PEMERINTAH PROVINSI NUSA TENGGARA TIMUR

DINAS PEKERJAAN UMUM DAN PERUMAHAN RAKYAT


Jalan Basuki Rachmat No 1 Gedung A Kantor Gubernur Pertama
Telp/Faks -Kupang-NTT

KEPADATAN
HASIL CORE DRILL ASPAL
Pekerjaan : Pembangunan Ruas Jalan Dintor-Wae Rebo (Destinasi Wisata) Kabupaten Manggarai
Kontraktor : PT. Floresco Aneka Indah
Konsultan : CV Clarioz Engineering
Komponen : HRS BASE
Tanggal :31 Juli 2021

TEBAL
NO. STA RATA-2 Nominal Toleransi BERAT BERAT BERAT VOLUME JSD JSD KEPADATAN SPEC. KET.
1 2 3
(cm) (cm) ± 3 mm UDARA DLM. AIR SSD LAP LAB %
1 2 3 4 5 6 7 8 9 10 11 12
1 0+005 R 3.70 3.50 3.50 3.57 3.50 3.47 731.00 399.00 732.00 333.00 2.195 2.257 97.26 97.00
2 0+100 L 3.60 3.50 3.50 3.53 3.50 3.47 820.00 456.97 824.00 367.03 2.234 2.257 98.99 97.00
3 0+200 CL 3.50 3.60 3.70 3.60 3.50 3.47 607.77 332.00 608.35 276.35 2.199 2.257 97.44 97.00
4 0+300 R 3.50 3.60 3.50 3.53 3.50 3.47 522.06 286.00 524.00 238.00 2.194 2.257 97.19 97.00
5 0+400 L 3.50 3.50 3.50 3.50 3.50 3.47 658.47 359.00 658.61 299.61 2.198 2.257 97.38 97.00
6 0+500 CL 3.50 3.50 3.60 3.53 3.50 3.47 566.81 312.89 567.28 254.39 2.228 2.257 98.72 97.00
7 0+600 R 3.50 3.50 3.50 3.50 3.50 3.47 648.35 355.00 649.11 294.11 2.204 2.257 97.67 97.00
8 0+700 L 3.80 3.60 3.70 3.70 3.50 3.47 546.95 301.00 547.54 246.54 2.219 2.257 98.29 97.00
9 0+800 CL 3.50 3.50 3.50 3.50 3.50 3.47 389.18 212.12 389.41 177.29 2.195 2.257 97.26 97.00
10 0+900 R 3.60 3.50 3.50 3.53 3.50 3.47 747.38 410.00 748.11 338.11 2.210 2.257 97.94 97.00
11 1+000 L 3.50 3.60 3.60 3.57 3.50 3.47 950.98 524.00 951.34 427.34 2.225 2.257 98.60 97.00 -
12 1+100 CL 3.50 3.60 3.60 3.57 3.50 3.47 788.90 433.00 789.58 356.58 2.212 2.257 98.02 97.00
13 1+200 R 3.50 3.70 3.70 3.63 3.50 3.47 570.57 313.00 571.12 258.12 2.210 2.257 97.94 97.00
14 1+300 L 3.70 3.50 3.50 3.57 3.50 3.47 658.65 361.44 659.78 298.34 2.208 2.257 97.82 97.00
15 1+400 CL 3.60 3.50 3.50 3.53 3.50 3.47 520.32 287.24 523.34 236.10 2.204 2.257 97.64 97.00
16 1+500 R 3.50 3.60 3.70 3.60 3.50 3.47 686.80 376.87 688.50 311.63 2.204 2.257 97.65 97.00
17 1+600 L 3.50 3.60 3.50 3.53 3.50 3.47 757.34 413.98 758.34 344.36 2.199 2.257 97.44 97.00
18 1+700 CL 3.50 3.50 3.50 3.50 3.50 3.47 603.44 332.00 604.23 272.23 2.217 2.257 98.21 97.00
19 1+800 R 3.50 3.50 3.60 3.53 3.50 3.47 413.90 228.55 415.45 186.90 2.215 2.257 98.12 97.00
20 1+900 L 3.50 3.50 3.50 3.50 3.50 3.47 546.95 299.98 547.54 247.56 2.209 2.257 97.89 97.00
21 2+000 CL 3.80 3.60 3.70 3.70 3.50 3.47 389.18 215.10 389.41 174.31 2.233 2.257 98.92 97.00
22 2+100 R 3.50 3.50 3.50 3.50 3.50 3.47 389.18 215.10 389.41 174.31 2.233 2.257 98.92 97.00
23 2+200 L 3.60 3.50 3.50 3.53 3.50 3.47 747.38 411.00 748.11 337.11 2.217 2.257 98.23 97.00

TEBAL RATA-RATA 3.56 KEPADATAN 2.211 2.257 97.98 97.00 MEMENUHI

Mengetahui Oleh: Diperiksa Oleh: Dibuat Oleh:


Direksi Lapangan Konsultan Pengawas Kontraktor Pelaksana
CV.Clarioz Engineering PT.Floresco Aneka Indah

Abraham A.Lalangpuling,ST Hendrikus Redo ,A.Md Agustinus Nuwa


NIP.19841129 201101 1 003 Lab.Tech Lab.Tech