Realisasi Kedatangan Material

NO Item Pile Sat.


04-Dec-21 05-Dec-21 06-Dec-21 07-Dec-21 08-Dec-21 09-Dec-21 10-Dec-21 11-Dec-21 12-Dec-21 13-Dec-21 14-Dec-21 15-Dec-21 16-Dec-21 17-Dec-21 18-Dec-21 19-Dec-21 20-Dec-21 21-Dec-21 22-Dec-21 23-Dec-21 24-Dec-21 25-Dec-21 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 31-Dec-21

1 Bottom btg 5 4 5 0 0 0 5 0 0 10 10 10 10 4 11 0 0 10 10 0 6 0 0 6
2 Middle btg 5 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Top btg 0 6 4 0 0 0 5 0 0 7 10 10 10 6 9 0 0 0 0 0 6 0 0 6
Total btg 10 20 30 30 30 30 40 40 40 57 77 97 117 127 147 147 147 157 167 167 179 179 179 191

`
Realisasi Pekerjaan Pile
NO Item Pile Sat.
04-Dec-21 05-Dec-21 06-Dec-21 07-Dec-21 08-Dec-21 09-Dec-21 10-Dec-21 11-Dec-21 12-Dec-21 13-Dec-21 14-Dec-21 15-Dec-21 16-Dec-21 17-Dec-21 18-Dec-21 19-Dec-21 20-Dec-21 21-Dec-21 22-Dec-21 23-Dec-21 24-Dec-21 25-Dec-21 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 31-Dec-21

1 Pile 12 +12 titik 0 0 0 2 1 1 10 2 1 0 7 10 12 7 8 11 0 0 0 0 0 0 0 0


2 Pile 12 +8 titik 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6
Total titik 0 0 0 2 3 4 14 16 17 17 24 34 46 53 61 72 72 72 72 72 72 72 72 78