Professional Documents
Culture Documents
Index: Construction Quantity Surveying: A Practical Guide For The Contractor's QS, Second Edition. Donald Towey
Index: Construction Quantity Surveying: A Practical Guide For The Contractor's QS, Second Edition. Donald Towey
Index
AL
a elemental bills 74
RI
Accounts department 179, 246, 270, 301, errors in a bill of quantities 235
302, 307, 310, 312 operational bills 73
TE
Accruals 310, 312, 313, 353, 354 preambles 62, 63, 64
Additional works 283, 303, 304, 305, trade bill of quantities (BQ) 41
349, 352 Building Control Body (BCB) 186
MA
Advanced payment bond 218, 219 Building Information Modelling (BIM)
Apprentices 273 31, 32
Architect 6, 7, 47, 159 Building inspector 17
Architect’s Instruction (AI) 222, 234 Building Regulations 15, 17
D
TPC2005 160 Certificates
Association of Cost Engineers certificate of making good
(ACostE) 45 346, 347
CO
Construction Quantity Surveying: A Practical Guide for the Contractor’s QS, Second Edition. Donald Towey.
© 2018 John Wiley & Sons Ltd. Published 2018 by John Wiley & Sons Ltd.
362 Index
Cost plan/planning 42, 43, 74, 132, 142 document register 46, 198, 199
Cost to complete 335, 354 material supply registers 197,
Cost value reconciliations (CVRs) new and revised information 279,
313, 314 280, 281
Council on Tall Buildings 241 plant hire register 197
reading file 281, 282
d
Defects e
latent 347 Earned Value Management (EVM) 190
patent 345 Economic cycle 25, 26
defects liability/rectification period Edited and bespoke forms of contract 163,
226, 280, 345, 346, 348, 352, 354 164, 165
Design creep 95 Employer’s agent (see Client’s agent)
Design manager 179, 199, 276, 280 Entire agreement 225, 284
Design team 4, 5 Environmental Impact Assessment
Development team 5 (EIA) 16
Dispute resolution Estimating
Adjudication 158 Build Cost Information Service
Adjudicator Nominating Body (BCIS) 132, 295
(ANB) 172, 173 buildability 129
Alternative Dispute Resolution CIOB Code of Estimating Practice
(ADR) 166, 167 (COEP) 132
Arbitration 173, 174 composite rate 74, 286, 287, 288
Award 173 consultants’ fees 127, 128, 178,
Conciliation 169 276, 277
Damages 166, 239, 323 contractor’s margin 81, 179, 187
Dispute Adjudication Board cost centres or cost codes 71, 300, 301,
(DAB) 170 306, 309,
Dispute Board (DB) 169, 170 cost planned tenders 142–146
Dispute Resolution Board database 62, 122, 129
(DRB) 170 director’s adjustment 67, 147
Dispute Resolution Board Foundation employer’s requirements (see
(DRBF) 170 preliminaries pricing)
Early neutral evaluation 170, 171 estimate and quotation 116
Expert appraisal 172 estimating software 30, 72, 73
Expert determination 171, 172 estimator 39
Expert witness 171 first principles 129
Litigation 166, 167, 323 Gross Internal Floor Area (GIFA) 143
Mediation 168, 169 labour all‐in rate 122, 123, 124
Negotiation 168 labour flat rate 122
Technology and Construction Court labour constant 129
(TCC) 167 materials and trade scheduling
Unliquidated damages 351 120, 121
Divergences 224 materials, conversion factors
Document control 125, 126
document communication materials, equal and approved 124
systems 29 materials, wastage 125
364 Index