequently. The channel width based on Figure 3.13 is as follows:
Dredging is required for approach channel at the first condition as shown in Figure
5.3 seeing that the elevation of riverbed does not satisfy the design depth of channel.
96
Figure 5.4 shows that the riverbed has enough elevation for the design depth of
channel with the result that dredging is not required.
Theَdepthَofَbasinَisَequalَtoَ1.1َtimesَofَship’sَdraftَwhenَfullyَloaded.َTheَbedَ
elevation of basin is calculated in accordance with Equation (3.40) as follows:
𝐸𝑙𝑏𝑎𝑠𝑖𝑛 = 𝐸𝑙𝐿𝐿𝑊𝐿 − 1.1𝑑𝑟𝑎𝑓𝑡𝑚𝑎𝑥
= −1.292 − 1.1 × 5.4
= -7.232َmَ≈َ-7.3 m
97
The elevation of riverbed does not satisfy the design basin depth as shown in Figure
5.6 with the result that it requires dredging.
𝐿𝑂𝐴 = 100.7 m
Length of dredged area > 1.25𝐿𝑂𝐴
> 1.25 × 100.7
> 125.875 m
𝐵 = 25.5 m
Length of dredged area = 𝐵 + 𝐿𝑂𝐴 + 𝐵
= 25.5 + 100.7 + 25.5
= 151.7َ≈َ150َm
150 m > 125.875 m (OK)
Based on Figure 3.15, the required dimensions of dredged area in front of jetty are
shown in Figure 5.7.
The capital dredging includes the dredging of basin and approach channel. The
required area of capital dredging when the coal barge can berth every time is shown
in Figure 5.8. The required area of capital dredging when the coal barge can only
berth during high tide is shown in Figure 5.9.
99
The value of added mass coefficient (𝐶𝑀 ) is calculated in accordance with Equation
(3.29) as follows:
𝜋𝐷
𝐶𝑀 = 1 +
2𝐶𝐵 𝐵
𝜋 × 5,4
= 1+
2 × 0.941 × 25.5
= 1.353
𝐿𝐵𝑃
𝑥 =
4
94.1
=
4
= 23.525 m
𝐿𝐵𝑃
𝑦 = −𝑥
2
94.1
= − 23.525
2
= 23.525 m
𝐾 = (0.19𝐶𝐵 + 0.11)𝐿𝐵𝑃
= (0.19 × 0.941 + 0.11) × 94.1
= 27.178 m
2
𝑅 = √𝑦 2 + ( 𝐵 )
2
2
= √23.5252 + (25.5)
2
= 26.758 m
Theَberthingَangleَ(α)َisَ15˚.َThus,َtheَvalueَofَØَisَequalَtoَ75˚.
𝐾 2 + 𝑅2 cos 2 ∅
𝐶𝐸 =
𝐾 2 + 𝑅2
27.1782 + 26.7582 cos 2 75
=
27.1782 + 26.7582
= 0.541
The value of configuration coefficient (𝐶𝐶 ) is equal to 1 since the added mass
coefficient (𝐶𝑀 ) has already been considered.
𝐸𝑁 = 0.5𝑀𝐷 𝑉𝐵 2 𝐶𝑀 𝐶𝐸 𝐶𝐶 𝐶𝑆
= 0.5 × 12500 × 0.1922 × 1.353 × 0.541 × 1 × 1
= 17.189 ton.m
Abnormal impacts arise when the normal energy is exceeded. According to Table
3.6, the safety factor for abnormal berthing (𝐹𝑆 ) is taken as 1.50. The abnormal
berthing energy (𝐸𝐴 ) is determined in accordance with Equation (3.28) as follows:
𝐸𝐴 = 𝐹𝑆 𝐸𝑁
= 1.5 × 17.189
= 25.784 ton.m = 252.939 kNm
The absorbed energy of 303.526 kNm is the maximum performance and used as a
parameter in fender selection. According to Table 5.3, the SH 1000 V-fender will
give the best performance.
The tidal range at the jetty is 1.292 – (-1.292) = 2.584 m. The suitable length of
fender is 3000 mm in accordance with Table 5.4.
Performance values of SH V-fender listed in Table 5.3 are transformed into curve
of relation between kinetic energy and reaction as shown in Figure 5.12.
Based on regression analysis, the relation between kinetic energy and reaction of
SH V-fender can be formulated as power equation as follows:
𝑦 = 42.019𝑥 0.501
where:
𝑦 = 𝑅 = Reaction (kN)
𝑥 = 𝐸𝐴 = Kinetic energy / Abnormal berthing energy (kNm)
𝐿𝑂𝐴 = 100.7 m
𝐴 = 1m
deflection = 45%
ℎ = 𝐴 − 45%𝐴
= 1 − 0.45
= 0.55 m
𝐶 = 15%𝐴
= 0.15 m
1 𝐵 𝐿𝑂𝐴 2
𝑅𝐵 = ( + )
2 2 8𝐵
1 25.5 100.72
= ( + )
2 2 8 × 25.5
= 31.229 m
𝑃 ≤ 2√𝑅𝐵 2 − (𝑅𝐵 − ℎ + 𝐶 )2
The following SPT N-value correction factors due to field procedures are according
to Table 3.16.
𝐸𝐻 = 0.60 (Donut hammer, hand dropped release mechanism)
𝐶𝐵 = 1.00 (73 mm borehole diameter)
𝐶𝑆 = 1.00 (standard sampler)
Table 5.5 shows the corrected SPT N-values for field procedures.
The SPT N-values are also corrected for overburden pressure in accordance with
Equation (3.54) to Equation (3.56).
𝐺𝑠 = 2.67
𝑒 = 1.3525
𝛾𝑤 = 9.81 kN/m3
𝛾𝑤 (𝐺𝑠 + 𝑒)
𝛾𝑠𝑎𝑡 =
1+𝑒
9.81 × (2.67 + 1.3525)
=
1 + 1.3525
= 16.77 kN/ m3
𝛾 ′ = 𝛾𝑠𝑎𝑡 − 𝛾𝑤
= 16.77 − 9.81
= 6.96 kN/ m3
𝑃0 ′ = ∑ 𝛾𝑖 ℎ𝑖
𝑖=1
= 0 + 6.96 × 2
= 13.93 kN/m2
𝑁60 ′ = 𝐶𝑁 𝑁60
= 1.68 × 7
= 12
108
Table 3.16 shows the corrected SPT N-values for field procedures and overburden
pressure.
Table 5.6 Corrected SPT N-values for field procedures and overburden pressure
Depth Interval
𝑁60 𝑃0 ′ (kN/m2) 𝐶𝑁 𝑁60 ′
(m) (m)
0 0 0 0.00 0 0
2 2 7 13.93 1.68 12
4.5 2.5 8 31.34 1.41 11
7 2.5 10 48.75 1.27 13
9.5 2.5 44 66.16 1.16 51
12 2.5 50 83.57 1.09 54
14.5 2.5 9 100.98 1.02 9
17 2.5 10 118.39 0.97 10
19.5 2.5 9 135.80 0.92 8
22 2.5 12 153.21 0.88 11
24.5 2.5 13 170.62 0.85 11
27 2.5 37 188.03 0.81 30
29.5 2.5 50 205.44 0.78 39
32 2.5 50 222.85 0.76 38
34.5 2.5 50 240.26 0.73 37
37 2.5 50 257.67 0.71 35
39.5 2.5 50 275.08 0.69 34
The end of pile is in granular soil. The unit end-bearing resistance in granular soil
is calculated in accordance with Equation (3.57) as follows:
109
𝐿
𝑓𝑏 = 40𝑁60 ′ ( ) ≤ 400𝑁60 ′
𝑑
23
= 40 × 39 × ( ) ≤ 400 × 39
0.8
= 15,600 kN/m2
1 2
𝐴𝑏 = 𝜋𝑑
4
1
= 𝜋 × 0.82
4
= 0.503 m2
𝑄𝑏 = 𝐴𝑏 𝑓𝑏
= 0.503 × 15,600
= 7,841.42 kN
The unit skin friction resistance is calculated based on the soil type for each depth
of SPT measurement to obtain the cumulative value of skin friction resistance
known as ultimate skin friction resistance.
The unit skin friction resistance is calculated in accordance with Equation (3.59)
and Equation (3.60). The ultimate skin friction resistance is calculated in
accordance with Equation (3.62).
𝑁60 = 10
ℎ = 1m
110
𝑓𝑠 = 2𝑁60
= 2 × 10
= 20 kN/m2
𝐴𝑠 = 𝜋𝐷ℎ
= 𝜋 × 0.8 × 1
= 2.513 m2
𝑄𝑠 = 𝐴𝑠 𝑓𝑠
= 2.513 × 20
= 50.265 kN
𝑁60 = 9
ℎ = 2.5 m
𝑓𝑠 = 1,8𝑁60
= 1.8 × 9
= 16.2 kN/m2
𝐴𝑠 = 𝜋𝐷ℎ
= 𝜋 × 0.8 × 2.5
= 6.283 m2
𝑄𝑠 = 𝐴𝑠 𝑓𝑠
= 6.283 × 16.2
= 101.788 kN
The net ultimate load capacity is calculated in accordance with Equation (3.63) as
follows:
𝑄𝑢 = 𝑄𝑏 + 𝑄𝑠 − 𝑊𝑝
= 7,841.42 + 3,015.93 − 151.46
= 10,705.9 kN
𝑄𝑢
𝑄𝑎 =
𝑆𝐹
10,705.9
=
3
= 3,568.63 kN
𝜑 = 1.92˚
𝛾 = 𝛾′
= 6.96 kN/m3
𝑀𝑚𝑎𝑥 = 𝑀𝑦 = 2,589.67 kNm
𝑒 = 8.3 m
𝜑
𝐾𝑝 = tan2 (45° + )
2
1.92
= tan2 (45° + )
2
= 1.069
𝐻𝑢
𝑓 = 0.82√
𝑑𝐾𝑝 𝛾
2𝑓
𝑀𝑚𝑎𝑥 = 𝐻𝑢 (𝑒 + )
3
𝐻
2 × 0.82√𝑑𝐾𝑢 𝛾
𝑝
𝑀𝑦 = 𝐻𝑢 𝑒 +
3
( )
𝐻𝑢
2 × 0.82√0.8 × 1.069 × 6.96
2,589.67 = 𝐻𝑢 8.3 +
3
( )
113
𝐻𝑢 = 222.468 kN
1/5
𝑛
𝛼 = ( ℎ )
𝐸𝑝 𝐼𝑝
1/5
4,850
= ( )
2 × 108 × 0.00457
= 0.351
2,4𝐻 1,6𝐻𝑒
𝑦0 = 2/5 + 3/5
(𝑛ℎ )3/5 (𝐸𝑝 𝐼𝑝 ) (𝑛ℎ )2/5 (𝐸𝑝 𝐼𝑝 )
The maximum deflection which occurs at the head of pile is 20 mm (Coduto, 2001)
2,4𝐻
0.02 = 2
(4,850)3/5 (2 × 108 × 0.00457)5
1,6𝐻 × 8.3
+
(4,850)2/5 (2 × 108 × 0.00457)3/5
𝐻 = 324.253 kN
5 𝐸𝑝 𝐼𝑝
𝑇 = √
𝑛ℎ
5 2 × 108 × 0.00457
= √
4,850
= 2.85
𝑧𝑓 = 1,8𝑇
= 1,8 × 2.85
= 5.13 m
𝐿𝑒 = 𝑒 + 𝑧𝑓
= 8.3 + 5.13
= 13.43 m
𝜋 2 𝐸𝑝 𝐼𝑝
𝑄𝑐𝑟 =
4𝐿𝑒 2
𝜋 2 × 2 × 108 × 0.00457
=
4 × 13.432
= 12,499.26 kN
The maximum output results for jetty head of structural analysis generated by
SAP2000 are shown in Table 5.9 to Table 5.11. The maximum output will give
higher results if the current load applied to the hull is considered as berthing force
to the jetty head structure.
116
Table 5.9 Maximum axial load of pile output for jetty head
Joint Q (kN) Load Combination
513 2,078.054 1.4DL
517 2,074.386 1.4DL
Table 5.10 Maximum lateral load of pile output for jetty head
Joint H1 (kN) Load Combination
574 47.269 1.4DL
585 -47.291 1.4DL
Joint H2 (kN) Load Combination
1350 66.977 1.2D + 1.0LL + 1.0Ey + 1.0C2 + 1.0M1
582 -123.219 1.4DL
117
Table 5.11 Maximum lateral deflection of pile output for jetty head
Joint U1 (m) Load Combination
21, 227 0.00483 1.2DL + 1.0LL + 1.0Ex + 1.0C1 + 1.0B1
30, 226 -0.0048 1.2DL + 1.0LL + 1.0Ex + 1.0C2 + 1.0B3
Joint U2 (m) Load Combination
223 0.00656 1.2DL + 1.6LL + 1.6C1 + 1.6B1
233, 234 -0.0082 1.2DL + 1.0LL + 1.0Ey + 1.0C2 + 1.0B3
Table 5.12 Maximum axial load of pile output for mooring dolphin
Joint Q (kN) Load Combination
46 1,410.855 1.2DL + 1.6LL + 1.6C1 + 1.6M2
46 1,387.052 1.2DL + 1.6LL + 1.6C2 + 1.6M2
Table 5.13 Maximum lateral load of pile output for mooring dolphin
Joint H1 (kN) Load Combination
44 90.613 1.2DL + 1.6LL + 1.6C2 + 1.6M3
90 -99.467 1.2DL + 1.6LL + 1.6C1 + 1.6M2
Joint H2 (kN) Load Combination
47 91.202 1.2DL + 1.6LL + 1.6C1 + 1.6M2
46 -93.343 1.2DL + 1.6LL + 1.6C1 + 1.6M2
Table 5.14 Maximum lateral deflection of pile output for mooring dolphin
Joint U1 (m) Load Combination
9 0.01005 1.2DL + 1.6LL + 1.6C1 + 1.6M2
9 -0.0093 1.2DL + 1.6LL + 1.6C2 + 1.6M3
Joint U2 (m) Load Combination
19 0.002067 1.2DL + 1.0LL + 1.0Ey + 1.0C1 + 1.0M3
15 -0.00426 1.2DL + 1.0LL + 1.0Ey + 1.0C2 + 1.0M1
118
CHAPTER 6
CONCLUSIONS AND RECOMMENDATIONS
6.1 Conclusions
From the results and discussions that have been conducted, the coal unloading port
design can be concluded as follows:
119
120
6.2 Recommendations
Based on the findings, the author recommends:
1. The design of reinforced concrete structure for slabs, beams, and pile caps are
considered.
2. The drag force due to current applied to the hull is considered as berthing force
to the structure.
3. Software is used as a tool for designing the pile foundations.
4. The sediment transport of the river is considered in determination of the
waterway and basin depth.
5. The erosion outside of river bend and the slope stability of river bank is
considered to design the bank protection along the river especially at the jetty
area.
6. The maintenance dredging is determined since the jetty is located near the
mouth of Baturusa River with the result that sedimentation often occurs.
122
BIBLIOGRAPHY
Adi, T. K. Y., 2016. Final Assignment: Curtain Wall Breakwater Analysis Using
Dualsphysics (Case Study: Port of Kuala Tanjung, North Sumatra),
Yogyakarta: Universitas Gadjah Mada.
Aggour, M. S. & Radding, W. R., 2001. Standard Penetration Test (SPT)
Correction, Baltimore: Maryland Department of Transportation State
Highway Administration.
American Society of Civil Engineers, 2002. ASCE 7: Minimum Design Loads for
Buildings and Other Structures. Reston: s.n.
Asada, E. et al., 2007. Design and Construction Overview of the Biggest Coal Fired
Power Plant in Thailand (BLCP Power Plant), Developed by Private
Companies as IPP Business. Technical Review, 44(4).
Badan Standardisasi Nasional, 2008. Cara uji penetrasi lapangan dengan SPT (SNI
4153:2008). Jakarta: BSN.
Badan Standardisasi Nasional, 2012. Tata cara perencanaan ketahanan gempa
untuk struktur bangunan gedung dan non gedung (SNI 1726:2012). Jakarta:
BSN.
Badan Standardisasi Nasional, 2013. Beban minimum untuk perancangan
bangunan gedung dan struktur lain (SNI 1727:2013). Jakarta: BSN.
Badan Standardisasi Nasional, 2013. Persyaratan beton struktural untuk bangunan
gedung (SNI 2847:2013). Jakarta: BSN.
Chopra, H. B. & Patel, P., 2015. Application of Forces Acting on Jetty Structure.
International of Science Technology & Engineering, 1(11), pp. 83-91.
Coal Industry Advisory Board, 2010. Power Generation from Coal. Paris:
International Energy Agency.
Coastal Engineering Research Center, 1984. Shore Protection Manual. 4th ed.
Washington, D.C.: US Army Corps of Engineers.
Deger, T. T., 2014. Overburden Stress Normalization and Rod Length Corrections
for the Standard Penetration Test (SPT), Berkeley: University of California.
E. J. Bean, n.d. A new generation of mooring bollards. Norfolk: s.n.
Edgar, T. F., 1983. Coal Processing and Pollution Control. Houston: Gulf
Publishing Company.
123
Firuliadhim, G., 2011. Perhitungan Stabilitas dan Struktur Pondasi Rig Base
Lokasi PM-3 & PM-4 untuk Kapasitas 400 Ton, Bandung: Politeknik Negeri
Bandung.
Ghiffari, R. A., 2017. Tugas Akhir: Perencanaan Dolphin Dermaga Bongkar
Batubara (Studi Kasus: PLTU Jeranjang, Nusa Tenggara Barat).,
Yogyakarta: Universitas Gadjah Mada.
Hardiyatmo, H. C., 2015. Analisis dan Perancangan Fondasi II. 3rd ed.
Yogyakarta: Gadjah Mada University Press.
International Navigation Association, 2002. Guidelines for the Design of Fenders
Systems, Brussels: PIANC.
Japan International Cooperation Agency, 2015. Feasibility Study on the Coal
Transshipment Terminal Project for Thermal Power Centers in the Mekong
Delta in the Socialist Republic of Viet Nam, s.l.: Sumitomo Corporation.
Liaw, L. S., 2008. Studi Perilaku Pondasi Rigid Mooring Dolphin untuk Kapal
CPO 30.000 DWT, Depok: Universitas Indonesia.
Manoppo, F. J., 2010. Perilaku Tiang Pancang Miring pada Daya Dukung Tiang
Pancang Kelompok Akibat Beban Vertikal di Tanah Pasir. Media Teknik
Sipil, X(2), pp. 81-84.
National Highway Institute, 2016. Design and Construction of Driven Pile
Foundations - Volume I. Washington D.C.: U.S. Department of
Transportation Federal Highway Administration.
Ngainuni'mah & Ni'mah, Z., 2006. Laporan Tugas Akhir: Perencanaan Dermaga
Bongkar Batubara PLTU Cilacap, Semarang: Universitas Diponegoro.
NOAA, 2006. Understanding Tides. Washington D.C.: NOAA.
OCDI, 1991. Technical Standards and Commentaries for Port and Harbour
Facilities in Japan. Tokyo: Ports and Harbours Bureau, Ministry of Land,
Infrastructure, Transport and Tourism (MLIT).
OCDI, 2002. Technical Standards and Commentaries for Port and Harbour
Facilities in Japan. Tokyo: Ports and Harbours Bureau, Ministry of Land,
Infrastructure, Transport and Tourism (MLIT).
OCDI, 2009. Technical Standards and Commentaries for Port and Harbour
Facilities in Japan. Tokyo: Ports and Harbours Bureau, Ministry of Land,
Infrastructure, Transport and Tourism (MLIT).
Okubo, Y. & Kitakaze, R., 2017. Bussiness Risks of New Coal-fired Power Plant
Project in Japan, Tokyo: Renewable Energy Institute.
124
Versteegt, G., 2013. Berthing loads in structural design, Delft: Delft University of
Technology.
Wang, C. & Mu, D., 2014. An LCA Study of an Electricity Coal Supply Chain.
Journal of Industrial Engineering and Management, pp. 311-335.
Wrana, B., 2015. Pile Load Capacity - Calculation Methods. Studia Geotechnica et
Mechanica, 37(4), pp. 83-93.
Zainul, H., Fuddoly & Iriani, D., 2014. Perencanaan Detail Pembangunan Dermaga
Pelabuhan Petikemas Tanjungwangi Kabupaten Banyuwangi. Jurnal Teknik
Pomits, 1(1), pp. 1-6.
126
APPENDIX