Professional Documents
Culture Documents
Notes of Meeting (ASD-HKCA)
Notes of Meeting (ASD-HKCA)
Item
Page 1 of 5
Our Ref: 9/91200/CMU/HKCA
Item
4.1.1 HKCA expressed their concerns on the quality of concrete core obtained
from the coring test of rock-socketed steel H-piles might be difficult to
demonstrate the continuity of grout due to core broke up during coring
while alternative proof of grout quality by means of CCTV inspection
might not be accepted by site supervisory staff.
4.1.2 ArchSD advised that the provision on the use of CCTV inspection as
alternative proof to demonstrate the continuity of grout for rock-
socketed steel H-piles had now been added in the ‘General Notes on
Drawing’. Briefings to site supervisory staff on the latest provision
would also be provided at the commencement of contract works.
4.2.2 HKCA supplemented that they had separate discussions with the
Development Bureau (DEVB) on the subject and it was agreed that
straight rebars without involving cut and bend processes would be
excluded from the requirement on the minimum percentage of rebars to
be supplied by approved prefabrication yard. Besides, HKCA had also
proposed to DEVB on reducing the minimum percentage of
prefabricated rebar products required for using in the pilot projects from
70% to 50% to allow greater flexibility for contractors to allocate the
required percentage of prefabricated rebar products for superstructure
and substructure works.
4.2.3 In response, ArchSD advised that the pilot scheme was implemented by
DEVB to mandate the use of prefabricated rebar products in selected
public works projects with the aims of allowing contractors and project
officers to gain more practical experience of using prefabricated rebar
Page 2 of 5
Our Ref: 9/91200/CMU/HKCA
Item
4.3.1 In response to HKCA’s enquiry on the time frame for approval of design
submissions, ArchSD advised that the checking process by the
Structural Checking Unit (SCU) would generally be completed within
28 days after all documents of the submission had been received. In case
there was any particular design submission requiring assistance,
ArchSD welcomed to discuss on the details of individual project.
4.3.2 HKCA expressed that the feedback from contractors were positive on
the provision of reference piling design in the tenders of ArchSD
contracts. HKCA suggested that it would be useful to include pile load
schedule in the reference drawings of reference piling design. In
response, ArchSD would keep in view of the information provided in
the reference drawings.
4.4.1 HKCA enquired whether contractor could make use of the width of
capping plate for shear enhancement when considering the shear
distribution in pile cap design of steel H-piles.
4.4.2 ArchSD responded that it was generally acceptable to consider the width
of capping plate in determining the width for shear enhancement in the
design of pile cap for steel H-piles in ArchSD projects.
4.5 Certification of Piling Design, As-built Piling and Pile Cap Drawings
4.5.1 HKCA expressed that pile cap drawings submitted by the contractor
shall be certified by a Registered Structural Engineer (RSE) in
Page 3 of 5
Our Ref: 9/91200/CMU/HKCA
Item
4.5.2 ArchSD advised that when the contractor was responsible for the design
of piling and pile caps, the Contractor’s design submissions and
subsequent amendments shall require a Designer who shall be a RSE in
accordance with the Standard Preliminaries for ArchSD contracts.
4.6.1 HKCA expressed that it took a long time in carrying out the trial pile
installation to achieve the required CAPWAP capacity in some recent
projects. HKCA also shared their experiences that the 90% CAPWAP
capacity requirements were sometimes not satisfied though the pile
capacities as determined by CASE method from the results of PDA tests
were in order.
Page 4 of 5
Our Ref: 9/91200/CMU/HKCA
Item
5.1.1 HKCA enquired if ground beams could be used as tie beams instead of
adding another layer of tie beams to pile caps.
5.1.2 ArchSD advised that if the distance between the top of ground beams
and top of pile caps was close, a note would be stated in the ‘General
Notes on Drawing’ to allow contractor to make use of ground beams as
tie beams.
5.2 Typical Splicing Detail for Steel H-section of Rock-socketed Steel H-pile
5.2.1 HKCA expressed that two steel plates were specified in the GS for the
typical splicing detail of steel H-section and suggested if these steel
plates between two segments of steel H-section could be omitted to
reduce the time required for the welding and associated tests of the steel
plates.
The date and time for the next meeting would be advised later.
Page 5 of 5