BILL OF QUANTITIES

CONSTRUCTION OF BARRACK (2x20x12) FOR SECURITY GUARD AT KALABAGH-1A

Tariq Khan
Rate Amount
Serial Description Unit Qty
(Rs) (Rs)
A Barracks Const Works
Excavation in any soil as per site
conditions including backfilling with
1 consolidation to full compaction and Cum 44.41 1,200 53,292
disposal of surplus excavated material
as directed.
Providing and laying 3" thick P.C.C
1:4:8 In foundation using 1" and
downgraded crushed stone, hill sand
and ordinary cement including
2 Cum 9.06 12,000 108,720
compacting, levelling, curing and
formwork complete according to the
drawings and instructions of site-In
charge.
Burnt Brick work in wall over 230 mm
3 thick laid and jointed in cement mortar Cum 46.64 12,000 559,680
1:4

Providing and laying reinforced cement


concrete 1:2:4 using crushed stone and
ordinary cement as in roof slabs,
4 landings, walls, plinth beams etc, Cum 10.35 18,000 186,300
including form work as specified,
completed in all respect and as per
instruction of site incharge

Providing and laying Steel


reinforcement 60 grade deformed bars,
with and including the cost of
straightening, cutting. bending, wastage
5 and such overlaps as are not shown in KG 1091.3 250 272,828
the drawing. placing in position on
cement concrete or M.S chairs,
complete in all respects and as per
Instruction of site Incharge.
Tariq Khan
Rate Amount
Serial Description Unit Qty
(Rs) (Rs)
Providing and Laying 3/4" thick Cement
Plaster 1:4 using ordinary cement, sand
mortar Including mixing, temping and
6 Sm 302.49 450 136,121
curing complete as specified, complete
in all respect and as per instruction of
site incharge

Earth Filling as in Ordinary or hard soil,


filling in foundation, pipe trenches,
shafts, wells, independent holes, under
floors or around plinths etc. 1.5 M below
or above Ground Level (GL), with spoil
7 Cum 11 1,000 11,000
obtained from excavation in
trenches/over areas within 10M incl
watering and compaction in 150 mm
layer and dressing to required profile
and shape.

Providing, laying, filling and compact 4"


8 Cum 5 5,000 25,000
thick stone soling under floor.

Providing and laying 100 mm thick


cement concrete 1:4:8 laid under floor
and in plinth protection using crushed or
9 broken stone, including compacting, Cum 4.53 14,000 63,420
levelling. curing and formwork complete
according to the drawings and
instructions of site-Incharge.
Providing and laying 50.8 mm thick
cement concrete floor 1:2:4 as in floors,
surface finished smooth with neat
cement and steel trowel, using crushed
10 Cum 3 20,000 60,000
or broken stone including form work,
curing, leveling and mixing, complete in
all respect and as per instruction of site
incharge.
Supply and fixing 18 gauge steel door
with all necessary steel fitting /
11 ironmongery, hold fasts 2"x2" angle Sm 5.21 14,000 0
frame etc, two coats of synthetic enamel
paint.
Tariq Khan
Rate Amount
Serial Description Unit Qty
(Rs) (Rs)
Supply and fixing Z" type steel window
or CSW using Z and beam sections
Including M.S Grill made of 3/8" thick
square bar in approved pattem
embedded in bottom, top and side walls
of windows through hold fasts of
approved design each with
12 Sm 8.92 12,000 0
operable/fixed panels with all nacessary
steel fitting iron mongery hold fasts etc.
With 18 x 18 mesh, 28 SWG wire gauze
mesh and 2 coats of synthetic enamel
paint In addition to one coat of
primer/rust proof paint but include 5mm
glass paper and wire gauze

Providing and laying plinth protection


consisting of following:
a. Excavation to depth of 4" with
watering and consoled action including
disposal of excavated earth as directed.
b. PCC 1:4:8. 4" thick.
13 Sm 32.53 3,500 113,855
c. PCC 1:2:4 flooring of 2" average
thickness using 3/4" and down graded
crushed stone, hill sand and cement
including finishing smooth divided Into
panels, form work, consolidation and
curing etc

2 x coat of hot bitumen applied on roof


at the rate of 0.75 kg/sqm, Double layer
of polythene sheet as specified, 100 mm
14 Sm 44.62 4,000 178,480
thick mud leaping and single layer of
300mm x 150mm x 50mm flal brick tile
on roof booled. Jointed and paint.

Internal site distemper and external site


15 Sm 300 500 150,000
weather shield, 3 coat including primer

UPVC Pressure pipe, 100mm dia. Class


16 B, complete, Z-joint with rubber ring, Rm 10 2,000 20,000
(excl excavation). supply and fixing.

A-Sub Total 1,938,695


B Electrification
Tariq Khan
Rate Amount
Serial Description Unit Qty
(Rs) (Rs)
Switch SP, 5A, piano type single or 2
way mounted in cast or malleable Iron
galvd conduit box, with solid metal or
Bakelite plate Including Wiring for one
1 light point, fan point, 5 A socket Point 14 7,000 98,000
controlled by one switch, wiring
complete, with PVC single core cable
3/29, in concealed PVC conduit, supply
and fixing.
Wiring for one three pin, 15 A socket
point. controlled by one switch, wiring,
2 complete PVC with single core cable 2.5 Point 6 10,000 60,000
2
mm , In concealed PVC conduit supply
and fixing

Patty fitting, complete with 1.20M, 40W


fluorescent tube, choke, starter and
3 Each 12 3,500 0
holder & Balk head light, complete,
supply and fixing
56” ceiling fan (Pak, malit, younis)
4 Each 4 7,000 0
complete, supply and fixing.
2
2 coure 16mm WAPDA cable
5 Mtr 100 1,300 0
(underground ) supply and fixing
B-Sub Total 158,000

C Geotechnical Evaluation of Soil

Drilling vertical bore holes: The task


includes drilling with dia. 76mm at the
site (with core recovery) and in different
depths (10 m to 15 m) depending on the
requirements of the site in accordance
with the Site Engineer's instructions.
The contractor shall do the falling head
1 permeability test when needed, also Each 1 350,000 0
collect the disturbed and undisturbed
samples of soil and core rock samples
for laboratory testing and preparing a
detailed geotechnical Investigation
report, which shall also include final test
results with conclusions and
recommendations.
Tariq Khan
Rate Amount
Serial Description Unit Qty
(Rs) (Rs)
C-Sub Total 0

Total (A+B+C) 2,096,695

Add PST @ 16% 335,471

Grand Total 2,432,166