Work Progress Abhishek Heights Dafale

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

14

Work Target Completed Percentage 12


12
1 RCC work (G+11 Floor) 12 8 66.67 10
2 BBM work 12 4 33.33
3 Electrical Work (Wall Conduting) 12 3 25 8
8
4 Internal Plaster 12 3 25
6
5 Waterproofing Work 12 0 0
6 Plumbing work - Internal 12 0 0 4
7 Flooring work 12
2
8 Window Grill Fixing - Fabrication 12
9 External Plaster 4 0
10 Aluminium Window Fixing 12 RCC work (G+11 Floo

11 Door Fixing Work 12


12 External Stone Cladding Fixing 3
13 Downtake Plumbing & Looping 12
14 Lift Installation 2 1) RCC Work - 8th Floor T
15 Electrical - Wiring and Swichplate 12 2) BBM Work - 5th Floor
16 Internal Painting work 12 3) Internal Plaster - 4th F
17 External Painting work 4
18 CP & Sanitaryware Fixing 12
19 Glazing work 4
20 External Elevational Arches Fixing 3
21 External Services
22 STP Installation Work
23 Puzzle parking Installation
Abhishek Heights
14

12
12 12 12 12
10

8
8
6

4
4
3 3
2

0
RCC work (G+11 Floor) BBM work Electrical Work (Wall Internal Plaster
Conduting)

Target Completed

1) RCC Work - 8th Floor Top slab Shuttering work in Progress


2) BBM Work - 5th Floor BBM work in progress
3) Internal Plaster - 4th Floor Internal plaster work in progress