16/Aug/21

Project Start:

1 Aug'21 Sept'21 Oct'21 Nov'21 Dec'21


Display Week:
Week - 01 Week - 02 Week - 03 Week - 04 Week - 05 Week - 06 Week - 07 Week - 08 Week - 09 Week - 10 Week - 11 Week - 12 Week - 13 Week - 14 Week - 15 Week - 16 Week - 17 Week - 18 Week - 19 Week - 20 Week - 21 Week - 22
1 2 3 4 5 6 7 8 9 ################################################################## 1 2 3 4 5 6 7 8 9 ############################################################### 1 2 3 4 5 6 7 8 9 ################################################################## 1 2 3 4 5 6 7 8 9 ############################################################### 1 2 3 4 5 6 7 8 9 ##################################################################

STAGE DESCRIPTION OF ITEM PROGRESS START END DAYS S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Ancillary Rooms MS Structure 16/Aug/21 26/Aug/21 10


Excavation, Levelling and PCC (Base Slab
15/Aug/21 27/Aug/21 12
Casting)
Structure and Civil Works

Foundation 24/Aug/21 7/Sep/21 14


Column Casting (from basement slab to first
8/Sep/21 14/Sep/21 6
floor beam bottom)
Installation of MS Structure 5/Sep/21 11/Sep/21 6
Ground Floor Brick Work including plastering
12/Sep/21 26/Sep/21 14
& curing (Civil Works)

Super structure readiness (including all


27/Sep/21 3/Oct/21 6
miscellaneous work)
Plumbing/Sanitation 4/Oct/21 19/Oct/21 15
Services

Electrical Wiring/ELV 7/Oct/21 22/Oct/21 15


HVAC (Air conditioning) Ducting 10/Oct/21 25/Oct/21 15

Tiles for showroom and workshop front-office 1/Oct/21 7/Oct/21 6


(KMI Approved Vendors Only)

Lights for showroom and workshop front-office 9/Oct/21 14/Oct/21 5


Procurement

Work Shop Front elevation glass and ACM/ACP 20/Oct/21 26/Oct/21 6

Signage and pylon including logos 15/Nov/21 19/Nov/21 4

Furniture elements for workshop front-office 26/Oct/21 30/Oct/21 4

Workshop equipment & tools 1/Nov/21 11/Nov/21 10


Paints 6/Nov/21 12/Nov/21 6
Fixing of Flooring/Tiling 8/Oct/21 18/Oct/21 10
Interior Finishing

Gypsum Ceiling 19/Oct/21 24/Oct/21 5

Basic Carpentry & Internal Glass Partition 31/Oct/21 6/Nov/21 6

Façade Glazing 27/Oct/21 3/Nov/21 7


Painting/Skirting 13/Nov/21 21/Nov/21 8
Fixed Furniture Installations 31/Oct/21 5/Nov/21 5
Exterior Finishing Installations

Lighting / Electrical Fixtures 14/Nov/21 20/Nov/21 6


Sanitary Fixtures 19/Oct/21 24/Oct/21 5
Loose Furniture Placement 6/Nov/21 12/Nov/21 6
Workshop equipment installation 12/Nov/21 22/Nov/21 10
Exterior Cladding 19/Oct/21 23/Oct/21 4
Paving 24/Oct/21 30/Oct/21 6
Signage installation 22/Nov/21 26/Nov/21 4
Pylon installtion 27/Nov/21 30/Nov/21 3