Professional Documents
Culture Documents
Preliminary and Primary Tratment-2021
Preliminary and Primary Tratment-2021
School of Engineering
The University of Jordan
Wastewater Engineering
Instructor: Ghada Kassab, PhD
Wastewater is essentially the water supply of the community after it has been
used in variety of application and which now contains constituents that render it
unsuitable for most uses without treatment.
Wastewater also contain nutrients, which can stimulate the growth of aquatic
plants, and may contain toxic compounds or compounds that potentially may be
carcinogenic.
For these reasons, the immediate and nuisance free removal of harmful
constituent from its sources of generation, followed by treatment, reuse or
disposal into the environment, is necessary to protect the public health and the
environment.
2
Wastewater Engineering is that branch of environmental engineering in which
the basic principles of science and engineering are applied to solving the issues
associated with the collection, treatment and reuse of wastewater.
3
Classification of wastewater treatment methods
4
2. Chemical unit processes
Treatment methods in which the removal of constituents is brought about by the
addition of chemicals or by other chemical reactions are knows as chemical unit
processes. Precipitation, gas transfer (aeration) , disinfection are the most
common examples used in wastewater treatment
The addition of oxygen to water to support aerobic reactions is the most common
example of gas transfer.
Another common chemical unit process is the use of chlorine for wastewater
disinfection, which has been practiced fro more than a century.
5
3. Biological unit process
Treatment methods in which the removal of constituents is brought about b
biological activity are know as biological unit processes. Biological treatment
is used primarily o remove the colloidal or dissolved biodegradable organic
substances found in wastewater.
6
Wastewater Processing
To achieve the removal of constituents, a number of unit processes are grouped together
to provide what is know as primary, secondary, tertiary and advance treatment.
7
Typical flow diagrams for the treatment of wastewater (a) Conventional
biological treatment (b) Biological nutrient removal
8
Typical flow diagram for the treatment of wastewater c) Advanced treatment following
conventional or nutrient removal treatment. D) anaerobic treatment of sludge from
primary sedimentation and excess biological sludge.
9
Criteria and indicators generally used to assess the sustainability of sewage treatment technologies
(Adapted from Seghezzo, 2004)
Institutional and Regulatory framework Local legislation that promotes or hinders the use of different options
regulatory aspect Management capacity Governmental and private proficiency to manage sanitation systems
Management scale Operation at different scales and by different actors, decentralization
Change of routines Changes by practitioners to adopt sanitation technologies,
10
Basic computations in wastewater treatment
1. Removal Efficiency and the log removal value
The objective of treatment processes is to remove contaminants. Removal can
be determined for bulk water quality measures (e.g.TSS, BOD, COD, TN, etc.)
or for individual constituents of interest (e.g coliform bacteria).
12
Preliminary Treatment
13
Screening
14
Screening
• First unit operation generally encountered in wastewater
treatment plants
15
Classification of screens
16
Fine screen are sometimes used in place of or following coarse screen where
greater removal of solids are required:
Screening elements may consist of parallel bars, rods or wires, wire mesh or
perforated plates
Opening may be of any shape generally circular or rectangular
Screen composed of parallel bars or rods are called a bar rack or coarse
screens.
17
Screenings retained on coarse screens
Rocks, branches, leaves, paper, tree root, plastics, bottles cans and rags
Manually used
• Ahead of pumps in small wastewater pumping stations
• Often they are used as standby screening in bypass channels during
high flow periods
• When mechanically cleaned screens are being repaired
• In the event of power failure
18
19
Photo adapted from Shandong Jinhaosanyang
Environment protection Machine Co. Ltd
20
Design of coarse screens
Design consideration
1. Location
2. Approach velocity
3. Clear openings between bars or mesh size (Table 13-3 Mackenzie)
4. Headloss through screens
5. Screenings handling , processing and disposal
For most mechanically cleaned coarse screen two or more units should be
installed so that unit maybe taken out of service for maintenance .
Each channel should have adequate capacity to pass the peak flowrate
Slide gates should be provided ahead of and behind of each screen so that the
unit can be dewatered for maintenance and repair (Figure 13-6 Mackenzie)
21
Velocity
Screen channel should be designed to prevent the settling and accumulation of grit
nd othe heavy materials
An approach velocity of at least 0.4 m/s is recommended
To prevent the pass through of debris at peak flowrates, velocity through bar
screens should not exceed 0.9 m/s
Headloss
• Headloss through mechanically cleaned screen is typically 150 mm
.
• The racking mechanisms are operated normally based on differential
headloss through screen or by a time clock
On for 5 minutes
Off for 25 minutes (with higher flowrates increase the frequency of cleaning)
22
Hydraulic losses through bar screens
V1= Q/A(flow)
V2= Q/ 0.7A
hL = headloss, m
C= an empirical discharge coefficient to account for turbulence and eddy losses
Typically 0.7 for clean screen and 0.6 for clogged screen
V thru= velocity through bar screens, m/s
V approach= approach velocity in upstream channel, m/s
g = acceleration due to gravity 9.81 m/s2
23
Fine screens
Used;
• preliminary treatment after coarse screens
24
Design consideration
• Minimum two parallel each of capability of handling peakflow
• Velocities
approach velocity in the range of 0.6 m/s – 1.2 m/s
another criteria; greater than 0.3 m/s at low flow and less than 1.4 m/s at peak
flow
Headloss
The clear water headloss may be obtained from manufacturers rating
tables or calculated using the equation
25
Range from 0.8-1.4 m
hL = headloss, m
C= coefficient of discharge (typical value of 0.6 for clean screen,
g = acceleration of gravity, m/s2
Q = discharge through screen m3/s
A= effective open area of submerged screen, m2
26
Screenings handling and disposal
Disposal
• Hauling and co-disposal with solid wastes
• Monofilling at site (small installations only)
• Incineration alone or with sludge and grit
• Discharge to grinders where it is returned to wastewater treatment plant.
27
Grit Removal
Grit in wastewater consists of sand, gravel , cinders or other heavy
solid materials that have specific gravities substantially greater
than the of the organic solids in wastewater.
28
Wastewater Grit Characteristics
Grit composition. Grit consists of sand, gravel, cinders and other
heavy materials. It also includes organic matters such as eggshells,
seeds and coffee grounds.
The presence of these constituents can alter the size and settling
characteristics of the grit size and settling characteristics of the grit
particle.
Grit quantities. The quantities of grit will vary greatly from one
location to another, depending on the type of sewer system, the
condition of the collection system, the types of industrial wastes,
the number of household with food waste grinders and amount
of infiltration in areas with sandy soils.
30
Traditionally , grit removal have been designed based on the
assumptions that, grit consists of inorganic, settleable solids
ranging in size from 0.050-1.0 mm with settling characteristics
similar to clean silica sand with a specific gravity of 2.65 and a
particle size predominantly larger than 0.2 mm.
31
Grit settling characteristics. The settling characteristics of
grit vary considerably form the point of entry in the collection
system and its location in the treatment plant.
33
Sand Equivalent Size (SES)
SES relates the settling velocity of wastewater grit to that of clean
sand.
Wastewater grit particle coated with SAAs with the same physical
size as a clean particle of sand will have a lower settling velocity
than the clean sand particle.
34
35 Adapted from Metcalf and Eddy (2014)
Settling velocity of wastewater grit
When possible, a grit study should be conducted to determine
the SES of the incoming wastewater grit and the design SES to
achieve the desired level of grit removal.
36
The physical size and the SES
of wastewater grit begins to
diverge at 0.106 mm with the
difference increasing as the
physical size increases.
For example,
for a physical particle size of
0.210 mm, the SES could vary
from 0.106 mm to 0.210 mm.
Consequently, to remove
particles with a physical size of
0.210 mm, an SES as low as
0.106 mm may have to be used
as basis for design
37
A design based on an SES of 0.106 mm will result in 90 percent
grit removal for most collections systems. However, for those
collection systems where very fine silt is expected, the grit removal
efficiency might be significantly lower than 50-65 percent. If the
goal is to achieve 90% grit removal, a design SES as low as 0.075
mm may be required.
Once the design SES ha been identified, the surface loading rate
of targeted grit particle can be established using the settling
characteristics of clean sand.
For an SES of 0.106 mm, the surface loading rate is 0.49 m/min.
For an SES of 0.075 mm, the required surface loading rate is 0.24
m/min, which doubles the size of the required grit removal system.
38
Grit separators for wastewater
39
Grit separators for wastewater
40
Grit separators for wastewater
And by Camp’s equation, to be scoured at a velocity
In horizontal flow grit chamber, to assure removal of the grit and scour
of organic matter, three conditions must be met:
1. The overflow rate of the chamber must be equal to the settling
velocity of the inert grit particle
2. The horizontal velocity must be less than the scour velocity of the
inert particles.
3. The horizontal velocity must be greater than the scour velocity of the
organic particles
41
1. Horizontal flow grit chambers
Rectangular and square horizontal flow grit chambers have been
used for many years. Their use, however, in new installations has
limited in favor of aerated and vortex type grit chambers.
The design velocity will carry most organic particles through the
chamber but will permit the heavier grit to settle out.
43
1.2 Square horizontal flow grit chambers
Square horizontal flow grit chambers have also been used for
over 60 years. Influent to the units is distributed over the cross
section of the tank by a series of vanes or gates, and the
distributed wastewater flows in straight lines across the tank and
overlfows a weir in a free discharge.
44
1.2 Square horizontal flow grit chambers
Typical set of design curves is shown on the Figure below
(Figure 5-36 Metcalf and Eddy, 2014). The SES should be
used for determining the settling area required
45
1.2 Square horizontal flow grit chambers
46
2. Aerated grit chambers
In aerated grit chambers, air is introduced along one side of a
rectangular tank to create a spiral flow pattern perpendicular to
the flow through the tank.
Wastewater will move through the tank in a spiral path and will
make two t three passes across the bottom of the tank at
maximum and more passes at average flow.
The heavier grit particles settle to the bottom of the tank. Lighter,
principally organic particles remain in suspension and pass
through the tank.
47
2. Aerated grit chambers
51
2. Aerated grit
chambers
52
If the velocity is too high, grit will be carried out of the chamber, if it
is too low, organic material will be removed with the grit.
53
A grit hopper about 0.9 m deep with steeply sloping sides is
located along one side of the tank under the air diffusers.
The air diffusers are located about 0.45 to 0.6m avove the
normal plane of the bottom.
54
55
Vortex type grit chambers
These devices uses a vortex flow pattern:
Mechanically induced vortex: Wastewater is directed to the
vortex unit by an inlet channel that is designed to guide the
wastewater flow into the vortex unit while the grit is directed
downward.
56
Hydraulically induced vortex: The vortex is generated by
the flow entering the unit without any mechanical devices.
Wastewater is directed to the unit by a channel and enter
tangentially into the cylindrical unit, causing the contents to
rotate slowly about the vertical axis.
The heavy grit moves down a spiral path to the center where
it passes under a center cone to the grit slurry hopper.
57
Flow is directed into the multiple
tray unit by an influent
distributor header which
distributes influent tangentially
into the multiple tray system.
58
59
Primary Sedimentation
60
Primary sedimentation
61
Description
Almost all treatment plants that have primary sedimentation, use
mechanically cleaned sedimentation tanks of standardized circular
or rectangular design.
62
Rectangular tanks
Rectangular sedimentation tanks may use either chain and flight solids
collector,
Scraper blade
Photo adapted from aaf envirotec Photo adapted from XRD Shandong
Xuridong Machinery Co., Ltd
65
Multiple rectangular tanks require less land area than multiple
circular tanks and find application where site space is at a premium.
66
67
Flow distribution
Figure 14-15
68
Circular tanks
71
Sedimentation tank weirs/ rectangular sedimentation tanks.
Settled effluent from sedimentation tanks is discharged over weirs into an
effluent launder which in turn discharges in a conduit leading to the
biological treatment process. Small rectangular settling tanks are often
fitted with a single transverse weir on the discharge end wall. However,
larger rectangular settling tanks require additional weir length to minimize
head loss and short circuiting. Head loss and short circuiting can be
minimized by adding a series of launders with double weirs that are
aligned either longitudinally (parallel to the length of the settling tank) or
transversely (perpendicular to the length of the settling tank, or both
longitudinally and transversely.
72
Sedimentation tank weirs/ circular sedimentation tanks.
73
Sedimentation tank performance
BOD and TSS removal
Typical performance data for the removal of BOD and TSS in
primary sedimentation tanks, as a function of the detention time
and constituent concentration, are presented in the figure below
(adapted from Metcalf and Eddy, 2014).
74
The curves shown are derived from observations of the
performance of actual sedimentation tanks. The curvilinear
relationship in the figure can be modeled using the following
relationship.
Where: R=expected removal efficiency
t= nominal detention time, T
a,b= empirical constants
Item b a
BOD 0.020 0.018
TSS 0.014 0.0075
75
The efficiency of sedimentation basins with respect to the
removal of BOD and TSS is influnced by short circuiting
and hydraulic stability:
76
77
Temperature effects. Temperature effects can be significant
in sedimentation basins. It has been shown that a 1C
differential between the incoming wastewater and the
wastewater in the sedimentation tank will cause a density
current to form.
The impact of the temperature effects on performance will
depend on the material being removed and its
characteristics. Temperature effects can be more pronounced
in secondary settling tank where a less dense sludge is
processed
79
Typical design information for primary sedimentation tanks
Primary sedimentation tanks followed by secondary treatment
81
In cold climates, increases in water viscosity at lower
temperatures retard particle settling in clarifiers and reduce
performance at wastewater temperature below 20°C.
The curve shown below, present the increase in detention time
necessary to equal the detention time at 20°C (WPCF, 1985). For
wastewater having a temperature of 10°C for example, the
detention period is 1.38 times that required at 20°C to achieve
the same efficiency. Thus, in cold climates, safety factors should
be considered in clarifiers design to ensure adequate
performance.
82
Surface loading rates:
Sedimentation tanks are normally designed on the basis of a surface
loading rate (commonly termed overflow rate) expressed as cubic meters
per square meter of surface area per day, m3/m2.d. When the area of the
tank has been established, the detention period in the tank is governed by
water depth. Overflow rates in current use result in detention periods
of 2-2.5 h based on average design flow.
The effect of the surface loading rate and detention time on suspended
solid removal varies widely depending on the characteristics of the
wastewater, proportion of settleable solids and concentration of solids.
83
Weir loading rates
In general weir loading rates have little effect on the efficiency of primary
sedimentation tanks, and should not be considered when reviewing the
appropriateness of clarifier. For general information purposes only, typical
weir loading rtes are given in Table 14-1. Baffles should be placed ahead of
effluent weirs in primary settling tanks to reduce hydraulic short circuiting.
The baffles also prevent the discharge of scum into the effluent.
Scour velocity
To avoid the resuspention (scouring) of settled particles, horizontal velocities
through the tank should be kept sufficiently low.
84
Where:
VH = Horizontal velocity that will just produce scour (m/s)
K= constant that depends on type of material being scoured (unitess)
S= specific gravity of particles
g= acceleration due to gravity 9.81 m/s2
D= diameter of particles, L
F= darcy-Weisbach friction factor , unitless.
Typical values of k are 0.04 for sand and 0.06 for more sticky matter.
The term f (Darcy-Weisbach friction factor) depends on the characteristics of
the surface over which flow is taking place and the Re number. Typical
values of f are 0.02 to 0.03.
85