1-MR-49 Regulating Skid-2 checking planned today and detector bypass will be done

regarding same. Update-Job Completed


1. CS10A&B: Fire water system piping painting job Completed.
2. CS10A: Pole replacement of scrubber area Completed for today and will
Continue tomorrow.
3. CS10A: GTC A PCV 109 /110 setting Completed.
2-CS10A GEG-C and CS10A GEG-A F&G PM job Completed
3-MR-51 Filter (B-in service) replacement job planned today and detector inhibit done
for the same job. MLV-19 Main Valve functional testing job also planned today
4-MLV-22 F&G PM Completed and Equipment Room drop down shutter limit switch
replacement job Completed.
7-CS06 GTC C preservation fire start planned today. Please follow-up CS06:
Regarding GTC-C Fire start preservation, discussed with Mr. Vikas. After call
conference, they will take a call to do fire start preservation internally. CS06 GTC A
AOP run, and GG Cranking and CC manual rotation planned today as per LO. GTC B
fire start preservation planned on tomorrow depending on Scrubber DP. CS06 GTC-C
Unit start command given at 14:19 Hrs. from Mark-VI by keeping station
suction/discharge in close condition. Flame On: 14:40 Hrs. Suction strainer DP went
high up to max 0.51 barg after FSNL speed and reduced to 0.44-0.46 barg. Flame
OFF: 15:06hrs.
8-CS05: 125 KVA GEGs change over done from E to D at 08:54 Hrs for tunning job.
As per Mr. Umesh shidkeTuning job postponed to the next week.
9-CS10A: F&G bypassed and station RTU taken into local for GTC-A instrument
maintenance activity. Maintenance job completed and all system normalized.
10-CS04 125KV GEG-4 and DG weekly trial Completed. In HPOC C/R power
disturbed but after few minutes normalized.
11-CS01: PM OF ANTISURGE CONTROL VALVE FOR GTC-B & GTC-C Job
Completed
12-CS02 GTC-A (S/B) L1 recommendation points being attended. RTV Apply for
GTC A GG Centre body. Update-Job Completed
13- CS06 GTC-A AOP preservation completed.
CS06 GTC-B calibration cranking completed.
CS06 GTC-C fire start preservation completed.

As discussed with BOC Team Mr.Aman , Mhaskal SQ will be zero from tomorrow.

SG1 flow started at 20:00 hrs after increase in SG1 pressure.


Ethane increase from 20 TPH to 23 TPH as per clearance from DPOC

In CS-06, After discussion with Sh.Pawan and Mr.Rabba CS06 Station bypass valve
opened at 18:28 Hrs.

ERSS test notification made as per Schedule .

Gas Day 01.11.2021·OT informed that the expected Gas export for sales could be
around 18.50 mmscm against (D-1) schedule of 18.40 mmscm.
Gas Day 02.11.2021·The estimated Gas export for sales as suggested by OT is 18.40
mmscm for the day.