FOUNDATION BOQ-LIFE MISSION ANCHAL, KERALA

S.no. Description Quantity Unit Rate Amount

1 Excavation 496.15 cum 400 1,98,461.40

2 Back Filling 303.78 cum 350 1,06,322.23

3 P.C.C. (1:4:8) 64.64 cum 7500 4,84,794.00

4 R.C.C.- M25

a Footing 160.76 cum 10500 16,88,029.88

b Column 12.93 cum 11500 1,48,651.83

c Beam 31.40 cum 11900 3,73,600.50

5 Reinforecemnt 20000.00 kg 95 19,00,000.00

6 Shuttering 416.59 sqm 400 1,66,637.80

7 Sand Filling under floor 207.59 cum 700 1,45,315.91

Total 52,11,813.54

Notes:
i The work shall be carried out as per CPWD specifications, if specifications are not available, IS codes shall be followed.
ii All equipment / machineris used at site should complay relevent safety standards of operation.
iii Materil to be used should be as from the list of approved materials attached
*All rates are exclusive of taxes and all other charges