Professional Documents
Culture Documents
Program of Work/ Budget Cost: For Funding
Program of Work/ Budget Cost: For Funding
Location: Linno-C,Rizal,Cagayan
Appropriation: Php 2,000,000.00
Estimated Project Cost: Php 3,000,000.00 Width : 5.0 m
TOTAL 2,288,605.13
Breakdown of Expenditures:
Direct Cost
Labor 70,347.81
Materials 1,168,812.98
VAT(5%) 142,857.14
200 Aggregate Base Course 950,439.04 31.68 3.17 3.17 3.17 3.17 3.17 3.17 3.17 3.17 3.17 3.17
Spl-2 Occupational Safety and Health Program 38,998.29 1.30 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
Spl-3 Mobilization/Demobilization 15,176.95 0.51 0.25
100 99.47
96.21
92.95
90 89.69
86.42
83.16
80 79.90
72.38
70
60
50
47.33
40
30
20
17.48
10
5.15
0-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Name of Project: Construction of Drainage Canal and Extension of Reinforced Concrete Retaining Wall
Location: Poblacion,Rizal,Cagayan
Amount: 3,000,000.00
Formula:
(GRA)x(RDK)
C.D. = + Dl
EAK
Where:
Dh = Reference Duration (Higher)
Dl = Reference Duration (Lower)
Ah = Reference Amount (Higher)
Al = Reference Amount (Lower)
Ap = Appropration, amount to be programmed
Given:
Dh = 27.00 CD
Dl = - CD
Ah = 5,000,000.00
Al = -
Ap = 3,000,000.00
(Dh-Dl) = 27.00
(Ap-Al) = 3,000,000.00
(Ah-Al) = 5,000,000.00
Curing of Concrete = 60.00
C.D. = 76.20 say 77.00
NO. OF PRE-DETERMINED
MONTH SUNDAYS HOLIDAYS
WORKING DAYS UNWORKABLE DAYS
September 20 4 1 5
October 22 4 0 5
November 3 4 1 5
45 12 2 15
32.00
C.D. = 74
Justification:
The 74 CD - project duration is based from the computed number of calendar days using the formula given in the
D.O. 141 s. 2014, plus the total number of sundays, holidays and pre-determined unworkable days.
2.57 10 2.5 12.5 102.00
TOTAL NO. OF
NO. OF WORKIN PRE-DETERMINED
MONTH SUNDAYS HOLIDAYS
DAYS UNWORKABLE DAYS
G DAYS
August 19 5 2 5
30 September 20 4 1 5
31 October 22 4 0 5
13 November 20 4 1 5
December 19 5 2 5
January 19 5 2 5
February 18 4 1 5
March 22 4 0 5
April 17 5 3 5
May 21 4 1 5
June 20 4 1 5
July 21 5 0 5
August 20 4 2 5
September 20 4 1 5
October 22 4 0 5
November 4 1 1 1
74 304 40 12 45
74
MARK-UPS IN
ESTIMATED TOTAL MARK-UP TOTAL
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT TOTAL COST UNIT COST
DIRECT COST INDIRECT COST
OCM PROFIT % VALUE
1 2 3 4 5 6 7 8 9 10 11 12 13
(5) X (8) 5%((5)+(9)) (9)+(10) (5)+(11) (12)/(3)
102(2)b Roadway Excavation (Surplus Common) 1,500.00 cu.m. 329397.475 15% 10% 25% 82349.37 20,587.34 102,936.71 432,334.19 288.22
104(1)a Embankment from Borrow 1690.50 cu.m. 801,321.47 15% 10% 25% 200330.37 50,082.59 250,412.96 1,051,734.42 622.14
105(1) Subgrade Preparation 7000.00 sq.m. 389,574.94 15% 10% 25% 97393.74 24,348.43 121,742.17 511,317.11 73.05
200 Aggregate Base Course 1610.00 cu.m. 724,144.03 15% 10% 25% 181036.01 45,259.00 226,295.01 950,439.04 590.33
Spl-2 Occupational Safety and Health Program all L.S. 29,712.98 15% 10% 25% 7428.25 1,857.06 9,285.31 38,998.29 38,998.29
Spl-3 Mobilization/Demobilization all L.S. 14,454.24 0% 0% 0% 0.00 722.71 722.71 15,176.95 15,176.95
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 319,060.50
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
B. SUB-TOTAL P 10,336.98
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
MATERIAL
C. SUB-TOTAL P -
SUMMARY:
A Equipment P 319,060.50
B Labor 10,336.98
C Materials -
D TOTAL DIRECT COST 329,397.48
DIRECT UNIT COST 219.60
E OCM 15% of D 49,409.62
F Contractor's Profit 10% of D 32,939.75
G VAT 5% of (D+E+F) 20,587.34
H Total Cost (D+E+F+G) 432,334.19
Unit Cost H/Quantity P 288.22
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 201,470.25
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
MATERIAL
C. SUB-TOTAL P 583,500.00
SUMMARY:
A Equipment P 201,470.25
B Labor 16,351.22
C Materials 583,500.00
D TOTAL DIRECT COST 801,321.47
DIRECT UNIT COST 474.01
E OCM 15% of D 120,198.22
F Contractor's Profit 10% of D 80,132.15
G VAT 5% of (D+E+F) 50,082.59
H Total Cost (D+E+F+G) 1,051,734.42
Unit Cost H/Quantity P 622.14
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 360,330.70
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
MATERIAL
C. SUB-TOTAL P -
SUMMARY:
A Equipment P 360,330.70
B Labor 29,244.24
C Materials -
D TOTAL DIRECT COST 389,574.94
DIRECT UNIT COST 55.65
E OCM 15% of D 58,436.24
F Contractor's Profit 10% of D 38,957.49
G VAT 5% of (D+E+F) 24,348.43
H Total Cost (D+E+F+G) 511,317.11
Unit Cost H/Quantity P 73.05
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 154,128.65
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
C. SUB-TOTAL P 555,600.00
SUMMARY:
A Equipment P 154,128.65
B Labor 14,415.38
C Materials 555,600.00
D TOTAL DIRECT COST 724,144.03
DIRECT UNIT COST 449.78
E OCM 15% of D 108,621.60
F Contractor's Profit 10% of D 72,414.40
G VAT 5% of (D+E+F) 45,259.00
H Total Cost (D+E+F+G) 950,439.04
Unit Cost H/Quantity P 590.33
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
EQUIPMENT
-
-
-
A. SUB-TOTAL P -
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
B. SUB-TOTAL - man-hour P -
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
Basic PPE
Hardhat 10.00 pcs 200.00 2,000.00
Safety Shoes 10.00 pcs 1,500.00 15,000.00
Working Gloves 20.00 pcs 148.96 2,979.17
MATERIAL
C. SUB-TOTAL P 29,712.98
SUMMARY:
A Equipment P -
B Labor -
C Materials 29,712.98
D TOTAL DIRECT COST 29,712.98
DIRECT UNIT COST 29,712.98
E OCM 15% of D 4,456.95
F Contractor's Profit 10% of D 2,971.30
G VAT 5% of (D+E+F) 1,857.06
H Total Cost (D+E+F+G) 38,998.29
Unit Cost H/Quantity P 38,998.29
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
-
-
EQUIPMENT
-
-
-
-
-
-
-
A. SUB-TOTAL P 14,454.24
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
B. SUB-TOTAL - man-hour P -
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
MATERIAL
C. SUB-TOTAL P -
SUMMARY:
A Equipment P 14,454.24
B Labor -
C Materials -
D TOTAL DIRECT COST 14,454.24
DIRECT UNIT COST 14,454.24
E OCM 0% of D -
F Contractor's Profit 0% of D -
G VAT 5% of (D+E+F) 722.71
H Total Cost (D+E+F+G) 15,176.95
Unit Cost H/Quantity P 15,176.95
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
EQUIPMENT
A. SUB-TOTAL P 32,152.00
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
Aggregate Surface Course 1.15 529.00 cu.m. 300.00 158,700.00
MATERIAL
C. SUB-TOTAL P 158,700.00
SUMMARY:
A Equipment P 32,152.00
B Labor 1,679.44
C Materials 158,700.00
D TOTAL DIRECT COST 192,531.44
DIRECT UNIT COST 481.33
E OCM 15% of D 28,879.72
F Contractor's Profit 10% of D 19,253.14
G VAT 5% of (D+E+F) 12,033.22
H Total Cost (D+E+F+G) 252,697.52
Unit Cost H/Quantity P 631.74
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 864,794.38
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
2.5
C. SUB-TOTAL P 4,163,900.00
SUMMARY:
A Equipment P 864,794.38
B Labor 187,403.29
C Materials 4,163,900.00
D TOTAL DIRECT COST 5,216,097.66
DIRECT UNIT COST 1,043.22
E OCM 15% of D 782,414.65
F Contractor's Profit 10% of D 521,609.77
G VAT 5% of (D+E+F) 326,006.10
H Total Cost (D+E+F+G) 6,846,128.18
Unit Cost H/Quantity P 1,369.23
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
EQUIPMENT
-
-
-
A. SUB-TOTAL P -
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
4' x 8' Tarpuline w/ Complete Letterings of Project Profile 2.00 pcs. 1,500.00 3,347.00
1" x 2" x 8' (Frame) 20.00 bd.ft. 38.00 760.00
MATERIAL
C. SUB-TOTAL P 4,757.00
SUMMARY:
A Equipment P -
B Labor 1,900.64
C Materials 4,757.00
D TOTAL DIRECT COST 6,657.64
DIRECT UNIT COST 6,657.64
E OCM 15% of D 998.65
F Contractor's Profit 10% of D 665.76
G VAT 5% of (D+E+F) 416.10
H Total Cost (D+E+F+G) 8,738.15
Unit Cost H/Quantity P 8,738.15
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
0.5
A. SUB-TOTAL P 16,571.49
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
B. SUB-TOTAL P 25,177.06
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
Reinforcing Steel Bar(w/ 5% wastage) 1.05
3,858.00 kgs. 40.00 154,320.00
MATERIAL
0.015
Tie Wire # 16 56.00 kgs. 80.00 4,480.00
C. SUB-TOTAL P 158,800.00
SUMMARY:
A Equipment P 16,571.49
B Labor 25,177.06
C Materials 158,800.00
D TOTAL DIRECT COST 200,548.55
DIRECT UNIT COST 54.59
E OCM 12% of D 24,065.83
F Contractor's Profit 8% of D 16,043.88
G VAT 5% of (D+E+F) 12,032.91
H Total Cost (D+E+F+G) 252,691.17
Unit Cost H/Quantity P 68.78
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 10,492.00
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
B. SUB-TOTAL P 94,999.57
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
C. SUB-TOTAL P 433,630.66
SUMMARY:
A Equipment P 10,492.00
B Labor 94,999.57
C Materials 433,630.66
D TOTAL DIRECT COST 539,122.23
DIRECT UNIT COST 5,901.72
E OCM 12% of D 64,694.67
F Contractor's Profit 8% of D 43,129.78
G VAT 5% of (D+E+F) 32,347.33
H Total Cost (D+E+F+G) 679,294.01
Unit Cost H/Quantity P 7,436.17
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 77,005.97
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
SUMMARY:
A Equipment P 77,005.97
B Labor 21,219.31
C Materials 206,750.00
D TOTAL DIRECT COST 304,975.27
DIRECT UNIT COST 3,812.19
E OCM 12% of D 36,597.03
F Contractor's Profit 8% of D 24,398.02
G VAT 5% of (D+E+F) 18,298.52
H Total Cost (D+E+F+G) 384,268.84
Unit Cost H/Quantity P 4,803.36
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 62,561.24
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
MATERIAL
C. SUB-TOTAL - P -
SUMMARY:
A Equipment P 62,561.24
B Labor 3,779.81
C Materials -
D TOTAL DIRECT COST 66,341.05
DIRECT UNIT COST 234.01
E OCM 12% of D 7,960.93
F Contractor's Profit 8% of D 5,307.28
G VAT 5% of (D+E+F) 3,980.46
H Total Cost (D+E+F+G) 83,589.73
Unit Cost H/Quantity P 294.85
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) Qty Unit Unit Cost Total Cost (Pesos)
EQUIPMENT
-
-
A. SUB-TOTAL P -
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
B. SUB-TOTAL P -
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
Transhipment of Construction Materials Lump Sump 694822.03 694,822.03
MATERIAL
C. SUB-TOTAL P 694,822.03
SUMMARY:
A Equipment P -
B Labor -
C Materials 694,822.03
D TOTAL DIRECT COST 694,822.03
DIRECT UNIT COST 694,822.03
E OCM 0% of D -
F Contractor's Profit 0% of D -
G VAT 5% of (D+E+F) 34,741.10
H Total Cost (D+E+F+G) 729,563.13
Unit Cost H/Quantity P 729,563.13
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL P 80,982.16
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
LABOR
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
MATERIAL
C. SUB-TOTAL - P -
SUMMARY:
A Equipment P 80,982.16
B Labor 4,255.90
C Materials -
D TOTAL DIRECT COST 85,238.05
DIRECT UNIT COST 148.24
E OCM 12% of D 10,228.57
F Contractor's Profit 8% of D 6,819.04
G VAT 5% of (D+E+F) 5,114.28
H Total Cost (D+E+F+G) 107,399.95
Unit Cost H/Quantity P 186.78
EMBANKMENT ITEM 200 SUBGRADE PREPARATION
STATION DIST.
Area Volume Area Volume Length Area
0 + 0 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 20 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 40 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 60 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 80 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 100 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 120 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 140 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 160 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 180 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 200 1.00 2.17 8.00
20 20.00 43.40 160.00
+ 220 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 240 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 260 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 280 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 300 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 320 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 340 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 360 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 380 1.00 2.17 8.00
20 20.00 43.40 160.00
+ 400 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 420 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 440 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 460 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 480 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 500 1.00 2.17 8.00
20 20.00 43.40 160.00
+ 520 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 540 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 560 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 580 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 600 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 620 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 640 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 660 1.00 2.17 8.00
20 20.00 43.40 160.00
+ 680 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 700 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 720 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 740 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 760 1.00 2.17 8.00
20 20.00 43.40 160.00
+ 780 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 800 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 820 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 840 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 860 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 880 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 900 1.00 2.17 8.00
20 15.00 43.40 160.00
+ 920 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 940 0.50 2.17 8.00
20 10.00 43.40 160.00
+ 960 0.50 2.17 8.00
20 15.00 43.40 160.00
+ 980 1.00 2.17 8.00
20 15.00 43.40 160.00
1 + 0 0.50 2.17 8.00
500.00
FURNISHING OF AGGREGATES:
QUARRY SITE: MATALAG RIVER BED,MAUANAN,RIZAL, CAGAYAN
1. STOCKPILING AND LOADING:
500 cu.m./day
DUMP TRUCK
2. HAULING COST ROAD
TERRAIN CONDITION TRAVEL SPEED
CONDITION
(KPH)
COMPUTATION OF CYCLE TIME
Loaded Empty
Terrain = Rolling FLAT Paved 40 60
Unpaved 30 50
Road Conditionn = Paved ROLLING Paved 30 40
Unpaved 25 30
MOUNTAINOUS Paved 25 30
Unpaved 15 20
Loading Time 5 min
Unloading Time 3 min
Average Hauling Distance = 3 km Allowance for Delay 2 min
1. Fine Aggregates :
Screening = P( 13,864.0 + 470.08 + 361.96 ) = P 73.48 /cu.m.
P 200 cu.m./day
Washing = P( 13,864.0 + 470.08 + 361.96 + 305.00 = P 50.00 /cu.m.
2. Coarse Aggregates :
Screening = P( 13,864.0 + 470.08 + 361.96 ) = P 97.97 /cu.m.
P 150 cu.m./day
Washing = P( 13,864.0 + 470.08 + 361.96 + 305.00 = P 50.00 /cu.m.
P 300 cu.m./day P 147.97 /cu.m.
3. Subbase Coarse
= P( 13,864 + 470.08 + 361.96
Screening = P 73.48 /cu.m
200 cu.m./day
4. Base Coarse
= P( 13,864 + 470.08 + 361.96
Screening = P 73.48 /cu.m
200 cu.m./day
P( 13,864 470.08 361.96
Blending = + = P 29.39 /cu.m
cu.m./day
P( 500 102.87 /cu.m
5. Surface Coarse
= P( 13,864 + 470.08 + 361.96
Screening = P 97.97 /cu.m
150 cu.m./day
P( 13,864 470.08 361.96
Blending = + = P 29.39 /cu.m
cu.m./day
P( 500 127.36 /cu.m
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
SUMMARY:
A Equipment P 2,804.66
B Labor 4,486.56
C Materials 26,831.68
D TOTAL DIRECT COST 34,122.89
DIRECT UNIT COST 2,676.31
E OCM 15% of D 5,118.43
F Contractor's Profit 10% of D 3,412.29
G VAT 5% of (D+E+F) 2,132.68
H Total Cost (D+E+F+G) 44,786.29
Unit Cost H/Quantity P 3,512.65
Project: Opening and Regravelling of Linno-C FMR
Location: Linno-C,Rizal,Cagayan
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
One Bagger Mixer 1.00 1 131.00 172.00 22,532.00
Concrete Vibrator 0.50 1 65.50 91.25 5,976.88
Water Truck/Pump (16000 L) 0.05 1 6.55 2,450.00 16,047.50
Backhoe (wheel type .28 cu.m) 0.10 1 13.10 1,537.00 20,134.70
Bar cutter, Single phase 0.05 1 6.55 219.75 1,439.36
Bar bender 0.05 1 6.55 351.50 2,302.33
Minor Tools (5% of labor) 6,398.43
A. SUB-TOTAL , EQUIPMENT P 74,831.20
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
Construction Foreman 1 1 131.00 81.30 10,650.30
Skilled Laborer 1 4 131.00 58.76 30,790.24
Laborer 1 8 131.00 45.25 47,422.00
Installation/Removal of Forms
Skilled Laborer 1 2 131.00 58.76 15,395.12
Laborer 1 4 131.00 45.25 23,711.00
B. SUB-TOTAL, LABOR - man-hour P 127,968.66
C. Name and Description of Material Qty Unit Unit Cost Total Cost (Pesos)
Lumber, Good -4 uses 20.00 2,616.00 bd.ft 38.00 99,408.00
Marine Plywood (1/2"x4'x8')-4 uses 0.48 63.00 pcs 725.00 45,675.00
Assorted CWN (1kg/100bd.ft of lumber) 0.188 25.00 kg 65.00 1,625.00
Cement 9.50 1,243.00 bags 300.00 372,900.00
Sand 0.50 66.00 cu.m 302.72 19,979.52
Gravel 1.00 131.00 cu.m 327.21 42,864.51
Weepholes(PVC), 50mm dia. 0.21 28.00 ln.m 235.00 6,580.00
Filter cloth 0.01500 2.00 sq.m 160.00 320.00
Granular Filter 0.0160 3.00 cu.m 285.07 855.21
Reinforcing Steel bar 26.0300 3,405.00 kg 40.00 136,200.00
#16 G.I tie wire (2% of RSB) 0.0200 3.00 kg 80.00 240.00