A Study of The MRP Implementation Process

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

JOURNAL OF OPERATIONS MANAGEMENT

Vol. 2, No. 3. May 1982

A Study of the MRP Implementation Process


Edna M. White*
John C. Anderson*
Roger G. Schroeder*
Sharon E. Tupy*

ABSTRACT process and where major problems can be


expected to occur.
This paper reports on a large-scale survey of
A great deal of information is currently available
companies involved in MRP implementation. Sur- as to the best way to implement an MRP system.
vey responses are used to develop a profile of Most of this research is in the form of personal
problems typically encountered during the imple- experience or case studies [e.g., 1, 131. The
mentation process. Discriminant analysis is used
detailed description of the implementation pro-
to determine which of those problems, and addi- cess provided by these studies is certainly valu-
tional factors, appear to affect the success orfail- able. However, a wider perspective is also desir-
ure of MRP implementation. Finally, compari-
able. This report provides that perspective by
sons are made between the problems encountered reporting on and analyzing the results of a survey
during implementation and problems which were
of MRP implementation.
found to significantly discriminate between suc- A six-page survey was developed to explore the
cessful and unsuccessful MRP implemen tars. current status of MRP in companies today. The
survey included questions about the respondent
Materials requirements planning (MRP) is prob- companies, the current status of MRP at the com-
ably the most rapidly growing system area in oper- pany, the benefits and costs incurred, the nature
ations today. Hundreds of companies have imple- of the implementation process used and the prob-
mented or are in the process of implementing an lems faced during implementation. Question-
MRP system. Many more companies are evalu- naires were sent to approximately 1,700 members
ating the applicability of MRP for their operations. of the American Production and Inventory Con-
MRP literature gives many impressive testimoni- trol Society (APICS) in the Upper Midwest. Of
als as to the results of successful implementation. this population, 679 (40%) of the companies
Unfortunately, case histories of unsuccessful responded. Of the respondents, 422 (62%)
implementation efforts are also common [3, 41. reported an MRP system in some stage of devel-
The potential MRP implementor may well be more opment. This is the largest and most comprehen-
discouraged by difficulties than encouraged by sive survey on MRP undertaken to date. A full
benefits. report on the survey is found in MRP: A Study of
Even in successful attempts, the implementa- Implementation and Practice, a manuscript
tion of an MRP system is a major undertaking for funded by and available through APICS.
any company. Cost, both in resources and in time, This paper will deal specifically with the reasons
is high. Additionally, since an MRP system inter- why MRP is being adopted, the problems encoun-
faces with most functional areas, some degree of tered during implementation, and the impact of
turmoil within the company is probably unavoid- these problems on the implementation process.
able [6]. Any company attempting or considering All results are based on the responses from the
implementation of an MRP system needs infor- survey described above. Although large, this is
mation on how to manage the implementation certainly not a random sample; it is confined to
the Upper Midwest, it is undoubtedly biased
towards production-oriented firms and towards
firms in the process of implementing an MRP sys-
*Operations Management Program, Graduate School of Business
Administration, University of Minnesota.
tem. There seems to be little reason, however, to
assume that the implementation strategy used and
This study was partially supported by a grant from the APICS Edu- the problems faced by this sample are unique to
cational and Research Foundation. these 422 companies. Table 1 shows the industry

Journal of Operations Management 145


TABLE 1 questionnaire: (1) What was your major reason for
INDUSTRY REPRESENTATION implementing an MRP system? and (2) What was
the major problem you encountered during imple-
Number of mentation? The responses to these questions
Industry Companies (summarized in Table 2) give an excellent over-
view of the MRP implementation process.
Food a Most of the reasons given for MRP implemen-
Lumber and Wood 1 PROCESS
tation are specific to the MRP system and centered
Paper 4
Chemicals a in Production and Inventory Control. Only two of
Petroleum and Coal 1 the categories, management practices and growth,
Rubber and Plastic 7 seem to center around more general issues. The
major problems encountered, however, show an
Fabricated Metals 49 METAL entirely different pattern. Few of the respondents
Machinery 65 emphasized problems with the technical installa-
tion of the MRP system. Most problems center
Electric-Electronic 76 ELECTRICS around issues of effective implementation, such
Instruments 71 ELECTRONIC as education, acceptance and top management
support.
Transportation
Equipment
Although 60% of the respondents implemented
75 TRANSPORT
their MRP systems for control of inventories, pro-
Misc. Manufacturing 75 duction and costs, only 9% reported their major
Apparel 40 MISCELLANEOUS problem to be in the area of inventory control and
Furniture 50 record accuracy. It has frequently been stated that
Printing and the technical problems in MRP implementation
Publishing 50 have been solved. The remaining problems in
Stone, Clay, Glass 50 implementation are “people problems” [2, 3, 71.
Other 44 Generally, the survey results support this view,
although technical problems such as forecasting
Industry Not Reported 14
demand were reported as major problems by some
companies. This point will be discussed in more
breakdown for the companies in the survey. As detail later. However, it should be noted here that
can be seen, a wide variety of industries is repre- the companies surveyed reported that manage-
sented. ment of the implementation process was more
important than the exact specifications of the sys-
IMPLEMENTATION OF MRP SYSTEMS
tern being implemented.
Two open-ended questions about the MRP Many articles have debated the merits of spe-
implementation process were included in the cific features of MRP systems (e.g., net change

TABLE 2
MAJOR REASON FOR MRP IMPLEMENTATION AND MAJOR PROBLEM ENCOUNTERED

Major Reason Percent Major Problem Percent

INVENTORY CONTROL 31% EDUCATION OF PERSONNEL 23%


PRODUCTION CONTROL 16% LACK OF TOP MANAGEMENT SUPPORT 20%
IMPROVE MANAGEMENT 14% IMPLEMENTATION APPROACH 15%
(Lack of time, personnel)
IMPROVE CUSTOMER SERVICE 13% PROBLEMS WITH MRP SYSTEM 15%
(Lack of technical expertise)
COST CONTROL 13% GAINING ACCEPTANCE 1 1%
COMPANY GROWTH 13% INVENTORY CONTROL AND RECORD
~___ ACCURACY 9%

109% FORECASTING DEMAND 7%

100%

146 American Production and Inventory Control Society


versus regenerative systems) and have attempted TABLE 4
to define the conditions for selecting the “right” EXTENT OF PROBLEMS ENCOUNTERED
methods [4, 111. None of the respondents, how-
ever, mentioned selection of such features or Confidence
selection of the wrong feature as a major problem. Problems with Data Accuracy Average* Interval
It appears that companies implementing MRP sys-
Bill of Material 2.2 2.07-2.33
tems do not find that the selection of features is of Vendor Lead Times 2.2 2.09-2.31
major importance. Production Lead Times 2.2 2.09-2.31
As would be expected from the reasons given Master Production Schedule 2.4 2.27-2.53
for MRP implementation, the process is most Inventory Records 2.5 2.37-2.63
often reported to have been initiated by produc- Capacity Data 2.7 2.56-2.84
tion and inventory control management, either Shop Floor Control Data 2.7 2.56-2.84
alone or in combination with top management Market Forecasts 2.8 2.67-2.93
(Table 3). It appears that top management support
is commonly found in MRP implementation. The Problems with Management
importance of top management support for any Support
successful implementation effort has been fre-
Lack of Support from Finance 1.6 1.50-1.70
quently stressed. Further results, discussed in the
Lack of Top Management
next section, give additional support for this view. Support 2.0 1.87-2.13
Lack of Manufacturing
PROBLEMS ENCOUNTERED IN MRP Management Support 2.1 1.98-2.22
IMPLEMENTATION Lack of Support from
A series of questions, exploring in more detail Marketing 2.2 2.08-2.32
Lack of Foreman Support 2.3 2.18-2.42
the extent to which various problems were
encountered, were included in the survey. Problems with System
Respondents were asked to indicate how much
each area had been a problem to them during High Cost of MRP System 1.8 1.69-1.91
implementation by marking one of four categories: Constraint of Computer
little/none, some, much or very much. For anal- Hardware 1.9 1.77-2.03
ysis, the categories were scored from one to four, Lack of Suitability of Software 2.0 1.87-2.13
respectively. A list of these questions, their aver- Lack of Clear Goals 2.1 1.98-2.22
age problem score, and confidence intervals for Lack of Company Expertise 2.5 2.37-2.63
the averages are shown in Table 4. Examination Lack of Communication 2.5 2.37-2.63
of these problem areas gives a profile of the extent
“Scoring Code
to which various problems can be expected during 1 = “Little/Some” 3 = “Much”
the MRP implementation process. 2 = “Some” 4 = “Very Much”
Since a materials requirements planning system
demands an extremely high standard of accuracy
of input data, record accuracy has frequently been Looking at the intervals shown in Table 4, it can
mentioned as a major problem in the implemen- be readily seen that the areas with most problems,
tation of the system. Responses to questions con- capacity data, shop floor control data and market
cerning all types of problems with data accuracy forecasts, show significantly higher mean problem
averaged between “some” and “much.” Since scores than the lowest four. These areas can be
groups of variables are considered, Bonferroni viewed as the problem areas of data accuracy for
family confidence coefficients [lo] were used to the MRP implementation process: the areas in
give 95% family confidence level for each group. which problems can be expected in MRP imple-
mentation.
TABLE 3 Problems with management support were also
INITIATOR OF MRP IMPLEMENTATION considered in detail. Again using Bonferroni con-
fidence intervals, lack of support from marketing
Production and Inventory Control 31%
and foremen were significantly higher, on the
Both Top and P&IC Management 3 1%
average, than from finance. In interpreting these
Top Management 18%
Data Processing 10%
results, it must be remembered that the responses
Other 10% are from companies who have at least begun the
implementation effort. Lack of support from

Journal of Operations Management 147


finance or top management may well be much mentation studies have typically measured suc-
more prevalent among companies where the effort cess by attitudes, intentions or behavior of users.
was never undertaken. Intended use, rather than actual use, is often
The highest mean problem score in the area of selected as a measure of success because of dif-
management support was in lack of foreman sup- ficulties in obtaining measures of actual use [9].
port. It appears that the attitude of line personnel, Actual pe~o~ance measures of MRP systems,
or secondary users, frequently do result in prob- however, can be readily specified and quantified.
lems during the process of implementation. These Successful implementation in this paper is
results suggest that, once the commi~ent to an defined along two dimensions: (1) improved per-
MRP system has been made, user involvement of formance, and (2) user satisfaction. Rather than
foremen and other personnel should be empha- attempting to combine these two dimensions, a
sized. Additionally, communications between simultaneous criterion was used: companies high
departments, particularly those including the mar- on both dimensions were defined as successful
keting department, should be encouraged. implementors and companies low on both as
The above results appear to highlight the impor- unsuccessful. Other companies were left unde-
tance of education during MRP implementation. fined.
Regretably, the complexities of the education Tables 5a and 5b show the questions in the sur-
process (e.g., type, amount, and timing) make it vey relating to performance measures and to user
unamenable to detailed study by mail survey tech- satisfaction. For those areas shown under perfor-
niques. This is particularly true in the present case mance measures 5A, respondents were asked to
where a broad range of notation was collected. give a “pre-MRP” estimate, a current estimate
Although the evidence from the present study cer- and a future estimate, all in terms of the current
tainly supports the concept of the importance of economic environment. It was thought that since
education, additional research exploring the edu- some companies undoubtedly have more room for
cational process remains to be done. improvement than others, a measure of improve-
Finally, problems with the system are shown in ment in performance would not be sensitive
Table 4. Again, it is found that problems such as enough to identify successful implementation. A
lack of communitiations and of company expertise measure of progress towards expected perfor-
are sign~cantly more prevalent than such highly
technical problems as computer hardware and TABLE 5A
software. A surprising finding is the relatively low BENEFIT MEASURES
problem score on lack of clear goals, often a major
problem in implementation. The low score is prob- For each of the characteristics below (a-f) state (in column
II) the current experience given your stage of MRP devel-
ably due to the nature of the MRP system itself.
opment. Then state (in column I) the experience that you
As was discussed previously, respondents were would expect operating in today’s economic environment
able to supply specific reasons for MRP imple- with your Pre-MRP production system. Finally, state (in
mentation. Difficulties arise, then, not in speci- column hi) the future experience that you anticipate given
fying goals, but in achievement of those goals. total completion of your MRP development plans.
This section has highlighted various problem
I II Ill
areas in implement~g an MRP system. The ques-
“Pre-MRP” Current Future
tion of how important the problems actually are Estimate Estimate Estimate
during the process of implementation still remains.
A completely problem-free implementation is a. Inventory turnover
ideal, but probably an unattainable ideal. The b. Delivery lead time (days)
important issue is the end result of the implemen- c. % of time meeting delivery promises
tation process: successful implementation of an d. % of orders requiring “splits” because of unavailable
MRP system. The remainder of this paper material
describes an analysis to determine which factors e. Number of expeditors
and problems appear to significantly affect the
success or failure of an MRP implementation. PROGRESS = ; 2 -$$$I,:bqre-f$;:’

DEF~~ION OF SUCCESSF~ AVERAGE FIGURES


~PLE~NTATION All companies .48
“Successful” companies .78
The first step in exploring reasons for successful ‘Unsuccessful” companies .15
implementation must be to define success. Imple-

148 American Production and Inventory Control Society


TABLE 58 questions used a Likert-type scale to collect data,
USER SATISFACTION the data should be interpreted as expressing user
perceptions of the success of MRP implementa-
To what degree have the following benefits been achieved tion, or user satisfaction. A measure of user sat-
from your MRP system? isfaction was obtained by summing over the coded
Degree of Improvement scores shown in Table 5B. The satisfaction score
Little/ could, thus, range from 9 to 36.
None Some Much Very Two distinct groups of companies were then
formed: those high on both performance and sat-
Coded Values- (1) (2) (3) (4) isfaction and those low on both. The average
a. Improved competitive
scores for all companies and for successful and
position unsuccessful implementors are displayed in
b. Improved customer sat- Tables 5A and 5B. As can be seen, the average
isfaction scores are well separated in the two groups. Three
c. Better production hundred and fifty-seven companies had both mea-
scheduling sures completed. Out of this number, 193 com-
d. Improved plant effi- panies were selected for further analysis: 109 were
ciency low on both measures (unsuccessful implemen-
e. Reduced safety stocks tors) and 84 were high on both measures (suc-
f. Better cost estimating
cessful implementors). The remaining 164 com-
g. Better control of inven-
panies were omitted from further analysis.
tory
h. Improved coordination
with marketing and ANALYSIS OF SUCCESSFUL AND
finance UNSUCCESSFUL IMPLEMENTORS
i. Improved morale in pro-
Discriminant analysis was selected as the
duction
appropriate technique to determine which of the
Satisfaction = 1 Reported Coded Values variables collected in the survey were important
in distinguishing between the successful and
AVERAGE FIGURES unsuccessful implementors. Variables which reli-
ably discriminate between the two groups can be
All Companies 22.1
interpreted as important attributes in the success
“Successful” Companies 27.3
14.5
of MRP implementation [8].
“Unsuccessful” Companies
Stepwise discriminant analysis was employed
to select variables for inclusion in the final model.
The BMDP stepwise discriminate program was
mance was constructed which measured each employed to screen potentially useful variables
company’s current progress against its own [5]. All variables which were included in the pre-
expected future performance: liminary search are listed in the framework shown
Prog- Current Estimate - “Pre-MRP” Estimate in Table 6. Before detailing the analysis and
ress = Future Estimate - “Pre-MRP” Estimate results, a brief description of these variables will
be given.
Progress for each of the five performance mea- The first major category is that of the indepen-
sures were summed to give a measure of overall dent variables. These are variables considered to
performance for each company, then divided by be outside of, or previous to, the implementation
five to show average progress in performance. process. The independent factors are further
This summary variable, therefore, includes fifteen divided into two main classes: (1) company or
individual responses for each company. As is environmental conditions, and (2) the features of
common with survey data, many companies did the MRP system being implemented.
not respond to every question. In cases where less Environmental conditions include the industry,
than half of the individual responses were missing, the percentage of employees in P&IC, the present
missing values were replaced with their mean accuracy of data, size of company and comput-
value. The estimates and real values were then erization of company. Numerous questions in the
used in calculating all summary variables. survey related to company characteristics. Factor
Table 5B shows the questions which comprise analysis was performed on these questions and
the dimension of user satisfaction. Since these two important factors identified: “size” and

Journal of Operations Management 149


TABLE 6
FRAMEWORK OF IMPLEMENTATION VARIABLES

INDEPENDENT INTERVENING RESPONSE


VARIABLES VARIABLES VARIABLES
Company/ Implementation
Environmental Process
Company size Initiator
Computerization Industry Formality of project
Industry Source of information
Prior conditions -outside people Successful or
Percent of employees in P& IC -software vendors Unsuccessful
Data accuracy -consultants Implementation
-computer vendors
-APICS {
-books/periodicals

System Features Problems with Data Accuracy*


. Pegging Problems with Mgmt. Support*
l Update frequency
l Length of MS.
l Cycle counting

0 Automatic lot sizing


I Length of Time Since Implementation

‘See Figure 3 for full description.

“computerization.” The company size factors was decided to hold back one-fourth of the data
was heavily weighted by facility sales, total com- from the analysis. A stepwise discriminate anal-
pany sales, total number of employees and num- ysis was performed on the remaining three-fourths
ber of employees in P&C. The computerization of the data to discover the most promising vari-
factor was most heavily weighted by the extent to ables from the developed framework. The analysis
which various modules of the MRP system were was performed on 116 complete cases, 52 suc-
computerized and the integration of the separate cessful implementors and 64 unsuccessful imple-
modules. These two factor scores were included mentors.
in the discriminant analysis. Prior condition of Table 7A shows the results of the final discrim-
company refers to a question as to what type of inant analysis. Of the 116 cases used to fit the
system was used previous to the MRP system. model, 90 percent of the successful companies and
The other variables in this classification have been 86 percent of the unsuccessful implementors were
discussed previously or are self-explanatory. correctly classified. Overall, classification was 88
System features of the particular MRP system percent correct.
have been classified as independent variables. The jackknifed classification is also shown in
Although decisions must be made about selection Table 7B. In a jackknifed classification, each case
of features, this selection is viewed here as sepa- is classified as either successful or unsuccessful
rate from the actual implementation process. using a discriminate function computed from all
The intervening variables are those factors other cases. The jackknifed classification both
which relate directly to the process of implemen- tests the predictive power of the model and gives
tation. In addition to the problems encountered a more robust measure than the simple classifi-
(discussed in previous sections) length of time cation [5, 91. As can be seen, the jackknifed clas-
since the implementation of MRP and information sification is close to the simple classification, with
about the process used are considered as poten- 85 percent of all cases correctly classified. The
tially important. discriminant analysis, therefore, is very reliable
The first step in the actual analysis was the in identifying successful from unsuccessful imple-
construction of a hold-out sample. As in all anal- mentors.
ysis, there is the possibility of “over-fitting” the The hold-out sample contained 44 complete
data: the analysis may describe the data being cases: 21 successful and 23 unsuccessful compa-
analyzed, but be inappropriate for other data. To nies. To further test the predictive power of the
test the predictive power of the fitted model, it model, the discriminant function was used to clas-

150 American Production and Inventory Control Society


sify these cases into the two groups. Seventy-four TABLE 8
percent of the successful companies and 86 per- DISCRIMINATE FUNCTION VARIABLES AND
cent of the unsuccessful ones were correctly clas- STANDARDIZED COEFFICIENTS
sified (Table 7C). Thus, the model developed in
the discriminant analysis is also reliable in pre- independent Intervening
dicting success or lack of success in implementa- Variables Variables
tion. Company/Environmental lmplemen ta tion Process
The standardized coefficients of the variables Condition
in the final discriminant function are shown in +.48 Computerization -t .36 Source of
Table 8. The size of the coefficient shows the +.23 Prior Conditions information
relative weightings of the variables. The sign (No Systematic (Hiring outside
shows the direction of the effect. For example, Inventory System personnel)
Previously) Problems with Management
data accuracy was found to be the most heavily
+.28 Percent Employees Support
weighted variable, with higher levels of accuracy in P&IC
associated positively with successful implemen- -.39 Top Management
+.78 Data Accuracy (sum) -,33 Marketing
tation. (Inventory records Management
The following section discusses the implications market forecasts
of the discriminate function for MRP implemen- System Problems
capacity plan)
- .44 Sum of problem scores
tation by discussing each of the variables in detail. System Feature (Lack of expertise
(None) Lack of suitable
DISCUSSION OF RESULTS computer hardware)
The most heavily weighted of the selected vari- Problems with Data
ables is data accuracy. This variable is the sum of Accuracy
the scores of current accuracy of data. This sup- (None)
ports the contention that accurate information is Length of Time of
a necessity for successful implementation of MRP Implementation
systems. Current accuracy is a more reliable pre- +.44 Year before MRP
dictor of success than problems encountered with
data accuracy during the implementation process. rather than responses to individual questions. This
Accuracy of information is a summary variable. was done primarily since summary variables tend
When possible, summary variables were selected to be more normally distributed. After the analysis
was completed, however, the separate compo-
TABLE 7 nents of each summary variable in the model were
DISCRIMINANT ANALYSIS CLASSIFICATION entered into discriminant function in place of the
summary variable to determine which, if any, of
A. SIMPLE CLASSIFICATION the components were particularly important. In
Actual Classified by Model as Percent the case of data accuracy, only three of the items
Group Successful Not Successful Correct were found to have separate discriminatory
Successful 47 5 90.4 power: accuracy of inventory records, market
Not Successful 9 55 85.9 forecasts and capacity plan. Market forecasts and
Total 87.9 capacity data, as discussed previously, were also
prevalent problems encountered during the imple-
B. JACKKNIFED CLASSIFICATION
mentation process.
Actual Classified by Model as Percent The next most important variable is computer-
Group Successful Not Successful Correct ization. The implication here is that computeriza-
Successful 45 7 86.5 tion and successful implementation of MRP are
Not Successful 10 54 84.4 closely intertwined. Higher levels of computeriza-
Total 85.3 tion appear, at least, to increase the chances for
C. HOLDOUT SAMPLE successful implementation.
Actual Classified by Model as Percent The last two independent variables included in
the discriminant model have relatively low
-___ Group Successful Not Successful Correct
weights. The percent of employees in P&IC has
Successful 17 6 73.9
Not Successful 3 18 85.7
a positive effect on implementation success. This
Total 79.5 implies that production-oriented firms are more
likely to successfully implement MRP. The rela-

Journal of Operations Management 151


tively low weight, however, suggests the MRP Finally, amount of time since the implementa-
may well be usefully and successfully imple- tion effort was first begun significantly increased
mented in firms which are less production- the chances of successful implementation. This is
oriented. Finally, having no systematic inventory encouraging, since it suggests that success is likely
policy previous to MRP implemen~tion was to reward continued efforts. Additionally, this
found to improve chances of successful imple- finding supports the view of MRP implementation
mentation. Previous use of a manual parts explo- as a continuous process rather than a goal to be
sion system or an order-point system had no reached.
effect. In summary, disc~minant analysis has been
None of the system features were found to have used to select those factors which most reliably
significant discriminatory powers in this analysis. distinguish between successful and unsuccessful
It might be argued that selection of features can implementors of MRP systems. These significant
help to “fine-tune” an MRP system, resulting in factors are often not the same factors which were
the highest possible benefits. Success or failure of reported to have the most severe problems during
the implementation effort, however, does not implementation.
appear to depend upon any specific features of the It cannot be concluded with certaintly, how-
system. ever, that variables which did not enter the dis-
The intervening variables, since they relate criminant analysis model are not important in suc-
directly to the implementation process, are of pri- cessful implementation. Many of the variables are
mary interest. Of the variables specifically intercorrelated. For example, company size did
describing the process, only use of personnel hired not show signi~cant disseminator power. Size,
from outside the firm as a source of expertise was however, is highly correlated with length of time
found to be important in the discriminate function. of implementation and with computerization. If
In the area of problems with management sup- these two variables were not included in the anal-
port, two items were found to be significant: prob- ysis, company size would appear to influence
lems with lack of top management and/or market- implementation success. In this analysis, how-
ing management support. Lack of support from ever, length of the effort and computerization
marketing management was reported as a preva- have been found to be more reliable discriminators
lent problem, while lack of top management sup- of successful and unsuccess~l ~plementors than
port was not. It appears as though lack of support company size.
from marketing management is a prevalent and
serious problem which should be expected,
planned for and overcome. Problems with lack of CONCLUSIONS
top management support are not so prevalent (see Comparing average problem scores reported by
Figure 4 for average problem scores). If top man- the companies to the results from discriminant
agement support is lacking, however, this problem analysis gives insight into how the implementation
appears to cripple an ~plementation effort. process should be managed. In general, areas with
Lack of support from foremen, although high problem scores tended to be important in the
reported to be the highest problem area, is seen analysis. Accurate capacity data and market fore-
not to be a key area in eventual implemen~tion casts, support from marketing and company
success. It seems likely, however, that support expertise on MRP have been shown to be impor-
from foremen would be extremely useful for a tant and common trouble spots in MRP imple-
rapid and relatively smooth implementation. mentation. Preventive action and management
A summary variable consisting of problems during implementation in these areas are crucial
encountered with the system was found to be sig- for success.
nificant. Further analysis showed that the two Other problem areas, although reported as prev-
most impo~ant components of this summa~ were alent, were found not to be impo~ant in the dis-
lack of company expertise and constraints of com- criminant analysis between successful and unsuc-
puter hardware. Lack of expertise had a high prob- cessful implementors. Shop floor control data,
lem score; it was perceived as a common problem problems with foremen and lack of communica-
in the implementation process. Constraints from tion should be expected and averted, if possible,
the computer hardware was a much less prevalent for a more effective and problem-free implemen-
problem. It appears that, like top management tation. However, avoiding these problems does
support, computer hardware is seldom a problem, not appear to be crucial for eventual implemen-
but if it exists, the problem is a serious one. tation success.

152 American Production and hventwy Control Society


Continuing effort over a period of time tends to 3. Andrews, Charles G. “Leadership and Motivation: The People
Side of Systems Implementation,” American Production and
produce success, suggesting that MRP implemen- Inventory Control Society Conference Proceedings, 1978, pp.
tation should be viewed as a long-term project. 352-387.
Computerization is apparently necessrsy for suc- 4. DeSantis, Gerald F. “Implementation Considerations in Sys-
cessful implementation. A final specific sugges- tems Design,” American Production and Inventory Control
tion is that hiring outside people with experience Society Conference Proceedings, 1977, pp. 210-217.
5. Dixon, W. J. and Brown, M. B. (eds.) BMDP-79: Biomedical
in MRP is the most effective way to deal with the Computer Programs P-Series, University of California Press,
problem of lack of expertise in the company. Berkeley, 1979, pp. 71 l-733.
Because of the nature of survey-based research, 6. Hall, Robert Ward and Vollmann, E. E. “Planning Your Mate-
many important details are missing from this pic- rials Requirements,” Harvard Business Review (September-
ture of MRP implementation. Much more research October, 1978), pp. 105-l 12.
7. Hoyt, George. “Successes and Failures in MRP User Involve-
is necessary to explore the best ways of introduc- ment,” American Production and Inventory Control Society
ing MRP into a particular company, the develop- Conference Proceedings, 1977, pp. 204-209.
ment of training and education programs and, per- 8. Maxwell, A. E. Multivariate Analysis in Behavioral Research,
haps most importantly, specific ways of managing Chapman and Hall, London, 1977, pp. 94-105.
the change process. The broad framework and 9. Mosteller, Frederick and Tukey, J. W. Data Analysis and
Regression, Addison-Wesley Publishing Company, Reading,
results provided by this report should prove useful Mass., 1977, p. 133ff.
in organizing future work on MRP implementa- 10. Neter, John, and Wasserman, William. Applied Linear Statisti-
tion. cal Models, Richard D. Irwin, Inc., Homewood, Ill., 1974, pp.
153-154.
11. Peterson, Leroy D. “Design Considerations for Improving the
Effectiveness of MRP,” Production and Inventory Control
REFERENCES (Third Quarter, 1975), pp. 48-68.
12. Schultz, Randall L. and Sleven, D. P. “Implementation and
1. Amdur, Nicholas. “Getting Started in Materials Requirements Management Innovation,” in Zmplementing Operations Research1
Planning,” American Production and Inventory Control Society Management Science, Schultz and Sleven (Editors), American
Conference Proceedings, 1973, pp. 137-145. Elsevier Publishing Company, New York, 1975, pp. 14-15.
2. Anderson, John C. and Narasimhan, R. “Assessing Project 13. Zeszutka, Jerome and Dixon, D. K. “Tailoring an MRP System
Implementation Risk: A Methodological Approach,” Manage- to Company Needs,” Journal of Purchasing and Materials Man-
menf Science (June, 1979), pp. 512-522. agement (Winter 1978), pp. 2-8.

Journal of Operations Management 153

You might also like