68 TANKS WORK-PROGRAMME UP TO 14 AUGUST - 2021

May-21 Jun-21 Jul-21 Aug-21


S.No Description of item REMARKS
2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND

Pump House
1 PUMPS ERECTION
2 MOTOR ERECTION
3 CONTROL PANEL ERECTION
4 SOFT STARTER ERECTION
5 CABLE TRAYS
6 BATTERY & BATTERY CHARGERS
7 VALVES ERECTION
8 SUB STATION VCB,CT &PTS ERECTION
9 EARTHING e.t.c
10 CABLE CONNECTION
POWER TAKING FROM SUB STATION TO PUMP Work on progress By
11 HOUSE Dept side
12 DRY RUN OF PUMPS & MOTORS
13 Roof truss
14 MANIFOLD BALANCE CONCRETE
15 DELIVERY PIPES ERECTION
Erection place didn’t
16 AIR VESEL ERECTION deside by dept
PRESSURE MAIN

Department change the


VALVES ERECCTION ALONG THE PRESSURE rating awaiting the
1 MAIN official letter.
Department approved
2 VALVE CHAMBES ALONG THE PRESSURE MAIN not arrival
BALANCE PRESSURE MAIN LAYING IN FOREST FOREST Approved
3 LAND pending
FOREST Approved
4 DELIVERY CHAMBER AT FOREST LAND pending
PSC Laying
1 GRAVITYMAIN-1 LAYING
FOREST Approved
FOREST LAND(M.S(0 -400M ) bending
FOREST Approved
FOREST LAND(PSC 401-1287 )-1400mm dia bending
2 1287M -2303M LAYING COMPLETED
3 2303-2398M Cultuvated land
4 2398-3295m LAYING COMPLETED
5 3295-3299m
6 3299-4637m LAYING COMPLETED
7 4637-5137m
8 5137-5600m
9 5600-6100m
10 6100-6600m
11 6600-7200m
12 7200m-7600m
13 7600m-10655m(1100mm dia)
14 10655m-10985m
15 10985-12984m Laying completed
16 12984-13085m
Cannal Portion Didn’t
deside for MS or PSC
17 13085-13185m Pipe
18 13185-13386 Laying completed
19 13386-14122
Cannal Portion Didn’t
20 14122-14172 deside for MS or PSC

21 14172-14648 Laying completed


Driange Cannal Portion
Didn’t deside for MS or
22 14648-14798 PSC Pipe

23 14798-15085 Laying completed


24 15085-16085

25 16085-16645 Laying completed


ABOVE MENTIONED CHAINAGES DC TO
HIGHWAY (UDUMALA PADU)
GRAVITYMAIN-2 LAYING IN FOREST LAND
FOREST Approved
1 FOREST LAND(M.S(0 -600M )500MM Pending
FOREST Approved
2 FOREST LAND(PSC600-1065)-800MM psc Pending
Land acquistion partially completed. Work started and stopped.
3 1065-3405m
4 3405-4783M Laying completed
5 4783-5003M
6 5003-6250M Laying completed
7 6250-6325M
8 6325-7904M Laying completed
9 7904-7909M
10 7909-10900M Laying completed
11 10900-10904M
12 10904-11900M Laying completed
800mm to 700mm started
13 11900-13322M
14 13322-16210M Laying completed
15 16210-16510M
GRAVITYMAIN-3
1 0-400mts FOREST CLEARANCE REQUIRED
2 400-1600M 400mts completed. Railway crossing is also yet to be cleared .
3 1600-2210m
4 2210-3790 Laying completed
5 3790-4282m
6 4282-5650m Laying completed
7 5650-5955m
8 5955-6375m Laying completed
9 6375-7002m
10 7002-8295m Laying completed
11 8295-8700m
12 8700-9800m FOREST GAP. PERMISSION CLEARANCE AWAITED
13 9800-16200 LAYING COMPLETED
14 16200-19810 4370 LAID. 520 mts cannot be done since alignemnt is in lake filled now with water.

NOTE
1 As mentioned above the laying works is considered taking that we will be receiveing all land clearances without any hurdles in laying. Since even today land compensation is not received to many and they are stopping works.
2 Forest and National Highway clearances are also waiting.