ID WBS Task Mode Task Name Duration Start 1 2 3 4 5 6 7 8: Project: Project1 Date: Sat 19/6/21

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID WBS Task Task Name Duration Start

Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022


Mode Aug Sep Oct Nov Dec Jan Feb Mar
1 1 Construction of 91 days Wed 1/9/21 Construction of Electrical Sub Station
Electrical Sub
2 1.1 Station
Temporary Works 15 days Wed 1/9/21 Temporary Works

3 1.1.1 Retaining 5 days Wed 1/9/21


System Retaining System
4 1.1.2 Soil 7 days Wed 8/9/21
Improvement Soil Improvement
5 1.1.3 Excavation 3 days Tue 21/9/21
Excavation
6 1.2 Permanent Works 65 days Sun 26/9/21 Permanent Works

7 1.2.1 Piling 11 days Sun 26/9/21


Piling
8 1.2.2 Sub Structure 23 days Mon Sub Structure and Super Structure Works
and Super 11/10/21
Structure
9 1.2.2.1 Works
Pile Cap and 4 days Mon
Stump 11/10/21 Pile Cap and Stump
10 1.2.2.2 Ground 9 days Sun
Beam and 17/10/21 Ground Beam and Slab
11 1.2.2.3 Slab
Column 4 days Mon
1/11/21 Column
12 1.2.2.4 Roof Beam 6 days Mon
and Flat Roof 8/11/21 Roof Beam and Flat Roof
13 1.2.3 Architecture 22 days Tue Architecture Works
Works 16/11/21
14 1.2.3.1 Brick laying 7 days Tue
16/11/21 Brick laying
15 1.2.3.2 Plastering 6 days Thu
25/11/21 Plastering
16 1.2.3.3 Tiling 5 days Sun 5/12/21
Tiling
17 1.2.3.4 Painting 4 days Sun
12/12/21 Painting
18 1.2.4 M&E Works 6 days Thu M&E Works
16/12/21
19 1.2.4.1 Plumbing 2 days Thu
16/12/21 Plumbing
20 1.2.4.2 Lighting 2 days Thu
16/12/21 Lighting
21 1.2.4.3 Ventilation 2 days Mon
20/12/21 Ventilation
22 1.2.4.4 Fire 2 days Wed
Protection 22/12/21 Fire Protection
23 1.2.5 External Works 8 days Sun External Works
19/12/21
24 1.2.5.1 Drains 5 days Sun
19/12/21 Drains
25 1.2.5.2 Access Road 4 days Thu
23/12/21 Access Road
26 1.3 Testing and 11 days Wed Testing and Commissioning
Commissioning 29/12/21
27 1.3.1 RI Inspection 4 days Wed
29/12/21 RI Inspection
28 1.3.2 Certificate of 0 days Sun 16/1/22
Statutory 16/1
Completion
(CSC)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Critical
Date: Sat 19/6/21
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1