Strategy and Procurement Plan WO Tubing P4
Strategy and Procurement Plan WO Tubing P4
Strategy and Procurement Plan WO Tubing P4
The completion of this form is mandatory for all Contracts with a gross contract value >USD 1MM and recommended for all
Contracts <USD 1MM.
1.0 Introduction
Description of Service: (1) Item required for the 12(twelve) wells (2) 4-1/2” Tubing and (3) 4-1/2” Pup Joint Tubing
Scope of Work
To purchase new tubing, pup joints tubing, cross-overs and flow couplings required in order to replace
(insert brief description
the existing tubing string on the wells
of the work)
Requisition Number
-
(SAP) if applicable
Business Unit/ Contract
Drilling & Workover
Coverage:
Major Stakeholders Drilling Manager
Contract Manager MLN Operations Manager: Contract Specialist Dony Rahadiyanto Kurniawan
Sponsor / Budget
Country Manager: Agus Purbaya
Holder/ Others
There are numerous tubing contractors within Algeria. Weakness: there is a high
Type of Market (any known level of risk associated with the service. As a result, a detailed technical evaluation
strengths or weaknesses in the shall be required in order to ensure that the selected contractor has (1) a
market) documented HSE management system and (2) available resources that are
competent and experienced with respect to the required work scope.
Procurement Council (extension term value > $10MM Gross < $15MM Net ) YES/NO
Country President (extension term value >$15MM Net but < $25MM Net) YES/NO
CPO&EVP (extension term value > $25MM Net. Single/Sole Source > $20MM Gross or $10MM Net) YES/NO
CEO (extension term value > $100MM Net) YES/NO
Prequalification Summary
(high level overview of how Bidders Bidders selected using public call for competition (BOASEM).
have been identified)
Incentive Scheme
KPI’s
Change Management
Handover
Justification
SIGNATURE
PRINT NAME
Date:
SIGNATURE