Professional Documents
Culture Documents
Section 03490-Glass-Fiber-Reinforced Precast Concrete
Section 03490-Glass-Fiber-Reinforced Precast Concrete
PART 1 - GENERAL
A. Provide labour, equipment and services and perform operations required for the Design,
fabrication, delivery and installation of glass fibre reinforced precast concrete (GRC)
fabrications, including integrated supports.
B. Work Includes:
C. Job Mock-Up: After samples are accepted for colour, pattern and texture, produce full scale
units for both screens meeting design requirements for each type of fabrication.
1. Retain job mock up on site as standard of quality for GRC work, when accepted by
Owner.
2. Incorporate mock up into work in location acceptable to Owner.
3. Distress an area and then patch mock up to display variations in colour and texture to
be expected in fieldwork.
A. Structural performance: Provide GFRC panels and panel frames capable of withstanding
gravity, wind, seismic and erection design loads as well as the effects of thermal and
moisture-induced volume changes, according to load factors and combinations established in
PCI MNL 128, “recommended practice for glass fibre reinforced concrete panel”
1. Wind loads: Wind load shall be as per BS 6399-2 corresponding to basic wind speed
160 km/hr.
2. Seismic loads: As per Uniform Building Code (UBC), 1997. Provide glass-fibre-
reinforced precast concrete, including anchorage, capable of withstanding the effects
of earthquake motions calculated according to requirements.
3. Seismic loads: uniform building code (UBC), 1997 edition; zone two A(2A)
4. Dead load: Provide glass-fibre-reinforced precast concrete system that does not
exceed the amount permissible for supporting structure by design code when carrying
full dead load.
5. Live load: Provide glass-fibre-reinforced precast concrete systems, including
anchorage that accommodates supporting structures deflection from uniformly
distributed and concentrated live loads indicated without failure of materials or
permanent deformation.
03490 GLASS FIBER REINFORCED CONCRETE Page 1/5 Rev.1 - 02 Aug 2015
ENGINEERING OFFICE
GENERAL SPECIFICATIONS DIVISION 3 - CONCRETE
6. Impact loads: Provide glass-fibre-reinforced precast concrete panels and systems that
withstand the impact load resulting from the window maintenance and cleaning
equipment.
7. Design framing systems to withstand design loads with lateral deflections no greater
than 1/360 of the wall height.
1.4 SUBMITTALS
A. Samples representative of finished exposed face showing typical range of colour and
texture and of appropriate thickness.
B. Product Data: For each type of product indicated, include GFRC design mixes.
C. Shop drawings detailing fabrication and installation of GRC panels, including the following:
D. Backup test data on which GRC design is based and data on GRC insert and anchor tests.
A. Delivery and Handling: Handle and transport units in a position consistent with their shape
and design in order to avoid excessive stresses or damage.
B. Job Site Storage: Store units to protect from contact with soil, staining, and physical damage.
1. Store units with non-staining resilient supports at same positions as when transported.
2. Store units on firm, level, and smooth surfaces.
3. Place stored units so that identification marks are readily accessible.
PART 2 - PRODUCTS
1. For surfaces exposed to view in finished structure, use same brand, type, and source
of supply throughout GRC production.
C. Sand: Washed and dried silica or other acceptable material with successful use in GRC
production meeting compositional requirements of ASTM C 144; all passing through No. 16
sieve.
D. Facing Aggregate: ASTM C 33, except maximum size not to exceed 1/2 inch; clean, hard,
strong, durable, inert, and free of staining or deleterious materials.
03490 GLASS FIBER REINFORCED CONCRETE Page 2/5 Rev.1 - 02 Aug 2015
ENGINEERING OFFICE
GENERAL SPECIFICATIONS DIVISION 3 - CONCRETE
E. Water: Potable, free from deleterious material that may affect colour stability, settings or
strength of GFRC and complying with chemical limits of PCI MNL 130
F. Admixtures
1. ASTM C 260 for air entrainment, ASTM C 494 for chemical admixtures, or ASTM C
618 for fly ash or natural pozzolana admixtures; at manufacturer's option. Do not use
admixtures that contain more than 0.1 percent chloride ions.
2. Use thermoplastic co-polymer where fabricator recommends it for required
characteristics.
G. Colouring Agent: ASTM C 979; ultraviolet and alkali resistant; high temperature stable;
harmless to concrete set or strength.
H. Glass Fibre: Specifically designed for compatibility with aggressive alkaline environment of
Portland cement based composites, complying with PCI MNL 128.
E. Threaded Anchors Finish: Electrodeposited zinc, ASTM B 633, or cadmium coated, ASTM B
766.
2.4 MIXES
A. General: Combine Portland cement, glass fibres, sand, and selected admixtures in proper
proportions to meet design requirements. Provide nominal glass content of not less than 5
percent, average yield strength of 6 MPa, and ultimate strength not less than 17 MPa.
2.5 FABRICATION
A. Forms: Construct of rigid materials that will result in finished product's conforming to profiles,
dimensions, and tolerances indicated. Use form release agent compatible with Engineering
finish and joint sealants.
B. Facing Materials: Place facing materials into forms so that there will not be displacement
during GRC application.
C. Proportioning and Mixing: Carefully measure amounts of mix constituents to achieve desired
mix proportions.
1. Meter glass fibre and cement slurry to spray head at rates to achieve desired mix
proportion and glass content. Check in accordance with standard procedures
recommended by PCI MNL 128.
1. Spray mist coat consisting of matrix without fibres onto forms, if required. Do not exceed
1/16 inch thickness to prevent an un-reinforced surface.
03490 GLASS FIBER REINFORCED CONCRETE Page 3/5 Rev.1 - 02 Aug 2015
ENGINEERING OFFICE
GENERAL SPECIFICATIONS DIVISION 3 - CONCRETE
2. Proceed with spray up of main body before mist coat has set, using procedures that
produce a uniform thickness and distribution of glass fibres and matrix.
E. Perform hand forming of intricate details, incorporation of formers or infill materials, and over
spraying before material has taken initial set to ensure complete bonding.
F. Inserts and Embedment: Properly embed inserts in built up homogenous GRC bosses or
bonding pads to develop their strength.
G. Dimensional Tolerances: Manufacture units so that each panel complies with following
dimensional tolerances. For dimensional tolerances not listed below, comply with PCI MNL
117 "Manual for Quality Control for Plants and Production of Engineering Precast Concrete
Products."
H. Finishes: Exposed face of panels to match Owner's samples. Joint marks, ‘grain’, or other
obvious defects on panel faces are not acceptable.
I. Curing: Employ initial curing method that will ensure sufficient strength for removing units
from form.
1. After initial curing, remove panel from form and place in a controlled curing
environment. Keep panels continuously moist for minimum 7 days in accordance with
manufacturer's standard curing practice. Maintain temperature between 16º C and 42º
C during this period.
2. An acrylic thermoplastic copolymer dispersant may be used as curing admixture in lieu
of moist curing. Use only copolymers shown to eliminate need for moist curing through
published independent laboratory test data.
J. Panel Identification: Mark each GRC panel to correspond to identification mark on shop
drawings for panel identification. Mark each panel with casting date.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Prior to installation of units, check job site dimensions affecting installation of GRC units.
Bring to Engineer’s attention any discrepancy between design dimensions and field
dimensions that could adversely affect installation. If discrepancies do exist, do not proceed
until corrected or until installation requirements are modified as acceptable to Engineer.
3.2 INSTALLATION
A. Supports and Bracing: Provide temporary supports and bracing as required to maintain
position, stability, and alignment as units are being permanently connected.
B. Fastening: Fasten GRC units in place by bolting or welding, as indicated on shop drawings.
3.3 PATCHING
A. General: Patching will be permitted provided structural adequacy of unit and appearance are
not impaired, as acceptable to Owner and as demonstrated on job mock up.
03490 GLASS FIBER REINFORCED CONCRETE Page 4/5 Rev.1 - 02 Aug 2015
ENGINEERING OFFICE
GENERAL SPECIFICATIONS DIVISION 3 - CONCRETE
B. Patching Mix: Match colour and texture of GRC unit. Blend and mix materials so that cured
patching blends with adjacent surfaces and is not evident when viewed from a distance of
1.8M.
3.4 CLEANING
1. Clean soiled GRC surfaces with detergent and water, using soft fibre brushes and
sponges, and thoroughly rinse with clean water.
3.5 REPAIRS
A. Repairs will be permitted provided structural adequacy of GFRC unit and appearance are not
impaired, as approved by engineer.
B. Blend and mix patching materials and repair GFRC so cured patches match colour, texture,
and uniformity of adjacent surfaces.
C. Prepare and repair damaged galvanized coatings on metal framing, anchors, and subsystems
with galvanizing repair paint according to ASTM A 780.
D. Wire brush, clean and paint accessible scarred areas, welds and rust spots on prime-painted
metal framing, anchors and subsystems. Paint with same type of shop paint used on adjacent
surfaces.
E. Remove and replace damaged GFRC units when repairs do not comply with requirements.
END OF SECTION-03490
03490 GLASS FIBER REINFORCED CONCRETE Page 5/5 Rev.1 - 02 Aug 2015