: PSA/P7A/MS/004
Project 7 Acres Rev No : 0
1 of 4
DOC. NO.: DOC. NO.: PSA/P7A/MS/004
Project 7 Acres Rev No : 0
TABLE OF CONTENTS
2 of 4
DOC. NO.: DOC. NO.: PSA/P7A/MS/004
Project 7 Acres Rev No : 0
1. SECTION –: PURPOSE
The purpose of this procedure is to provide proper guidelines for post concrete inspection
and repair works at site to establish a system to control the work and to ensure that proper
quality control is exercised as per the specified requirement, maintain required quality and
to prepare all necessary documentations.
2. SECTION –: SCOPE
This procedure covers material, supervision and method of record keeping for all post
concrete inspection and repair works in Provident – Kenworth project.
3. SECTION –: REFERENCES
Good for Construction drawings.
Relevant codes and standards.
4. SECTION –: RESPONSIBILITIES
The responsibility of implementation of this procedure is with the Section In-Charge / Site
Engineer. Front line or SVD Engineer shall verify its implementation and checking the
activity, process and making necessary instruction for development.
5. SECTION –: MATERIALS
Cement
Non shrink cementitious grout (Approved make/GP2)
Cebex 100
Flexible PVC nozzles
Pressure grouting machine
6. SECTION –: METHODOLOGY
6.0 Before proceeding for any repair post pour inspection should be completed.
6.1. General Surface Preparation
The surface shall be sound, clean and free from any loose materials up to sound concrete
and the surface must be free from oil, grease and dust.
Concrete surfaces shall be prepared and shall be thoroughly soaked to ensure a saturated
but surface dry condition at the time of application of Repair product.
6.2. HONEYCOMB TREATMENT:
3 of 4
DOC. NO.: DOC. NO.: PSA/P7A/MS/004
Project 7 Acres Rev No : 0
Surface defect if reinforcement is exposed those area will be packed with Non – shrink
grout (GP2 ).
Grouting nozzles shall be fixed on the concrete surface at the particular location. After
setting time fixing the grouting nipple, grouting operation shall be carried out.
The Grout shall be prepared with mix of OPC /PPC & Cebex 100, W/C ratio shall be
maintained not more than 0.45.
Grout shall be pumped till the time it flows into the structure and the handle of grout
pump get tightened, filling all the gaps inside.
Once completed and grout is completely set, the projected parts of the nozzles shall be
removed, surface shall be cleaned and finished smooth.
After setting time of mortar, the curing must be started.
6.3. BULGE / UNDULATIONS IN STRUCTURE
If Bulge found in structure, excess concrete will be chipped Using light chipping hammers
weighing approximately 7 kg or less to remove the required amount of concrete. Follow
chipping remove this fractured surface.
Surface will be plastered with Non – shrink grout in proper line & level.
6.3.1. Repair of unformed surface
If undulation, in an unformed surface in high areas, it will be corrected by using a grinding
machine.The unsound concrete particles must be removed by using hand tools.
Bonding slurry mixture consists of cement and water will be applied on the pre-wet
substrata. The surface will be plastered with Non – shrink grout (GP2)/rendrocplug, in
proper line & level. Mixing & application to be done as per manufacture spec.
After setting time for repairing material; the curing must be started.
4 of 4