(i) Where connection is to be provided from existing distribution system in electrified areas:-
Sl. No. Description Time Period
(i) Acceptance of Application Zero date
(ii) Field Inspection Within 2 days of Acceptance of Application
(iii) Load Sanction and demand note Within 2 days of Field Inspection
Within 2 days of raising demand
(iv) Payment of demand note
note
Release of connection, where no RoW or road
(v) Within 1 day of receipt of payment
cutting permission is required
Total time for release of connection where no Within 7 days of acceptance of
(vi)
RoW or road cutting permission is required application
Total time for release of connection where Within 15 days of acceptance of
(vii)
RoW or road cutting permission is required application
Sl. No. Service Area Standard Computation of period Compensation payable to consumer
of default for the period of default incase of
violation of
standard
(1) (2) (3) (4) (5)
1 Connection where no Network augmentation is required
Release of connection in electrified As per From 8th day from the 1.5% of the demand charges deposited by
areas Regulation 11 acceptance of application in consumer for each day of default.
case where no RoW or road
cutting permission is required
or From 15th day from the
acceptance of application in
case where RoW or road
cutting permission is
required, as the case may be.
2 Connection where Network augmentation is required
(i) Release of connection in Electrified As per From 16th day from the date
Areas (where extension of line upto Regulation 11 of receipt of full payment
five poles is required) against demand note.
(ii) Release of connection in Electrified As per After 2 months from the date
Areas (Where extension of lines or Regulation 11 of receipt of full payment
augmentation of Distribution against demand note.
Transformation capacity, where peak
load of transformer has reached 90%
of its rated capacity)
1.5% of the demand charges deposited by
(iii) Release of connection in Electrified As per After 4 months from the date
consumer for each day of default
Areas (Where new Distribution Regulation 11 of receipt of payment against
Transformer is required) demand note
(iv) Release of connection in Electrified As per After 6 months from the date
Areas (Where existing 11 kV network Regulation 11 of receipt of payment against
needs to be augmented) demand note
(v) Release of connection in Electrified As per After 8 months from the date
Areas (Where existing 66/33 kV grid Regulation 11 of receipt of payment against
sub- station needs to be augmented) demand note
3 Connection in Un-electrified Areas
(i) Release of connection in Un- As per After 4 months from the date 1% of the amount deposited by
Electrified Areas (Where connection Regulation 11 of receipt of payment against developer/applicants per day of default.
from nearby existing network is demand note.
possible)
(ii) Release of connection in Un- As per After 12 months from the
Electrified Areas/ Green Field Regulation 11 date of receipt of payment
Projects (Where new network is to be against demand note.
laid or grid station needs to be
established)
4 In case connection is denied after - - 1.5% of the demand charges deposited by
receipt of payment against demand consumer for each day of default subject
note to maximum of the amount paid as per
demand note. Default to be computed
from the date of receipt of payment
5 Connection energized through loop As per - Rs. 500 per kW of sanctioned/ contract
Regulation 11 demand