Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Page 1 of 3

Kai Qi Tay

From: Kevin Attrill


Sent: 15 October 2009 09:12
To: Wallace Lee; Zamri Mat Ail; Brian Teh; Tan Li Ling Angeline; Charlotte Sze Sze Kong; Jason Zhou; Vincent Khin Voon
Chin; Li Hoon Lim; Dalencia Kwong; Ping Keong Lee; Teo Wei Ling Joan; Kai Qi Tay
Subject: FW: Liquidated damages 0: General damages 1
FYI
Kevin Attrill
Senior Commercial Manager
Gammon Contruction Limited Singapore Branch

Co. Reg. No: FO2909C

The latest from Law-Now

If you cannot view this email correctly, please click here to view it online.

Liquidated damages 0: General damages 1


An issue that continues to bedevil the construction industry is whether general damages are
recoverable when the parties agree that liquidated damages are not. In a typical scenario where
this issue arises, the parties will have agreed that liquidated damages are not payable if the
contractor is late in performing its works by striking out the liquidated damages clause in a
standard form, or by stating that the rate of liquidated damages is “nil”, “£0”
this, are they implicitly agreeing that the employer is also unable to recover general (or
unliquidated) damages, i.e. damages that the employer proves that it actually suffered due to
the contractor’s delay?
In one case last year from Western Australia, the court upheld an arbitrator
general damages were recoverable where liquidated damages were stated to be
has been another recent case where the Court of Appeal of Western Australia reached a similar
conclusion.
Background
A builder entered into a standard form lump sum building contract with a proprietor to construct
a brick house. The contract stated that the builder would not be responsible for delays in
commencing or completing the works over which the builder had no control. Additionally, the
contract stated that the builder “shall be liable to pay the Proprietor liquidated damages at the
rate of NIL DOLLARS ($00.00) per day for each day beyond practical completion until practical
completion is deemed to have taken place”.
Findings
The court held that while there was a clear intention that liquidated damages did not apply, on
the proper construction of the contract the court was unable to find a clear and unambiguous
intention to exclude the common law right to damages. The fact that the parties did not intend
liquidated damages to apply did not mean they also intended that general damages should be
irrecoverable.
Comment and Commercial Implications

 This Australian decision may be contrasted with the most prominent English case on point,
the decision of the Court of Appeal in Temloc v Errill (1987), in which the insertion of
in the appendix in relation to liquidated damages was held to exclude both liquidated and
unliquidated damages. The approach that all courts have taken to the question of whether
general damages are recoverable is to look at the words of each particular contract, in an
attempt to divine the intentions of the parties. By taking this approach, different results
may be yielded according to the facts.

05/07/2011
Page 2 of 3

 However, the common feature of most of these cases is that when the parties provide that
liquidated damages are “nil”, “£0” or “n/a”, or they strike out a liquidated damages clause,
they usually haven’t turned their minds collectively to the issue of whether general
damages should be recoverable even though liquidated damages are not. A further
complication is that the contract will often give no real indication either way of what the
parties actually intended (even if they had a common intention).

 How can the courts resolve this dilemma? The approach taken in the most recent case
from Australia takes an attractively simple approach, i.e. if the parties have not expressly
excluded the general right at common law to recover unliquidated damages for delay, the
presumption is that that right persists. This approach may help to avoid getting into
(intractable) difficulties over what the parties really meant, and effectively casts the burden
on the contractor to demonstrate that the parties intended a different meaning (i.e. that
general damages would not be recoverable).

 What is the lesson for parties negotiating a contract? If you don’t want liquidated damages
to apply, and you don’t want general damages to be recoverable, your contract needs to
spell this out, otherwise there is a real risk of a court (or an arbitrator or adjudicator)
deciding that general damages may be recovered for contractor delay. Simply stating that
liquidated damages are “nil”, “£0” or “n/a”, or striking through the liquidated damages
clause, is not enough because it creates an ambiguity.

Reference: J-Corp Pty Ltd v Mladenis [2009] WASCA 157


For further information, please contact:

Sarah-Jane Archdale
London
+44 (0) 20 7367 2880

Julian Bailey
London
+44 (0) 20 7367 2057

my profile:
edit my choices
edit my details
password reminder
contact the Law-Now administrator:
Law-Now Administrator
London
+44 (0)20 7367 2586

If you would like specific advice, please call your usual contact or the named contact responsible for the issue
addressed in this email (see above).
You have received this email as a registered member of Law-Now, CMS Cameron McKenna's free online information
service. To manage your Law-Now alerts, click here.To unsubscribe from Law-Now, click here.
All rights reserved. Information may be shared; however, reproduction in any medium requires our permission.
©CMS Cameron McKenna LLP 2009|Disclaimer|Terms & conditions and privacy policy
Feedback
If you have any comments on our Law-Now service, please contact our Law-Now Administrator:

CMS Cameron McKenna LLP


Mitre House
160 Aldersgate Street

05/07/2011
Page 3 of 3

London EC1A 4DD


Law-Now.Administrator@cms-cmck.com
Tel: +44 (0)20 7367 2586
www.law-now.com

Windows Live: Keep your friends up to date with what you do online.

05/07/2011

You might also like