by Crispus Mugisha — December 29, 2019 in Homes Reading Time: 3 mins read 0
For Shs60m or slightly over, one can get themselves a decent three bedroomed self-
contained house, fully complete and finished.
Nile Post together with our partners First Village and Technical Construction Company
did the maths on what you would need to have such a project executed.
Setting out, one would require at least Shs500,000, this would help prepare the site for
the substructure.
A D V E R T I S E M E N T
Substructure
At least 6000 bricks are needed at this level if each brick costs Shs280 that would cost
one around Shs1.6m.
About 4 trips of lake sand (Shs800,000), 3 trips of river sand (Shs540,000), 4 trips of
hardcore (Shs800,000), 3 trips of aggregate (Shs720,000) and 40 bags of cement
(Shs1,120,000).
It is also important to buy the Anti termite, about 2 litres (Shs40,000) and 2 pieces of
DPM (Shs160,000).
Foundation
For a proper execution on the foundation, you need to dig in up to about Shs8m on the
higher end.
Timber
principal rafters —75pcs@7000=525000sh
Tie beams—70pcs@8500=560,000sh
Struts and ties—50pcs@7000=350,000sh
Under purlins—50pcs@8500=425000sh
Wall plates —25pcs@8000=200,000sh
Fascia board —20pcs@15000=300,000sh
TOTAL ROOFING =7,565,000sh
Ceiling
Timber
4*2—70pcs@7000=490,000sh
3*2—60pcs@5000=300,000sh
EML(8*2)—15bundle@25000=375000sh
Nails2″—10kg@5000=50,000sh
1.5kg—10kg@5000=50,000sh
Cement —5bags@28000=140,000sh
Sand—1trip elf@140,000=140,000sh
TOTAL CEILING =1,545000sh
Shutters
metallic windows fully finished with burglars,loovers and locks —6 of size
5*5ft@400,000=2,400,000sh
Size 1.5*1.5ft toilet windows—4@150000=600,000sh
FRONT DOOR
size 9*8ft—1@1300,000sh=1300,000sh
BEHIND DOOR —1@350,000=350,000sh
TOTAL SHUTTERING =4,650,000sh
Door frame—10@150000=1,500,000sh
Dooors—10@300000=3000,000sh
TOTAL WOODEN DOORS =4,500,000sh
Internal finishing
Plaster and floor screed
Cement —20bags@28000=700,000sh
River sand—3trips forward @180,000sh=540,000sh
Lake sand—200,000sh—200,000sh
A D V E R T I S E M E N T
Tiles
floors tiles—130SM@28000=3,640,000sh
Wall tiles —60SM@28000=1,680,000sh
Adhessive cement 15@20,000=300,000sh
Grout—30@6000=180,000sh
Strips—10pcs@8000=80,000sh.
Spacer—5pkts@3000=15000sh
TOTAL INTERNAL FINISHES =7,235,000sh
Painting
Undercoat paint—5cans@50000=250,000sh
Vinyl paint—3cans@200000=600,000sh
Supergloss oil paint—40ltrs@11500=460,000sh
Sanding paper —-1roll@80000=80,0000sh
Filler—-5kg@8000=40,000sh
Thinner—10ltrs@6000=60,000sh
Brushes—-5@5000=25,000sh
Rollers—-3@10000=30,000sh
Total painting =1,545,000sh
External finishing
Cement—20Bags@28000=560,000sh
Sand river —3forward@180000=540,000sh
Sand lake—1forward@200000=200,000sh
Under coat—5cans@50000=250,000sh
Weather guard —3cans@260,000=780,000sh
Solvent thinner —-5ltrs@5000=10,000sh
Scar folds —-200,000sh
Electrical installations
Conduits 3.1″—40pcs@3000=120,000sh
Conduits 1″—-15pcs@3500=52,500sh
MK boxes single —–10pcs@3000=30,000sh
MK boxes double —–10pcs@3500=350,000sh
Wall brackets —-15pcs@2000=30,000sh
Connectors—-10bars@5000=50,000sh
Lamp holders—–15pcs@3000=45,000sh
Cables 1.5mm—-150m@3000=450,000sh
Cables 2.5mm—-80m@3500=280,000sh
Earthing —-800,000sh
Sockets single —10@3000=30,000sh
Sockets double —–10@4000=40,000sh
Bulbs & roses —–15@25000=375,000sh
Accessories ——-400,000sh
Plumbing
TOTAL :51,516,600sh
Labour is 25% of the BOQ=12,879,150sh
TOTAL BOQ=64,395,750SH
The quotation has been compiled with help from First Village Technical and
Construction Company.