Contents of questions
Exercise 1:
Item = A
LT: 1 week
Week 1 2 3 4 5 6 7 8
Gross requirement 0 0 50 0 250 0 150 0
Scheduled receipts 0 0 0 0 0 0 0 0
Projected on hand 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 0 0 0 0
Planned receipts 0 0 0 0 0 0 0 0
Planned order release 0 50 0 250 0 150 0 0
Projected on hand calculation = Last Period Closing + Scheduled Receipt + Planned Receipt -
Gross Requirement
Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement(If the
above calculation results in negative amount, then such amount is taken as Net Requirement,
else 0)
Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size
Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed
Lot size: L4L
Item = B
LT: 2 weeks
Week 1 2 3 4 5 6 7 8
Gross requirement 100 0 500 0 300 0 0
Scheduled receipts 100 0 0 0 0 0 0
Projected on hand 0 0 0 0 0 0 0 0
Net requirements 0 0 500 0 300 0 0
Planned receipts 0 0 500 0 300 0 0
Planned order release 500 0 300 0 0 0 0
Production Management
Item = C
LLC: 1 & 2 LT: 1 week WEEK
Lot size = 800 1 2 3 4 5 6 7
Gross requirement 0 1050 0 850 0 150 0
Scheduled receipts 0 300 0 0 0 0 0
Projected on hand 120 170 170 120 120 770 770
Net requirements 0 630 0 680 0 30 0
Planned receipts 800 0 0 0 800 0 0
Planned order release 0 800 0 800 0 800 0
LT: 1 week
Week 1 2 3 4 5 6 7 8
Scheduled receipts 0 0 0 0 0 0 0 0
Projected on hand 50 50 50 0 0 0 0 0 0
Exercise 2:
Exercise 3:
Project on hand 85 95 95 0 0 0 0 0
Exercise 4:
In conclusion, we have:
And in the inventory, there are 5 items A, 6 items Q, 20 items D and 120 items E left.
Exercise 5:
Projected Available 10 10 10 10 10 10 10 10 0
Net Requirement 0 0 0 0 0 0 0 90
Planned Order Receipt 0 0 0 0 0 0 0 90
Planned Order Release 0 0 0 0 90 0 0 0
Part B:
Planned Order Release of week n = Net Requirement of week n+2 (LT=2, Lot Size: L4L)
Planned Order Receipt of week n+2 = Planned Order Release of week n
Part B LT=2 Week
Lot size: L4L SS=0 1 2 3 4 5 6 7 8
Gross Requirement 0 0 0 0 0 200 0 0
Schedule Receipt 0 0 0 0 0 0 0 0
Projected Available 5 5 5 5 5 5 0 0 0
Net Requirement 0 0 0 0 0 195 0 0
Planned Order Receipt 0 0 0 0 0 195 0 0
Planned Order Release 0 0 0 195 0 0 0 0
Part C:
Gross Requirement = 3* Planned Order Release of part A
Planned Order Release of week n = Net Requirement of week n+4 (LT=4, Lot Size: L4L)
If Net Requirement of week n+4 < 50, then Planned Order Release of week n = 50
Planned Order Receipt of week n+4 = Planned Order Release of week n
Part C LT=4 Week
Lot size: min50 SS=0 1 2 3 4 5 6 7 8
Gross Requirement 0 0 0 0 270 0 0 0
Schedule Receipt 0 0 0 0 0 0 0 0
Projected Available 140 140 140 140 140 0 0 0 0
Net Requirement 0 0 0 0 130 0 0 0
Planned Order Receipt 0 0 0 0 130 0 0 0
Planned Order Release 130 0 0 0 0 0 0 0
Part D:
Production Management
Gross Requirement = 2* Planned Order Release of part A + 3* Planned Order Release of part
B
Planned Order Release of week n = Multiple of 250 if Net Requirement of week n+2 > 0
(LT=2, Lot Size: 250)
Planned Order Receipt of week n+2 = Planned Order Release of week n
Part D LT=2 Week
Lot size: mult 250 SS=0 1 2 3 4 5 6 7 8
Gross Requirement 0 0 0 585 180 0 0 0
Schedule Receipt 0 250 0 0 0 0 0 0
Projected Available 200 200 450 450 115 185 185 185 185
Net Requirement 0 0 0 135 65 0 0 0
Planned Order Receipt 0 0 0 250 250 0 0 0
Planned Order Release 0 250 250 0 0 0 0 0
Exercise 6:
Period 1 2 3 4 5
Demand 20 40 30 10 50
Cc = $1
Co = $100
D = 30
Item LLC: 0 Period
Lot size: L4L LT: 1 1 2 3 4 5
Gross Requirements 20 40 30 10 50
Scheduled Receipts
Projected on hand 25 5 0 0 0 0
Net Requirements 0 35 30 10 50
Planned Order Receipts 0 35 30 10 50
Planned Order Releases 35 30 10 50
Total cost of L4L = (4 X $100) + 5 X $1 = $405
b)
77.4596
EOQ = 7 ~ 78