Professional Documents
Culture Documents
Documents - Pub - World Bank Ghorasal Urea Fertilizer H Feasibility Report On The Fertilizer
Documents - Pub - World Bank Ghorasal Urea Fertilizer H Feasibility Report On The Fertilizer
Document of FILECOPY
The World Bank
FOR OFFICIAL USE ONLY
BANGLADESH
Public Disclosure Authorized
This document has a restricted distribution and may be used by recipients only in the performance of
their official duties. Its contents may not otherwise be disclosed without World Bank authorization.
CURRENCY EQUIVALENTS
US$1 = Tk 15.5
Tk 1 = US$0.065
Tk 1 million = US$64,516
July 1 - June 30
FOR OFFICIAL USE ONLY
BANGLADESH
TABLE OF CONTENTS
Page No.
I. INTRODUCTION ................................ 1
This report was prepared by Messrs. S. Venkataraman and Kurt Loos of the
Industrial Projects Department.
This document has a restricteddistributionand may be used by recipients only in the performance
of their official duties. Its contents may not otherwise be disclosed without WorldBank authorization.
TABLE OF CONTENTS (Continued) Page No.
A. General .......o............................................
*......o... 34
B. Operating Costs and Revenues ........* ................... 34
C. Financial Rate of Return . ...... .... ........ ....... . .. . 37
D. Financial Covenants and Reporting Requirements ......... 38
E. Major Risks ......................... .....................38
X. AGREEMENTS ...................................................
42
ANNEXES
MAP
Reference
I. INTRODUCTION
A. ExistingPlants
B. AdditionalCapacity
2.04 During the Ashuganj project appraisal the Government and the lenders
agreed that it would be preferableto create a new entity which could devote
its full attention to the implementationof the project. Subsequently,a new
government-ownedcompany,the Ashuganj Fertilizerand ChemicalCompany (AFCC),
- 3-
the period intendedto be covered under the Eighth Program Credit, the
credit presentedhere includesUS$8.3 million to cover about two years'
import requirements. For this purpose, BCIC will prepare before December 31,
1980 a maintenance program satisfactoryto the Association,and the new
fertilizercompanies will carry it out in accordancewith appropriate
engineering standardsand practices. The preparationof the maintenance
program will be a conditionof disbursementof the spares,catalysts and
chemicalscomponent. The annual foreign exchangerequirementsof US$24
million to cover the operationalimport requirementsof the existingplants
will contributefertilizerproductionof about US$100 million in value based
on present fertilizer CIF prices. The Government has agreed to take all
necessary steps to ensure adequateand continuingprovisionof foreign
exchange funds to meet the plants' requirementsfor imported raw materials,
spares, catalystsand chemicals.
E. Staffingand Training
2.12 Under a UNDP financed project,a contract has been signed with
UNICO Internationalof Japan (UNICO) to provide operations assistance to the
Ghorasal and Chittagongplants. This project provides technicalmanagement
assistance to develop the BCIC management skills and will train each year
approximately4 managerial,7 supervisory,14 skilled technicaland 25
operative staff. In addition, the project includestraining adviserswho
will assist BCIC in developingproposals for the setting up of an adequate
training center and in assessing the equipment and facilitiesneeded for the
purpose. In addition,the Ashuganj Credit (CreditNo. 527-BD) and the IFAD
Credit (Credit 31-BA) have provided funds for the import of training aids
to be used initiallyfor training techniciansfor the Ashuganj project and
later to be made availablefor training techniciansfor the other fertilizer
plants. Since the UNDP project does not finance the setting up of the train-
ing center, the Governmenthas requested IDA financingunder the proposed
Credit. Thus the proposed training componentwould complementthe assistance
provided to Bangladeshin this crucial area throughother UNDP and IDA projects.
2.14 In the proposed Credit documents, BCIC has agreed to furnish its
detailed training plans for review by the Association before December 31,
1980. Completion of training plans acceptable to the Association will be a
condition of disbursement of the training component. Further, the Government
has agreed to introduce procedures and schedules governing the recruitment
of fertilizer technicians and engineers from Bangladesh to work abroad. For
this purpose, the Government will require newly recruited and trained fertil-
izer technicians and engineers to continue in service in Government-owned
plants for an appropriate period. The Government will also take measures to
minimize, with the cooperation of relevant agencies, the departure of
fertilizer technicians and engineers to such numbers as can reasonably be
replaced without adversely affecting the operation of the fertilizer plants.
BCIC has agreed that the three fertilizer plants will establish by December
31, 1980 and maintain subsequently an appropriate program of incentives for
their skilled technicians in order to retain them in service.
A. Fertilizer Consumption/Demand
Average Annual
FY (ending June 30) 1966 1970 1975 1976 1977 1978 1979 Growth Rates (%)
1966-79 1976-79
Total Fertllizer 106 277 280 457 513 715 740 16.1 17.4
Between FY77 and FY78, total fertilizer consumption increased by 40% due
to improved paddy support pricing and the Government's promotional efforts.
Actual consumption in FY79 was about 740,000 tons of product, well below the
earlier projected figure of 900,000 tons due to severe drought in that year
when fertilizer application levels were below normal under the excessively
dry soil conditions. With this unexpectedly sharp drop in consumption
growth, the mid-1979 stocks were about 370,000 tons of product resulting
in inadequate storage capacity to handle the additional imports ordered
previously and domestic production. Fertilizer consumption growth continued
to be depressed by drought conditions during early FY80.
3.04 Future Demand. The estimated demand for FY80 for all fertilizers
is between 850,000-900,000 tons, though the BADC target is 1,000,000 tons.
The projected offtake for FY81 ranges between 1.05 and 1.15 million tons with
urea forming about 61% of total demand, TSP/DAP about 31% and the remaining 8%
being made up of potash. Based on historical trends and planned agricultural
irrigation programs, demand for all fertilizers and urea is projected to
increase by about 15% per annum between FY81 to FY85, and by at least 10% per
annum during the rest of the decade as shown in the following table. This
would compare to actual growth rates for urea (para 3.03) of 14.6% during
FY66-79 and 15.7% during FY76-79 and even slightly higher growth rates reached
for all fertilizers combined. The projected consumption of all fertilizers
in FY85 is slightly lower than the latest Planning Commission estimates.
The Planning Commission, however, expects the nitrogen demand growth rate to
be significantly lower than the average for all fertilizers, which appears
unlikely.
- 8 -
Average Annual
Growth Rates %
FY (ending June 30) 1980 1982 1985 1987 1990 1980-85 1985-90
The urea requirements based on these assumptions would be about 1.13 million
tons by FY85 and 1.80 million tons by FY90. The present use of phosphatics
forms about 31% of the total fertilizer product. Even if the phosphate
consumption grows only at the same rate as that of urea, maintaining the
present ratio with nitrogenous fertilizers, the TSP/DAP consumption could
reach 574,000 tpy by FY85 and 924,000 tpy by FY90.
B. Fertilizer Supply
Potash
C. FertilizerSales Prices
1974 28 74 9.3
The Taka 1,301 million (US$84 million) subsidy in FY79, (and for that matter
in the previous years) imposed a heavy burden on the Government budget. If
unaltered, the burden would further increase as fertilizer consumption is
expected to rise in the coming years. Government policy, agreed with IDA
(Report P-2588-BD dated June 8, 1979) and USAID in the context of financing
fertilizer and foodgrain imports, is to gradually reduce the fertilizer
subsidy, and the Government has stated its intention to eliminate it altogether
by 1985. As a first step, average farmer fertilizer prices were increased by
about 28% in August 1979 reducing the average per ton subsidy from Taka 1,950
per ton in FY79 to Taka 1,376 in FY80. The Government's food procurement
program is also being structured to ensure attractive foodgrain prices to the
farmer so that fertilizer application continues to be economic despite in-
creases in farm fertilizer prices. The present paddy/fertilizer price ratio
of 1.3 in Bangladesh continues to be attractive (India 0.60, Philippines
0.80). In periods of scarcity, significant amounts of fertilizers are
reportly sold at black market prices substantially higher than the official
prices. These factors indicate that fertilizer prices can be further
increased without adversely affecting consumption growth rates.
D. Marketing Arrangements
3.09 Transport and Storage. Even though fertilizers form only a small
part of the total freight movement (about 3% at ports, 8.5% rail freight and
8% of inland water cargo), transport and storage system inadequacies have
limited fertilizer availability and use. While the Government is taking
several steps to remedy these inadequacies, improvement can only be gradual,
particularly in the railways. Current fertilizer storage facilities totalling
about 440,000 tons are not adequate even for FY81 and would continue to be
inadequate even after completion of the additional 63,000 tons of capacity
currently under construction, including about 35,000 tons of capacity with
USAID financing. An additional 173,000 tons of storage is programmed under
USAID financing and is expected to be completed by 1981-82. While the above
program will meet the requirements in the next few years, there would still be
need in the near future for some additional storage at particular locattons
and inaccessible areas and for substantial additional capacity to meet long-
term needs.
4.03 Since the formation of BCIC, its management has been primarily
occupied with two tasks: (i) restructuring the accumulated assets into
manageable and self-sufficient operating units; and (ii) improving the operat-
ing efficiency and levels of capacity utilization in various plants. During
this process, about 60 of the companies acquired earlier were either dis-
invested to the private sector, integrated into existing or newly created
units, or shut down where no other economic solution could be found. At
the end of this first phase of reorganization in mid-1979, BCIC's corporate
structure had improved considerably limiting the company's activities to 10
mainly chemical related product areas and 30 operating units (Annex 4-1).
B. FinancialPerformance
Operating Profit/Sales(%) 22 12 19 12
Current Ratio 1.2 1.2 1.4
Debt/Equity Ratio 88:12 72:28 70:30
- FERTILIZERINDUSTRYREHABILITATION
BANGLADESH PROJECT
BCICORGANIZATIONCHART
BOARD OF DIRECTORS
CHAIRMAN
- | | ~~~MANAGEMENT
l
PERSONNEL INFORMATION PBLIC RELATION SECRETARIAT
SERVICE
l COST l|MAINTENANCE| li
_
ACCOUNTING | _ CHEM. PLANT EXPORT
& BUDGETING |& EQUIPMENT
a/ Includes: Fertilizer, Paper, Paper Products, Boards, Matches, Rayon, Dilphane, Pharmaceuticals.
$/ Includes: Chemicals, Tanneries, Rubber Products, PVC Products, Resin Products, Insecticides,
Pesticides, and Other Miscellaneous Products.
4.06 Part of the problem lies in unusually high stocks of raw materials
and spare parts, considered by BCIC as necessary to ensure sufficient supply
due to long delivery times. Despite the recent substantial increases of
inventory of spares and components--mainly towards imported spares, chemicals
and catalysts--there is still a noticeable need to complement and to replace
the present stocks with specialty items in the forthcoming years. Inventory
of finished products is relatively low with about 1.8 months of production
costs (excluding depreciation). While the above observations are, in general,
also valid for the three individual fertilizer units, their capital structure
and profitability are better than that of the consolidated company, as shown
in the table below and detailed in Annex 4-2:
1/ While 1977 experienced a deflation of 5%, the inflation rates for 1978
and 1979 were 6% and 15%, respectively. However, many of the company's
product prices were hardly or not at all increased. Ex-factory fertil-
izer prices, for example, have remained practically unchanged since
April 1976.
- 16 -
Ghorasal
Chittagong
Fenchuganj
4.07 The operating performance of the three existing fertilizer units are
given in Annex 4-3 and summarized below:
First Half
FY (ending June 30) 1977 1978 1979 1980 1980
(actual) (target)
Ghorasal 56 40 65 69 67
Chittagong 40 27 41 30 b/ 60
Fenchuganj 67 55 50 81 87
Average 52 40 55 63 69
a/ Based on 330 operating days for Fenchuganj and Ghorasal, and 300
operating days for the TSP plants at Chittagong according to
industry practice.
b/ The low production during the first six months of FY80 was due to
raw material shortages and product movement problems.
- 17 -
C. Restructuring of BCIC
4.08 With the formation of separate profit centers and the assignment
of competent management to the operating units, the first phase of the Govern-
ment's efforts to restructure the chemical industry was completed in mid-1979.
However, the wide range of products of the industry and the relative scarcity
of managerial capabilities at corporate level have made it difficult to res-
pond quickly to the day-to-day requirements of the individual units, especially
in the technologically difficult fields like fertilizer and paper. The Govern-
ment has recognized the need to implement a second phase of reorganization to
overcome inefficiencies associated with the rigid nature of centralized proce-
dures. To give unit management maximum entrepreneurial initiative, decisions
requiring quick responses should be taken as far as possible at the plant unit
level.
4.10 The following three sections of this Chapter give a brief description
of the history, major technical features, recent performance, current operating
problems and major plant improvement needs of the three existing fertilizer
plants at Ghorasal, Chittagong and Fenchuganj.
- 18 -
4.12 The natural gas required for ammonia, steam and power production
is supplied from the Titas gas fields by a pipeline which delivers gas at
pressure to the plant. The raw water needed for the process and cooling tower
make-up requirements are taken from the Sitalakhya River, and the effluent
water is returned after treatment to the river. The steam requirements are
met from the process waste heat boilers and a gas-fired auxiliary boiler.
The fertilizer plant requires approximately 12.6 MW of power. At present,
two gas turbines installed as part of the Ghorasal facilities, each with a
rated capacity of 8 MW, supply the plant's power requirements. The system has
been engineered to use the national grid power if one of the turbines is under
maintenance. Urea is shipped both through a five-mile rail spur to Tongi and
from the plant's river wharf using barges and the inland waterways.
4.13 Following the test run in 1970, the Ghorasal complex suffered two
major shutdowns--in FY72, during the war of independence, and in FY75,
following an explosion in the control room. Urea production touched a peak of
236,000 tpy in FY79 against the rated capacity of 374,000 tpy. The production
performance of the Ghorasal plant since start-up in FY71 is shown below:
Fiscal Year Annual Urea Capacity Average Daily Production Operating Days
(ending June 30) Production Utilization Urea Ammonia Urea Ammonia
(%)
Ammonia production continues to be the major constraint and there have been
difficulties in reaching and maintaining rated levels of production as well
as in achieving consistently even 300 annual operating days, while the annual
production capacity is based on the general industry practice of 330 operating
days per year. FY79 has been the best performance year so far and production
could have been significantly higher but for interruptions due to events
outside plant management's control. Of the FY79 total ammonia plant downtime
of 103 days, nonavailability of gas supply (25 days) and national grid power
supply interruptions (17 days) together accounted for 42 days of downtime; 61
days of downtime was due to normal and unforeseen maintenance. The gas supply
was interrupted due to the fall in hydel power production following the
drought and the resulting priorities assigned to gas supply for increased
thermal power generation. The excessive downtime for maintenance was due
primarily to the lack of appropriate preventive maintenance, spare parts and
poor physical condition of some equipment. During the first six months of
FY80, urea production was about 143,000 tons. The FY80 urea production is
expected to be 240,000 tons, equivalent to a capacity utilization rate of 64%.
4.14 Under the First and Second Technical Assistance Credits (Credit Nos.
409-BD and 622-BD), Bresler and Associates, Inc. (BAI) of the US carried out
studies to review the performance of the Ghorasal facilities and to recommend
specific measures to improve their operation and maintenance. The findings of
the BAI study presented in the consultants' final report submitted in August
1979 (Reference B - Prolect File) were reviewed by IDA staff with the plant
and BCIC managements. Several of the recommendations have been implemented
during the latest plant shutdown for maintenance in 1979 and some others will
be during the scheduled shutdown in the next few months. The performance of
the facilities was also reviewed in April 1979 by Toyo Engineering Corpora-
tion, who formulated their preliminary recommendations in their report dated
September 12, 1979 (Reference C - Project File). The recommendations of the
consultants proposed to be implemented as part of the present Project are
summarized in Annex 4-4.
4.17 The FY79 production was only equivalent to 41% of the rated annual
capacity, primarily due to the very low plant operating days of 150. During
the days the plant was operating, production averaged 75-80% of the daily
rated capacity. Factors responsible for the plant downtime and their share
in total operating days lost are summarized below:
Equipment failures and maintenance problems accounted for 53% of the total
lost days. Shortage of raw materials, power supply interruptions, and BADC's
difficulties in moving fertilizers, all of which were outside the control of
the plant authorities, were also important factors accounting for 47% of the
lost days. These same factors are expected to adversely affect the FY80
production which may be only about 70,000 tons of TSP. Production during the
first six months of FY80 was only about 23,000 tons mainly due to shortage of
raw materials.
4.18 The BAI study mentioned earlier also included the Chittagong TSP
plants (para 4.14). These facilities were reviewed by Jacobs Engineering
Group, Inc. (JEG) of the US under a subcontract with BAI. The Chittagong TSP
complex was also studied by Cremer and Warner Ltd. of the UK in January 1978
and recommendations made to the UK Ministry of Overseas Development (Reference
D - Project File). The rehabilitation and conversion options for the TSP
complex were studied by JEG in April 1979 (Reference E - Project File) under
a separate subcontract to Soros Associates Consulting Engineers of the US as
part of the study on bulk shipment and unloading of fertilizer imports in
Bangladesh. In addition to the major technical recommendations, the various
studies highlighted the need for: (i) adequate and acceptable quality water
supply; (ii) more reliable power supply; (iii) long-term arrangements for
gypsum disposal; (iv) resolutions of other environmental problems; and (v) a
study of the economics of continuing TSP production at Chittagong. These
aspects are discussed further in the following paragraphs.
4.19 The two TSP plants were initially designed to use water drawn from
tubewells within the plant area and having a salinity not exceeding 100 parts
per million (ppm) of chlorides, for the process and boiler feed water require-
ments. The quality of the tubewell water has deteriorated with salinity
increasing up to 1,400 ppm and as a result the water treatment and demineraliz-
ing facilities have proved inadequate. Limiting the use of the tubewells to
periods when the quality is acceptable and supplementing the supplies with
public utility water have not been adequate to meet the plant process water
requirements. Hydrological surveys have also not identified possibilities of
improved water supply with new tubewells. BCIC studies have, however, con-
firmed that Karnaphuli river water has acceptable salinity during 1-2 hours
per tide. BCIC has, therefore, already made arrangements to meet most of the
plant process water requirements by pumping water from the river during low
salinity periods and thus providing adequate plant raw water storage; con-
sidering the small size of the plants which require modest amount of water,
this solution would not require construction of large storage capacity. BCIC
supplements the water supply by stand-by arrangements with the public water
supply authority. With these arrangements the plants are assured of adequate
water supply.
- 22 -
4.20 Power interruptions are mainly due to the failure of the Chittagong
grid supply. The deficiency of the Chittagong grid supply is recognized by
the Government and a project is currently being implemented to improve the
supply by installing additional substations in the area. The Chittagong TSP
plant has two diesel generators which provide emergency power supply to keep
the vital plant units (such as the agitators in the phosphoric acid reaction
vessels) in operation during grid power supply failures. The diesel generator
capacity however is not adequate to provide emergency power to all those units
which should be kept in operation during power failures. To minimize produc-
tion losses and limit equipment damage, BCIC intends to install additional
diesel generating capacity which, along with the expected improvements in
the Chittagong power grid quality, will make the power supply situation
satisfactory.
capacity utilization rate) after renovation, the annual economic cost of TSP
production would be lower than the import cost by about Taka 104.5 million or
US$6.7 million (in 1979 dollars). It is, therefore, considered economically
advantageous to Bangladesh to continue with the Chittagong Plant TSP produc-
tion. This conclusion differs from the findings of a study carried out by
Soros Associates in April 1979 on the economics of bulk import of fertilizers
through the Chittagong and other Bangladesh ports (Reference F - Project File)
that there could be economic advantages in shutting down TSP production to
permit the plant's wharf, handling, storage and bagging facilities to be used
instead for bulk fertilizer imports. This study concluded that the savings
from import of bulk fertilizer (instead of bagged fertilizer) using the
factory's facilities would be greater than the savings from continued TSP
production in Bangladesh vis-a-vis imports. However, a further detailed study
by a Bank consultant has concluded that the plant facilities have adequate
capacity to handle fertilizer imports without shutting down TSP production. A
recent IFAD project (Report 2729-BD) includes a component to quickly upgrade
existing facilities at the TSP jetty to handle small bulk ships, lighters,
mini-bulkers and, if the river were dredged, large bulk ships. The IFAD
project bulk unloading component would assist in meeting immediate requirements
while long-term solutions such as an offshore unloading platform or use of
shuttle bulkers with wharf bagging are being investigated and carried out.
4.27 The Fenchuganj complex, located about five miles from the Fenchuganj
town in Sylhet district, includes a 200 tpd ammonia plant, a 333 tpd urea
plant, a 35 tpd sulfuric acid plant and a 40 tpd ammonium sulfate plant. The
facilities also include steam turbine power generating facilities, cooling
towers, maintenance shops and other auxiliary facilities. The plant and
facilities were supplied and erected by Kobe Steel (Japan) based on ammonia
and urea technologies from Chemical Construction Corporation (US) and the
sulfuric acid and ammonium sulfate technologies from Lurgi-Mitsubishi (FRG-
Japan). The ammonia and urea plants were completed in 1961 and commenced
commercial production in 1962. The sulfuric acid and ammonium sulfate plants
were completed in 1969 and began commercial production in 1970. Natural gas
for process and energy needs are met from the Haripur gas fields. Most of
the urea is shipped via rail spur to the main rail system through Maijgaon.
Annual Average
FY (ending June 30) Annual Urea Production CapacityUtilization%
1964 53,300 46
1966 98,700 85
1968 122,200 106
1970 96,700 84
1973 35,900 31
1977 77,500 67
1978 61,400 53
1979 59,500 51
1980 (Projected) 95,000 82
V. THE PROJECT
5.01 The Project has been designed to improve the performanceof BCIC's
existing fertilizerplants. It consistsof three components: (i) improve-
ments to be carried out at Ghorasal, Chittagongand Fenchuganj(Plant Improve-
ment Component); (ii) constructionof a training center at Ghorasal to ensure
availabilityof skilled staff to operate the plant facilities (Training
Component);and (iii) import of critical plant spares, catalystsand chemicals
- 26 -
to meet the needs of the plants for the next two years (Spares, Catalysts and
Chemicals Ccmponent). The specific modifications and improvements required at
the three plants for better performance were identified by consultant studies
(para 4.11 to 4.29) and further reviewed by a BCIC Technical Committee for
preparing feasibility reports. In formulating the details of the improvement
programs, the Technical Committee has taken into account the more recent
performance experience of the plants and the modifications already carried
out or planned to be carried out in turnarounds before the implementation of
the proposed Project. The three project components are described below.
5.03 The requirements of the Chittagong plant were identified by the BAI
and Cremer and Warner studies (para 4.18). Parts of the requirements were
implemented during late 1979. The improvement program intended to be carried
out under the proposed Project (Reference H - Project File) includes the
following categories of works: (a) provisions of replacement and standby
equipment where required; (b) improving plant utilities including steam, power
and treated water facilities; (c) improvements in instrumentation; and (d) TSP
granulation facilities (Annex 4-4).
5.04 The Fenchuganj facilities were fully renovated during the summer
of 1978 (para 4.29) and the present program (Reference I - Project File) is
limited to: (a) improvement of the present instrumentation for better process
control; (b) replacement of heat exchangers for some of the critical duties;
and (c) a set of turbine blades and diaphragm for the power generation unit.
These items would improve reliability and reduce downtime.
B. Training Component
5.05 Under UNDP financing, technical assistance has been made available
to BCIC in the preparation and implementation of training plans at Ghorasal
(para 2.12). The UNDP project does not include financing for setting up the
training facilities. IDA staff will review the training plans prepared by
- 27 -
A. Project Management
| GENERAL MANAGER
L
VVORKING
GROUP
WORKING
GROUP
WORKING
GROUP GGROUP
WORKING
B. EngineeringArrangements
C. Project Schedule
A. Capital Cost
7.02 The base cost estimates are in December 1979 prices and were pre-
pared by Bank staff, based on BCIC staff's estimates followingpreliminary
designs and informationsubmitted by engineering firms combined with the
Bank's own cost informationobtained from contractors'budgetary quotations.
Physical contingenciesare calculatedgenerally at 15% of the base cost
estimate, in light of the rehabilitationnature of this project component.
Price contingenciesare based on annual escalationrates for equipmentand
materials of 12% for 1980 and 10% thereafter,slightly higher than the
latest CPS guidelines. These estimated escalationrates were used for both
local and foreign expenditures (when expressed in US dollars) on the assump-
tion that differencesin the internationaland domestic inflation rates will
be accounted for by changes in the exchange rate which is periodically
repegged. It is estimated that all equipment and materials will be imported
and that about 60% of engineeringand managementassistancewill be provided
by foreign suppliers. The cost of engineeringservices are expected to form
about 5% of the base cost estimate, excluding duties for Ghorasal and
- 31 -
I Plant ImprovementComponent
Ghorasal 6.1 11.7 17.8 38
Chittagong 5.3 9.7 15.0 32
Fenchuganj 1.5 3.0 4.5 10
B. FinancingPlan
Equity
Governmentof Bangladesh 12.9 - 12.9
IDA Credit to Government - 2.0 2.0
Sub-total 12.9 2.0 14.9 40
Debt
Dutch Assistanceto Government - 4.7 4.7
IDA Credit to Government - 17.7 17.7 60
Sub-total - 22.4 22.4
The above componentwill be financedwith 40% equity and 60% debt. The
Governmentwill provide as equity US$12.9 million equivalentto finance
local project costs. The terms of on-lendingof the Dutch financing (US$4.7
million) have not yet been determined. The project debt financingof US$22.4
million equivalentis assumed to be financedwith Dutch and IDA assistance
on-lentby the Governmentto the new fertilizercompanies. To the extent
such on-lendingmay bring the ratio of debt financingto equity financing
for any of the new companiesabove 60:40, a part of IDA assistancenow esti-
mated at US$2 million may be passed on as equity. The proposed IDA credit
portion of US$19.7 million will cover 53% of total financingrequirementsand
is equivalentto 81% of the estimatedforeign exchange cost of the Plant
ImprovementComponent. US$18.7 million out of an IDA credit totallingUS$20.7
million for the Plant Improvementand TrainingComponentswould be on-lentby
the Governmenton standard terms to the new fertilizercompaniesat a rate of
interestof 10%, for 10 years including3 years of grace. The exchangerisk
will be borne by the new fertilizercompanies. These terms are comparable
with the terms currentlybeing applied to other foreign currencyloans presently
on-lent to BCIC and other similar enterprises. Finalizationof satisfactory
on-lendingagreementsfor the plant improvementand trainingcomponentswill
be a condition of credit effectiveness.
C. Procurementand Disbursement
7.06 The proposed credit covers plant improvementsin the three existing
plants, the setting up of training facilitiesand importsof spares, catalysts
and chemicalsfor the operationof the three existingplants. The proposed
procurementarrangementshave taken into account the specificneeds of the
three componentsand proceduresmost appropriatefor them. The procurement
packages for the plant improvementcomponentwill generallybe of small value
and in large part of proprietarynature. It is expected that only about 15
packageswill exceed US$50,000 in value and several of them are best procured
from the originalequipmentvendors. Only 7 packageswith total value of
about US$3 million may be appropriatefor internationalcompetitivebidding
(ICB). The rest of the equipmentand supplies totallingabout US$13 million
in value will include proprietaryitems (about US$8 million)and small value
items (about US$5 million) procured followingBank procurementguidelines.
The same arrangementswill also cover suppliesfor the training component.
In view of the nature of the project, such procurementproceduresare
appropriateto ensure timely and efficient plant renovation.
Equipment,Materials&
Spares procuredunder ICB 2.5 1.0 - 3.5 100% of foreign
and local
ex-factory
Critical,Proprietaryor
Small Items 5.5 1.5 2.5 9.5 100% of foreign
Unallocated - - 6.6
Total 29.0
VIII. FINANCIALANALYSIS
A. General
As a result of the low cost of the abundantly available natural gas (between
US$0.30 and US$0.40 per Mscft), urea production costs including depreciation
are very competitive at Ghorasal with similar plants elsewhere. Although
Fenchuganj costs are substantially higher than Ghorasal because of smaller
plant size and the use of power-intensive technology, they are nevertheless
well below international prices. While the current price of natural gas
permits the covering of operating expenses and capital charges of related
facilites, it is on the low side considering the present costs of developing
new gas fields and providing transport facilities. The Bank is currently
appraising a pipeline project in Bangladesh and the issue of an appropriate
gas price for commercial users will be reviewed in the context of that project.
Natural gas accounts for only about 20% of urea production cost--as indicated
in the table above--so that even a 50% rate increase would not significantly
affect the project's financial viability.
Capacity Utilization in % 67 85 60 80 87
Operating Margin 26 32 18 22 20
Return on Assets b/ Before
Interest and Tax 12 19 9 16 8
Return on Assets Before
Interest and After Tax c/ 10 13 7 10 7
a/ Assuming that the capital structure of June 1979 for the three
entities remains basically unchanged.
b/ Defined as total assets minus non-interest bearing current liabilities.
c/ Corporate tax rate is 55%.
d/ Amount of debt service is notional, based on 1979 balance sheets.
8.05 The operating profits for both plants at Ghorasal and Chittagong
are expected to improve substantially, i.e., by 58% and 67%, respectively,
after completion of their plant improvement projects. Similarly, the return
on assets before interest and after tax will increase from 10% to 13% for
Ghorasal and from 7% to 10% for Chittagong, which are considered as acceptable
- 37 -
levels of income. In both cases the cash flow after debt servicewill approxi-
mately double. With regard to Fenchuganj,the project will help sustain the
estimated operatingprofit. The return on assets of 7% is lower than for the
two other plants,mainly as a result of higher operating costs which are not
adequatelycovered by the present FenchuganJex-factoryprice of urea. A
price increaseof about 10% to Taka 2,635per ton of urea would achieve a
return on assets of approximately10x. The relativelysmall cash flow after
debt service at Fenchuganjis a direct consequenceof high requirementsof
net working capital which by requiring large short-term debt substantially
increases the debt service.
8.06 The financial rates of return before tax, in constant 1979 terms,
on an incrementalbasis for the plant improvementcomponentsat Ghorasaland
Chittagongare calculatedat about 30% and 22%, respectively. The cost/benefit
streams for the base cases are given in Annex 8-2 and the results of the
sensitivityanalysisare summarizedbelow:
Rate of Return
Ghorasal Chittagong
The financial rate of return is most sensitive to changes in the assumed rates
by which the capacity utilization is projected to improve. Nevertheless, even
in a severe case of a combinationof a capital cost increaseof 25% and an
improvementof capacityutilization25% below target would result in a still
satisfactoryrate of return of 15% for Ghoras4l and a marginallyacceptable
rate of return of 9% for Chittagong. However, due to commercially proven
technology, experienced contractors and increased operating training assis-
tance, the likelihoodof a combinationof such adverse sensitivitiesappears
to be remote.
D. FinancialCovenantsand ReportingRequirements
8.07 BCIC has agreed that the three new fertilizercompaniesto be formed
under BCIC's restructuringplan (para 4.09) will follow prudent financial
practices and conform to the following financial covenants: (i) maintain at
all times a debt/equity ratio of 60/40 or better; (ii) maintain a current
- 38 -
8.08 BCIC has agreed that the successor companieswill submit: (i) annual
audited financial reports within six months of the closing of each fiscal year;
and (ii) monthly progressreports and periodic financial statementsand pro-
jections according to a schedule and form satisfactoryto the Bank.
E. Major Risks
8.09 The Project faces only limited technical risks since the technology
associatedwith the plant improvementcomponent is commerciallyproven and
will be suppliedby internationallyexperiencedfirms. However, the sustained
performanceof the plants at the projected operating levels will depend to a
substantialextent on the availabilityof an adequate and competentmanagement
and work force. The availabilityof sufficientlyexperiencedpersonnel is
expected to be reasonablyensured by including a trainingcomponent in the
credit and by other measures that would help to retain the trainedmanpower
at technical and managerial levels (para 2.14).
8.10 The Project also would face some potential financial risks if not
for the pricing arrangementsproposed. The continuedsatisfactoryfinancial
performanceof the sponsoringcompanies is largely dependent on the recommended
change in the Government'spresent fertilizerpricing policy at producer level
and subsequentimplementationof a pricing mechanism which allows for timely
price adjustmentsduring periods of rapidly rising productioncosts. This
risk is expectedto be adequatelymet by the proposed agreementswith the
Government,which will allow the companies to earn a minimum agreed return
on their assets (para 2.08).
IX. ECONOMICANALYSIS
9.01 For the economic analysis,costs and benefits are divided into
tradeableand non-tradeableitems. The economic costs and benefitsof the
tradeablesare calculatedby using projected long-terminternationalprices,
while those of non-tradeablesare determinedby using domesticprices after
making necessaryadjustmentsfor local taxes, except for natural gas for which
a higher opportunitycost of US$1.00/Mscftis used (Annex 8-1). Bangladeshhas
adequategas reservesto meet the country'sand the Project'sneeds. In
addition,Bangladeshhas a small fuel oil surplus thus preventingits economic
substitutionby natural gas. Therefore,the opportunityvalue of naturalgas
used by the Project should be based on the higher of (i) economiccost of gas
productionsand delivery,or (it) anticipatedvalue of exports of natural gas
in the form of LNG. Bangladeshis in an unfavorablepositionfor the produc-
tion and export of LNG due to its somewhat limited gas reserves relative to
the very substantial gas requirements for an economically sized LNG plant, its
inadequatelydeveloped infrastructurebase and the limited port capabilities.
Furthermore,studies carried out tn the past on possibleLNG projects in
Bangladesh have not established the economic viability of such a project.
As a result, the gas price at which LNG can be exported competitively from
Bangladesh would be lower than in other possible locations. Even with the
increasinginternationalLNG prices, the netback for natural gas from a
possibleproject in Bangladeshis, therefore,not likely to exceed US$1.00
per Mscft in 1979 terms. The economiccost of gas productionand delivery
to Chittagongis estimated at about US$0.66 per Mscft (ReportNo. P-25-68-DP
dated May 18, 1979). While the base case uses US$1.00 per Mscft, a sensitiv-
ity analysiswas undertakenfor Ghorasalapplying a 50% increaseabove the
apparentmaximum value of US$1.00 per Mscft. The Project'seconomiccost is
derived from the financialcapital cost estimate after deductingapplicable
import duties and taxes on equipmentand are expressedin US Dollar based on
an exchangerate of US$1.00 - Taka 15.5.
urea an FOB price of US$245/ton 1/, US$40/ton for ocean freight and US$10/ton
for port-handling and inland transportation differential are assumed. In the
case of TSP, a FOB price of US$195/ton is assumed with ocean freight and port
handling cost of US$50/ton and US$10/ton, respectively. The computation of
economic costs and prices are shown in Annex 8-1 and its results are given
below:
US$/ton
Raw Material
Sulfur 115
Phosphate Rock 73
Output
TSP 270
Urea 280
9.04 The cost/benefit streams used for calculating the economic rates
of return are given in Annex 9 and results of the sensitivity analysis are
summarized below:
Rate of Return
Case Ghorasal Chittagong
X. AGREEMENTS
10.01 Satisfactory assurances and agreements have been obtained from the
Government that it will:
(d) cause BADC and the three new fertilizer companies to enter
into a satisfactory agreement before October 31, 1980 on
arrangements for pick-up of fertilizers from the plant
warehouses with provision that BADC payment will include
an agreed compensation to cover additional cost of higher
stacking or renting additional warehouse space if fertilizer
is not picked up according to a predetermined schedule and
that arrangements will be evolved to permit BCIC to sell
fertilizers directly to wholesalers, as well as to BADC
(para 3.10);
(a) it will furnish its detailed training plans for review before
December 31, 1980 (para 2.14);
IndustrialProjects Department
April 23, 1980
- 44 -
ANNEX 3
FERTILIZEROFFTAKE IN BANGLADESH1965-79
1965 93.8
Source: BangladeshAgriculturalDevelopmentCorporation
IndustrialProjects Department
April 1980
ANNEX 4-1
I Fertilizer
1. Urea FertilizerFactory 370
2. Natural Gas Fertilizer Factory 119
3. Triple Super Phosphate Fertilizer 297
Complex
IV Safety Matches
1. Dacca Match Factory 50
2. Dada Match Factory 39
3. Ujala Match Factory 22
4. Habib (Match) Industries 24
V Rubber
1. Bengal Belting Corporation 30
2. Karim Rubber Industries 33
3. Lira IndustrialEnterprise 9
4. Bella Artifitex Industries 7
Sub-total 79 3 120 4
- 46 - ANNEX 4-1
Page 2
FY79 FY80
Projected
Production Unit Sales X Sales %
Sub-total 52 2 95 3
Sub-total 44 2 50 2
VIII Pharmaceuticals
1. Albert David (Bangladesh)Ltd. 37 2 50 1
TX Chemicals
1. The Chemical Industriesof Bangladesh 27
2. Farookh Chemical Industries 4
Sub-total 31 1 40 1
IndustrialProjectsDepartment
April 1980
BANGLADESH - FERTILIZER INDUSTRY REHABILITATION PROJECT
Ratios
a/ Source: BCIC
- 48 - ANNEX 4-2
Page Z
Assets
Cash and Banks 51.2 58.8 134.1 78.1
Accounts Receivable 460.6 828.1 1,018.0 1,464.4
Inventory 1,090.5 1,089.4 1,240.2 1,600.3
Raw Material 379.4 385.8 459.0 632.3
Stores and Spares 416.2 346.2 565.1 729.2
Finished Goods 294.9 357.4 216.1 238.8
Loans and Advances 177.2 247.2 298.1 355.2
Liabilities
Accounts Payable 1,139.4 960.3 888.8 806.5
Bank Loan 262.9 116.7 185.8 235.3
Other Current Liabilities 514.3 772.4 1,121.9 1,534.3
Ratios
Current Ratio 1.6 1.2 1.2 1.4
Quick Ratio 0.4 0.6 0.7 0.7
Debt Service Coverage 0.1 1.7 0.9 1.5
Debt/Equity Ratio 88:12 72:28 70:30
a/ Source: BCIC
BANGLADESH - FERTILIZER INDUSTRY REHABILITATION PROJECT
Ratios
47 14 36 30 * X
Gross Margin in % 15
40 6 23 21 >
Net Margin (Bef. Taxes) in % 10
a/ Source: BCIC
ANNEX 4-2
Page 4
GHORASALBALANCESHEETS
(In Million Takas)
Assets
Cash and Banks 1.8 1.3 20.3 1.3
Accounts Receivable 176.1 374.8 439.5 621.9
Inventory 94.7 112.6 183.4 227.5
Raw Material - 30.9 50.9 2.7
Stores and Spares 94.5 78.6 132.5 219.9
Finished Goods .2 3.1 .0 4.9
Loans and Advances 12.4 3.5 8.2 10.1
Total Current Assets 285.0 492.2 651.4 860.8
Gross Fixed Assets 773.1 811.8 817.0 822.6
Less Accumulated Depreciation 195.5 298.1 373.3 448.5
Net Fixed Assets 577.6 513.7 443.7 374.1
Investments - .3 _
T o t a 1 A s s e t s 8634.9
862-6 _55.9 1,095.4
Liabilities
Accounts Payable 196.4 193.6 259.4 185.5
Bank Loan _ _ _ _
Other Current Liabilities 3.6 7.6 54.4 137.1
Total Current Liabilities 200.0 201.2 313.8 322.6
Long-Term Debt 775.7 771.9 601.9 601.9
Share Capital 8.4 8.4 177.9 177.9
Retained Earnings (121.5) 24.4 1.8 132.5
Total Equity (113.1) 32.8 179.7 310.4
T o t a 1 L i a b. & E q u i ty 862.6 1_005.9 1,095.4 1.234.9
Ratios
Current Ratio 1.4 2.5 2.1 2.7
Quick Ratio 1.0 1.9 1.5 2.0
Debt Service Coverage 1.3 2.7 1.3 1.3
Debt/Equity Ratio - 96:4 77:33 66:33
a/ Source: BCIC
BANGLADESH - FERTILIZER INDUSTRY REHABILITATION PROJECT
a/
BCIC - FINANCIAL STATEMENTS 1976-80 -
Ratios
a/ Source: BCIC
- 52 -
ANNEX4-2
Page 6
CHITTAGONGBALANCESHEETS
(In Million Takas)
Assets
Cash and Banks 3.1 1.2 7.4 5.3
Accounts Receivable 20.9 70.5 130.4 259.1
Inventory 96.8 124.6 153.6 322.2
Raw Material 47.1 6.8 14.9 49.3
Stores and Spares 13.4 .0 127.6 251.1
Finished Goods 36.3 117.8 11.1 21.8
Loans and Advances 4.0 3.5 6.2 7.8
Liabilities
Accounts Payable 103.8 20.9 13.5 9.4
Bank Loan 70.0 - - -
Other Current Liabilities 116.7 288.3 328.7 565.1
Ratios
Ratios
Current Ratio .4 .7 .9 1.0
Quick Ratio .1 .2 .4 .5
Debt Service Coverage - 1.9 1.8 2.9
Debt/Equity Ratio - 28:72 27:73
a/ Source: BCIC
BANGLADESH - FERTILIZER INDUSTRY REHABILITATION PROJECT
__ . ~~~~~~a/
BCIC - FINANCIAL STATEMENTS 1976-80
Ratios
Gross Margin in % (8 ) 41 33 43 30 A
Net Margin (Bef. Taxes) in % (29 ) 34 24 32 13 sX
a/ Source: BCIC
- 54 - ANNEX 4-2
Page 8
Assets
Cash and Banks 2.3 1.5 13.7 3.5
Accounts Receivable 47.3 94.6 125.0 171.2
Inventory 120.4 139.5 134.9 162.0
Raw Material 14.0 - 1.3 46.8
Stores and Spares 104.0 120.4 130.2 100.7
Finished Goods 2.2 19.1 3.4 14.5
Loans and Advances 13.5 5.1 27.1 56.8
Liabilities
Accounts Payable 82.3 76.6 49.9 58.0
Bank Loan - - - -
Other Current Liabilities 6.2 19.5 56.4 14.6
Ratios
Current Ratio 2.1 2.5 2.8 5.4
Quick Ratio .7 1.1 1.6 3.2
Debt Service Coverage .3 5.0 4.0 3.0
Debt/Equity Ratio 35:65 31:69 36:64 61:39
av Source: BCIC
Chittagong
a/ Based on 330 operating days for Fenchuganj and Chorasal, and 300 operating
days for the TSP plants at Chittagong according to industry practice.
4-
ANNEX 4-4
- 56 -
A. GhorasalPlant ImprovementProgram
B. ChittagongPlant ImprovementProgram
- Additional agitators.
C. FenchuganjPlant ImprovementProgram
IndustrialProjects Department
April 1980
BANGLADESH - FERTILIZER INDUSTRY REHABILITATION PROTECT
PLANT IMPROVEMENT COMPONENT - CAPITAL COST ESTIMATE
(in million US Dollars)
Equipment and Supplies - 7.31 7.31 - 6.46 6.46 - 2.10 2.10 - 15.87 15.87
Freight and Insurance 0.07 0.73 0.80 0.06 0.65 0.71 0.02 0.21 0.23 0.15 1.59 1.74
Taxes and Duties 1.62 - 1.62 1.43 - 1.43 0.47 - 0.47 3.52 - 3.52
Inland Handling 0.41 - 0.41 0.04 - 0.04 0.10 - 0.10 0.55 - 0.55
Foundation and Structures 0.39 - 0.39 1.00 - 1.00 0.05 - 0.05 1.44 - 1.44
Erection 0.52 - 0.52 0.45 - 0.45 0.16 - 0.16 1.13 - 1.13
Engineering and Management 0.64 0.82 1.46 0.20 0.30 0.50 0.05 - 0.05 0.89 1.12 2.01
Base Cost Estimate (BCE) 3.65 8.86 12.51 3.18 7.41 10.59 0.85 2.31 3.16 7.68 18.58 26.26 X
Physical Contingency 0.55 1.33 1.88 0.47 1.11 1.58 0.13 0.35 0.48 1.15 2.79 3.94
(PC) at 157. of BCE
Price Escalation 0.60 1.46 2.06 0.52 1.21 1.73 0.14 0.38 0.52 1.26 3.05 4.31
(14.37, of BCE + PC)
Total Project Cost 4.80 11.65 16.45 4.17 9.73 13.90 1.12 3.04 4.16 10.09 24.42 34.51
Interest during Construction 1.30 - 1.30 1.11 - 1.11 0.33 - 0.33 2.74 - 2.74
Financing Required 6.10 11.65 17.75 5.28 9.73 15.01 1.45 3.04 4.49 12.83 24.42 37.25
1. Variable Costs
Natural Gas (Mscft) 48.2 6.25 301.3 95.8 15.5 747.1 237.6
Chemicals - - 108.6 34.5 - 103.2 32.8
Duty on Electricity (MKWH) .381 10.0 3.8 1.2 - -
Packing Materials 37 9.46 350.0 111.3 8.50 314.5 100.0
Others - - 73.3 23.3 70.4 22.4
Total Variable Costs 837.0 266.1 1,235.2 392.8
2. Fixed Costs
Economic Assumptions
1. Natural Gas Tk 15.5 or US$1.00 per Mscft reflects economic price (para 9.01).
2. Chemicals Financial cost less 5% for local taxes and duties.
3. Packing Materials: Financial cost less 10% for import duties (35%) on PE lining.
4. Maint. Materials : Financial cost less 5% for import duties.
Port Handling,
Ocean Transportation
FOB Freight Differential Economic Cost
- - - -US$-US$
- - - - - - - Tk
5. Urea 230 40 10 280 4,340.0
- 61 - ANNEX8-1
ESTIMATEDPRODUCTIONCOST SUMIMARY
AND OUTPUTVALUE
1. Variable Costs
2. Fixed Costs
4. Value of Output
1. Variable Costs
2. Fixed Costs
4. Value of Output
omic Assumptions
1. Natural Gas Tk 10.3 or US$.66 per Mscft reflects charges applied to non-preferential industrial users and
is used as economic price due to the remote location and limited size of the Hiaripur gas fields.
2. Chemicals Financial cost less 5% for local taxes and duties.
3. Packing Materials Financial cost less 102 for import duties (35X) on PFE lining.
4, Maint. Materials Financial cost less 5% for import duties.
Port Handling,
Ocean Transportation
FOB Freight Differential Economic Cost
- - - - - - - US$- - - - -- - - - - - - US$ Tk
Incremental Incremental
Capital Variable Output Net
FY ending June 30 Costs 2/ Costs Value Benefit
Chittagong
1981 3.5 - - (3.5)
1982 7.6 - - (7.6)
1983-1992 - 5.5 8.5 3.0
Ghorasal
1981 4.1 - - (4.1)
1982 9.0 - - (9.0)
1983-1992 - 3.7 8.3 4.6
Incremental Incremental
Capit2a3 Variable Output Net
FY ending June 30 Costs- Costs Value Benefit
Chittagong
Ghorasal
2/ Financial cost less import duty of US$1.9 million and US$2.1 million for Chittagong and
Ghorasal, respectively.
x
IBRD 14866
:D
ra 0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~a
LU g
(b
LU /
zL E
< 'Z
-J~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~x