VILLARIN
BS ARCH 3
BT 4 ( ACTIVITY 2 – MIDTERM )
PROBLEM EXERCISE
FROM THE FOLLOWING FIGURE, SOLVE FOR THE QUANTITY OF CEMENT, SAND
AND GRAVEL BY THE VOLUME METHOD USING (a) CLASS “A” CONCRETE.
(b) CLASS B CONCRETE.
SOLUTION:
CONVERT ALL MEASUREMENTS FROM INCHES TO METERS
SOLVE FOR THE CROSS-SECTIONAL AREA OF THE COLUMNS.