OM SAI TRADERS

IMPLEMENTATION SCHEDULE:-

S.no ACTIVITY START (FROM THE FINISH


DATE OF
POSSESSION)

1. Maps, drawings and Site Plan, 00 month 3Month


approval etc
2. Arrangements of Contractors 3Month 5Month
and obtaining government
approvals
3. Water System Installation work 5Month 6Month

4. Temporary roads etc 6Month 6 ½ Month

5. Generator etc 6 ½ Month 7Month

6. Construction Site Office 7Month 7 ½ Month

7. Building Construction work & 7 ½ Month 26Month


order placement of plant &
machinery and other fixtures
8. Final development of Road Etc 26Month 28Month

9. Development of Infrastructural 28Month 29Month


Facilities
10. Plant & Machinery Installation 29Month 30 Month

11. Permanent Power Connection 30 Month 32Month

12. Start of Activities 32Month 34 Month

13. Completion 34 Month 36 Month

Total 36 Months
OM SAI EXPORTS

Plot Area 450 SQM


covered Area 225 SQM
Entrance Guard

Pantry Office A/C


Hall Deparment

Godown
Testing
Room

Quality WorkShop
Control

Tool
Packing Room
Line
Store

You might also like