Electrical Cable, Cable Tray and Accessory (Electrification Work of Saponification and ETP Plant) After MCC
Electrical Cable, Cable Tray and Accessory (Electrification Work of Saponification and ETP Plant) After MCC
Finish Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 Transformer 298 days October 29, 2021 December 20, 2022
2 received offer from ABB 2 days October 29, 2021 November 1, 2021 Project team
4 Approval 5 days November 9, 2021 November 15, 2021 Jemal,Mufid,Project team,Supply Chain
5 Contract term and condition approval 4 days November 2, 2021 November 5, 2021 Supply Chain
8 Manufacturing ,Shipment and clearance 227 days January 24, 2022 December 6, 2022
9 Transformer Installation 10 days December 7, 2022 December 20, 2022
10 Electrical cable , cable tray and accessory 213 days October 29, 2021 August 23, 2022
(Electrification Work of Saponification and
ETP plant )(Before MCC it is not required
Manufacturing)
11 Finalized offer 1 day October 29, 2021 October 29, 2021 Project team
14 Approval 5 days November 4, 2021 November 10, 2021 Jemal,Mufid,Project team,Supply Chain
15 Contract term and condition approval 4 daysNovember 11, 2021 November 16, 2021 Supply Chain
17 LC opening and PO create 10 days January 3, 2022 January 14, 2022 Supply Chain
18 Manufacturing and Clearance 157 days January 17, 2022 August 23, 2022
19 electrical cable , cable tray and 213 days October 29, 2021 August 23, 2022
accessory (Electrification Work
of Saponification and ETP plant
) After MCC
20 Finalized offer 1 day October 29, 2021 October 29, 2021 Project team
21 Final negotiation 2 days November 1, 2021 November 2, 2021 Jemal,Project team,Supply Chain
23 Approval 5 days November 5, 2021 November 11, 2021 Jemal,Mufid,Project team,Supply Chain
24 Contract term and condition approval 4 daysNovember 12, 2021 November 17, 2021 Supply Chain
26 LC opening and PO create 10 days January 3, 2022 January 14, 2022 Supply Chain
27 Manufacturing and Clearance 157 days January 17, 2022 August 23, 2022
28 Automatic Tank gauging (ATG) 144 days October 29, 2021 May 18, 2022
29 Finalized offer 2 days October 29, 2021 November 1, 2021 Project team
30 Final negotiation 2 days November 2, 2021 November 3, 2021 Jemal,Project team,Supply Chain
32 Approval 4 daysNovember 10, 2021 November 15, 2021 Jemal,Mufid,Project team,Supply Chain
33 Contract term and condition approval 4 daysNovember 16, 2021 November 19, 2021 Supply Chain
35 LC opening and PO create 10 days January 4, 2022 January 17, 2022 Supply Chain
36 Manufacturing and Clearance 87 days January 18, 2022 May 18, 2022
37 Industrial process control system 179 days October 29, 2021 July 6, 2022
(IPCS) of ETP plant
38 Finalized offer 2 days October 29, 2021 November 1, 2021 Project team
39 Final negotiation 1 day November 2, 2021 November 2, 2021 Jemal,Project team,Supply Chain
41 Approval 4 days November 5, 2021 November 10, 2021 Jemal,Mufid,Project team,Supply Chain
42 Contract term and condition approval 4 daysNovember 11, 2021 November 16, 2021 Supply Chain
44 LC opening and PO create 10 days January 4, 2022 January 17, 2022 Supply Chain
45 Manufacturing and Clearance 122 days January 18, 2022 July 6, 2022
Project: Electrical Material Purchase Split Inactive Task Duration-only Finish-only Progress
Date: November 10, 2021
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone